Permit: T08CM00837
Permit Details
Apply Date:
03/13/2008
Applicant:
RAY GARCIA
Description:
HAMPTON INN AND SUITES ORIGINAL C OF O ISSUED 9/15/09
Contractors:
- TROON CONSTRUCTION L L C
Permit Reviews
Permit Number - T08CM00837
Permit Status: C of o
Permit Description: HAMPTON INN AND SUITES ORIGINAL C OF O ISSUED 9/15/09
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/02/2009 | REVISION - - 3RD | 05/05/2009 | COMPLETED |
03/13/2008 | PLANS OK TO SUBMIT - 3RD PARTY | 03/21/2008 | COMPLETED |
03/26/2008 | COMMERCIAL NEW | 05/15/2008 | COMPLETED |
05/23/2008 | RESUBMITTAL | 06/23/2008 | COMPLETED |
07/01/2008 | RESUBMITTAL | 07/28/2008 | COMPLETED |
07/28/2008 | RESUBMITTAL | 09/09/2008 | COMPLETED |
07/30/2009 | REVISION - - 4TH | 08/10/2009 | COMPLETED |
07/30/2009 | REVISION - - 5TH | 09/04/2009 | COMPLETED |
09/09/2008 | RESUBMITTAL | 10/31/2008 | COMPLETED |
10/31/2008 | REVISION - - 1ST | 01/16/2009 | COMPLETED |
12/15/2008 | REVISION - - 2ND | 12/17/2008 | COMPLETED |
12/17/2008 | REVISION - - 2ND | 02/23/2009 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T08CM00837
Permit Status: C of o
Permit Description: HAMPTON INN AND SUITES ORIGINAL C OF O ISSUED 9/15/09
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
03/13/2008 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T08CM00837
Permit Description: HAMPTON INN AND SUITES ORIGINAL C OF O ISSUED 9/15/09
Total Completed Inspections - 46
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2008 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST THRU BLD. TO 5' EXTERIOR ON 8" BUILDING DRAIN. SANITARY DRAINAGE. |
11/05/2008 | PLUMBING - ROOF DRAINS | RRICH | Approved | IVRS - Inspection :* 1. POST AN ADDRESS FOR YOUR JOB SITE 2. WATER TEST ALL RAIN DRAINS FROM 4' BLD. EXTERIOR UP INSIDE BLD. TO 3" AFF |
11/24/2008 | ELECTRIC - UFER | RJIROUDE | Approved | IVRS - Inspection :* |
11/25/2008 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* 4" C-900 PER TUCSON WATER STANDARDS, WITH RESTRAINTS AND NO 90 DEG. TURNS YET, PER INITIAL PAGE 1 OF 1 SITE PLAN IN TRAILER, COMPLETION WITH HYDROSTATIC TEST LATER DATE - OK TO COVER THIS SECTION. 1. EXPOSE COPPER BLD. RISER AND PROVIDE TEST ON THIS PIPING AT LATER DATE. |
12/05/2008 | STEM WALL/RETAINING WALL | GDABBS | Approved | IVRS - Inspection :* BLDG. CENTER SPREAD FOOTING @ GRID LINES A TO K/6 TO 7 OK |
12/12/2008 | FRAMING | GDABBS | Approved | IVRS - Inspection :* NO SUPERINTENDENT ON SITE DON'T KNOW WHAT TO LOOK AT |
12/16/2008 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* OK TO PROCEED |
12/22/2008 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* 1. OK U.G @ ELEVATOR MACHINE ROOM AND PIT 2. OK 6 FLOOR BOXES DINING AREA AND MEETING ROOM |
12/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* SPREAD FOOTING @ K TO N/6 TO 7 OK SPECIAL INSPECTION |
12/23/2008 | BUILDING PRE-SLAB | GDABBS | Approved | IVRS - Inspection :* K TO N/4 TO 6 AND K TO N/7 TO 10 -- OK SPECIAL INSPECTED |
12/23/2008 | PLUMBING - PRE SLAB | RRICH | Approved | IVRS - Inspection :* CENTER, CENTER FOOTING AREA OK |
12/31/2008 | ELECTRIC - INTERMEDIATE | RMORENO | Approved | IVRS - Inspection :* 1) FIRST FLOOR CORRIDOR HALLWAY WEST BLDG AND EAST BLDG OK FOR CEILING |
01/09/2009 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | Pressure test OK - still need flush |
01/27/2009 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* OK TO DRY IN ROOF AREA |
04/02/2009 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* PLEASE CALL IN 03055 FOR APPROVAL |
04/06/2009 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
05/07/2009 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. JIROUDEK |
07/06/2009 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* 1) 3RD FLOOR COMPLETE-OK TO SET CEILING TILES |
07/30/2009 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
07/30/2009 | NPPO - FINAL | ACONNOR | Approved | |
08/21/2009 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :* |
08/21/2009 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
08/21/2009 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
08/27/2009 | ZONING - FINAL | ACONNOR | Approved | |
08/27/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
08/27/2009 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
08/27/2009 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
08/27/2009 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
08/27/2009 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
08/31/2009 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* 1) OK FOR FINAL 2) LEFT GAS CARD 3) WILL CHECK AIR BALANCE ON POOL HEATER INSPECTION |
08/31/2009 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | |
08/31/2009 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
08/31/2009 | RIGHT OF WAY - FINAL | MCASTRO | Approved | PER EMAIL |
09/01/2009 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
09/01/2009 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
09/01/2009 | FIRE - FINAL | LTHOMAS | Approved | |
09/10/2009 | FIREWALL/FIREBARRIER/FIRESTOP | GDABBS | Approved | IVRS - Inspection :* |
09/11/2009 | ENGINEERING - FINAL | DROBERTS | Approved | THE SITE HAS BEEN CHECKED, THE PREVIOUS NOTED COMMENTS HAVE BEEN COMPLETED AT THIS TIME. THE DEVELOPER WILL BE MAKING SOME REPAIRS TO SIDEWALKS THAT HAVE BEEN DAMAGED RECENTLY BY THEIR OWN EQUIPMENT, I WILL RE-INSPECT THIS WORK PRIOR TO THE 9/18/09. THIS WORK WILL BE HELD AGAINST THE COMPLETION OF THE GRADING PERMIT FOR THIS SITE. |
09/11/2009 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
09/11/2009 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* |
09/14/2009 | BUILDING - PROGRESS | GDABBS | Approved | IVRS - Inspection :* |
09/15/2009 | PERMIT FINALED | LJACKSON | Approved | |
09/15/2009 | PLUMBING - PROGRESS | RRICH | Approved | |
09/15/2009 | BUILDING - FINAL | GDABBS | Approved | |
09/15/2009 | PLUMBING - FINAL | RRICH | Approved | |
09/15/2009 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |