Permit Details

Status:
Inspections
Type:
Development Package
Address:
3400 E ZOO CT
Address NEW:
3400 E ZOO CT
Apply Date:
05/19/2023
Applicant:
Description:
**Restricted Record-Revision 1 -New Asia Exhibit, Reid Park Zoo

Permit Reviews

Permit Number - TD-DEV-0523-00249
Permit Status: Inspections
Permit Description: **Restricted Record-Revision 1 -New Asia Exhibit, Reid Park Zoo
Start Date Submittal Complete Date Status  
11/06/2024 DEVELOPMENT PACKAGE NEW REVISION v.1 01/02/2025 APPROVED Review Details
09/11/2023 DEVELOPMENT PACKAGE NEW v.2 10/12/2023 REQUIRES RESUBMIT Review Details
05/22/2023 DEVELOPMENT PACKAGE NEW v.1 06/28/2023 REQUIRES RESUBMIT Review Details
11/14/2023 DEVELOPMENT PACKAGE NEW v.3 11/15/2023 REQUIRES RESUBMIT Review Details
11/17/2023 DEVELOPMENT PACKAGE NEW v.4 01/16/2024 APPROVED Review Details

Outstanding Inspections

Permit Status: Inspections
Permit Number: TD-DEV-0523-00249
Permite Description: **Restricted Record-Revision 1 -New Asia Exhibit, Reid Park Zoo
Total Outstanding Inspections - 15
Last Inspection Date Description Inspector Results Comments
11/13/2023 COT - SITE - Zoning Intermediate N/A Not Ready
11/13/2023 SITE - Zoning Violation N/A Not Ready
11/13/2023 SITE - Zoning Compliance N/A Not Ready
11/13/2023 City of Tucson (COT) Planning and Development Services Engineering (ENGR) Zoning Compliance Inspection N/A Not Ready
04/26/2024 PDSD Site/Engineering Division - NPPO N/A Not Applicable
11/19/2024 PDSD Site/Engineering Division - Landscaping N/A Not Ready
12/30/2024 COT - ENGR - Stormwater N/A Partial Pass continued installation of the roof drainage pipeline into the vault, 12/30/24.
12/13/2024 ENGR - Drainage Structures N/A Partial Pass Vault looked at on 12/13/2024 good to backfill
08/21/2024 SITE - Stormwater Follow-up N/A Complete (Recurring) Pipe in grassy area looks good, backfill. SWPPP is being maintained throughout.
07/15/2025 SITE N/A Canceled
07/28/2025 For trash and recycling enclosures N/A Partial Pass 07/28/25, top of block at side entrance to west wall good to grout.
10/14/2025 SITE - SWPPP Correction Notice N/A Re-inspection required 10/14/25
The majority of the wattle around the perimeter is not lapped sufficiently. Laps should be 2’ and placed side by side. Stake wattle to SWPPP plan. Sand bags to used if staking is not practical, or not snug up to fencing. Approximately 50% of wattle is breaking down or missing/ non functional and needs to be replaced.
The many of the inlets on SWPPP plan are either uncovered, or covered with plastic but it is breaking down with rips and holes or it isn’t sealed around pipes. No Filter Fabric on any inlets. Plastic can be used to keep out water on as needed basis. Pipes that are also lifted above grade also do not need filter fabric.
10/17/2025 N/A Partial Pass Okay to grout final course on SW site wall.
08/04/2025 N/A Partial Pass Contractor will call in for reinspection on the flat work sidewalk. The 10 inch storm waterline that was installed is good to backfill.
08/07/2025 N/A Partial Pass Contractor continues to install the storm drain good to backfield for the next hundred feet

Completed Inspections

Permit Status: Inspections
Permit Number: TD-DEV-0523-00249
Permit Description: **Restricted Record-Revision 1 -New Asia Exhibit, Reid Park Zoo
Total Completed Inspections - 3
Date Description Inspector Results Comments
04/26/2024 PDSD Engineering Division Pre-Construction SITE Passed Jesse with Lloyd. Parking lot demo in progress. Temporary fencing and stormwater controls installed as needed. Five enclosures to be built. Schedule inspections for underground, stormwater piping, and Stormwater follow up.
01/15/2025 COT - ENGR - Stormwater Passed Drainage pipe between tiger life and panda buildings, passed on 01/14/25, same area the next 60' of pipe passed on 01/15/25,
09/24/2025 SITE - Stormwater Setup and Controls Passed 9/24/25

Wattle at perimeter is beginning to break down and will need to be replaced in areas where it is torn up. Lap joints minimum of 2'. Stake it correctly and where it goes over hardscape use sandbags per detail.

Inlets protection needs to be checked. Filter fabric should be used per details and needs to be secured all around under grates. Currently plastic sheet is used but much of it is frayed with holes at edges. Some are being covered with dirt. If Superintendent prefers plastic sheet on some inlets that are not connected that is ok, check with him.

Trackout needs to be reconditioned and have rock added per plan.

Trackout
Inlet protection fabric
Wattle

Scheduled Inspections

Scheduled Inspections - TD-DEV-0523-00249
Status: Inspections
Description: **Restricted Record-Revision 1 -New Asia Exhibit, Reid Park Zoo
Scheduled Date Description Entered By Entered Date
12/05/2025 Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .