Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - TD-DEV-0523-00249
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2025 | Partial Pass | drainage pipe looked at in 3 separate areas, 01/21/25 | ||
| 01/22/2025 | Partial Pass | Section adjacent to yesterday’s pipe location, passed good to backfill. 01/22/25 | ||
| 01/24/2025 | Partial Pass | Section again on the southwest corner of the exhibit. okay to backfill. 01/24/25 | ||
| 07/11/2025 | Partial Pass | 7/11/25 At the far west end of the site I looked at one 4" iron pipe and one 12" iron approximately 100' length. These run parallel between the pump vault to the south sloping up to the backwater valve vault to the north. Slope is correct. Pressure test has held water at 100 lbs for an hour in both pipes. The dials read 100 lbs. This complies. Originally it was designed using HDPE but has been revised to ductile iron. Subsequent revision approved. Contractor informed me As-Builts will be submitted for these pipes. Okay to back fill. see details in checklist. | ||
| 07/22/2025 | Partial Pass | Doctor is good to backfill 40 lineal feet of storm drain pipe | ||
| 07/25/2025 | Partial Pass | Drainage pipe (through center of project, from ‘tiger enclosure tie-in’ catch basin to next catch basin upstream is installed correctly and okay to backfill. | ||
| 08/07/2025 | Partial Pass | Contractor continues to install the storm drain good to backfield for the next hundred feet | ||
| 08/11/2025 | Partial Pass | Contractor is good to to backfill storm drain pipe line Street cluster mines | ||
| 08/18/2025 | Partial Pass | 08/18/25, inspection on the pool drain and drain valve, set pitch to pipe from pool is 12.5% but due to a fiber optics line it will be set at 10%. Please note this on an as built. | ||
| 08/28/2025 | Not Ready | contractor will call inspection when ready | ||
| 08/29/2025 | Partial Pass | 08/29/25, continued underground roof drain system. Passed good to backfill | ||
| 09/04/2025 | Partial Pass | Drain pipe on west side is good to backfill | ||
| 09/08/2025 | Partial Pass | Final leg of drainpipe coming from roof detention pond behind the pavilion to the storm drain. | ||
| 09/12/2025 | Partial Pass | 9/12/25. 4 inch PVC drain pipe runs along the north side of pavilion. Connection to basin to the north will be done later. 3 Y tie ins are in for roof drains. Pipe is bedded and sloped .5 % correctly. OK to leave Y tires open and shade backfill other areas as progress requires. Make sure pipe stays clear of debris. Compact backfill underneath sidewalk areas. okay to backfill. | ||
| 09/23/2025 | Partial Pass | Contract is good to backfill the 4 inch pipe coming off the roof drainage | ||
| 10/10/2025 | Partial Pass | Okay to backfill SD run from CB19-19A | ||
| 11/07/2025 | Partial Pass | Bedding required prior to backfill. Photos sent. Okay for Backfill | ||
| 11/19/2025 | Partial Pass | 11/19/25 - Catch basins 19A, 19B, 19C okay to backfill. | ||
| Scheduled | ||||
| 12/10/2024 | Complete (Recurring) | This was for the 2nd set of pipes and structures installed |