Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 07/29/2019 |
PLUMBING - ROUGH, SOIL |
|
Approved |
|
| 03/14/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
Red Hilti Boxes Approved For Level1 |
| 03/08/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
SLEEVES IN SEEQUENCE 3 EAST SIDE OK |
| 03/07/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
|
| 02/21/2018 |
PLUMBING - ROUGH, SOIL |
|
Not ready for Inspection |
WORK INCOMPLETE. |
| 02/21/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
BASEMENT AREAS AT GL: 4 - 8/A -E (4" - 8" LINES) OK TO COVER PROGRESS AREAS. |
| 02/14/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
GL 8 TO 6.8 / C TO F.5 OK TO COVER LEVEL B2 |
| 02/08/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
8" STORM DRAIN, 4" FLOOR DRAIN WEST OF RAMP WALL; 6" AND 8" DRAIN LINES (SOUTH) TO TIE INTO 8" LINE TO MANHOLE AT GL: G.4/7.3 - 6.7 |
| 02/07/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
STORM DRAIN (8") AT BASEMENT RAMP AREA. OK TO COVER |
| 02/01/2018 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
B1 deck south sleves only |
| 12/20/2017 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
OIL SEPERATOR AND LIFT STATION TANKS OK TO BACKFILL. |
| 12/18/2017 |
PLUMBING - ROUGH, SOIL |
|
Partial Approval |
SOUTH HALF OF TOTAL DRAIN SYSTEM AND DOMESTIC WASTE SYSTEM OK TO COVER (AS MARKED ON PLAN) |