Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/27/2026 | Partial Pass | contractor can pour the sidewalk on the north west side 10 x 40+ or minus | ||
| 05/29/2026 | Re-inspection required | Slab keynote calls for 5” SOG over 4”AB over Vapor Barrier. | ||
| 06/24/2025 | Partial Pass | 06/24/25, Flat to 1%. Sidewalk on the northwest side. Good to pour. | ||
| 06/26/2025 | Partial Pass | 06/26/25, concrete pour on the 1st section on the west end is within tolerance and looks good. 06/26/25, forms for 2nd section of the west end sidewalk are good. |
||
| 07/01/2025 | Partial Pass | 07/01/25, footings for columns passed, these are @ opening in the middle of the perimeter block wall looking at the entrance to the pool building. | ||
| 07/10/2025 | Partial Pass | Sidewalk extension along West side: layout, forms, subgrade, and reinforcement are good, okay to pour. Wall section along West side: Horizontal and Vertical reinforcement is accurate, okay to grout. |
||
| 07/17/2025 | Partial Pass | Contractors good to pull the sidewalk area | ||
| 07/21/2025 | Partial Pass | Contractors good to support the sidewalk. Everything is foreign up correctly and all expansions are in. | ||
| 07/22/2026 | Partial Pass | Okay to pour light pole foundations | ||
| 07/28/2026 | Partial Pass | Sidewalk on north side of Reptile House: 40ft section is good to pour. | ||
| 07/30/2026 | Partial Pass | Flatwork at west side of Reptile House, in front of Aviary, to Tiger Pavilion 1: subgrade, forms, and reinforcement are good. Okay to pour. | ||
| 07/31/2025 | Partial Pass | Contractor for the sidewalk on the west side | ||
| 08/03/2026 | Partial Pass | Okay to pour Concrete Paving 4" at Tiger Pavilion #1 and doorway of Aviary. Expansion material in place at cold joints w/ .5" x 8" slip dowels-Per detail 1 page DD 5.1. Of DP. Take pictures of chairs or dobies being used to keep 6"x6" WWF spaced consistently and correct off of the AB. Thickened edges correct. | ||
| 08/04/2025 | Partial Pass | Contractor will call in for reinspection on the flat work sidewalk. The 10 inch storm waterline that was installed is good to backfill. | ||
| 08/05/2026 | Partial Pass | Flatwork poured in Aviary entryway and Tiger pavilion 1 is good as well as the next large section north of the aviary. Dobies were used successfully to keep wire mesh spacing consistent and the opinion is that it was not any more difficult than not. Track out needs more rock or mat at entrance because it is starting to not function correctly. |
||
| 08/06/2026 | Partial Pass | Next section of 4" Flatwork next to Tiger pavilion 1 towards the Aviary and to the east 80' section of sidewalk extending towards Red Panda is formed correctly. Thickened edge, dowels expansion joints, wire reinforcing and correct slope. Okay to Pour these areas of sidewalk. | ||
| 08/07/2026 | Partial Pass | This is a Lightpost Footers inspection. Light posts- 4 @ 16’ to top of lamp shade. Reinforcement, spacing, dimensions, ground, and conduit clearance correct. Okay to pour footers. Trackout rock is process of being removed for ABC to be placed at entrance and at adjacent fire access road. Contractor will ensure sweeping all sediment at construction entrance daily continues. |
||
| Scheduled | ||||
| 08/20/2025 | Partial Pass | Architect we designed the patio area where we could not get the 2%. Architect is installing a planner to break up the area where we could not get our 2% contractor will as build it on the set up plans. | ||
| 10/23/2025 | Partial Pass | Contractor can pour the ribbon around the sidewalk area | ||
| 10/27/2025 | Partial Pass | Contractor poor the patio area on the north west side | ||
| 11/20/2025 | Not Ready | Rain day contractor did not work today | ||
| 11/24/2025 | Partial Pass | Contractors good to pour the last of the patio slab on the north west side |