Permit: TD-DEV-0523-00249

Parcel: 12620001C


Addresses:

3400 E ZOO CT

Inspection Status: Partial Pass

Inspection History

Date Description Inspector Results Comments
05/27/2026 Partial Pass contractor can pour the sidewalk on the north west side 10 x 40+ or minus
05/29/2026 Re-inspection required Slab keynote calls for 5” SOG over 4”AB over Vapor Barrier.
06/24/2025 Partial Pass 06/24/25, Flat to 1%. Sidewalk on the northwest side. Good to pour.
06/26/2025 Partial Pass 06/26/25, concrete pour on the 1st section on the west end is within tolerance and looks good.

06/26/25, forms for 2nd section of the west end sidewalk are good.
07/01/2025 Partial Pass 07/01/25, footings for columns passed, these are @ opening in the middle of the perimeter block wall looking at the entrance to the pool building.
07/10/2025 Partial Pass Sidewalk extension along West side: layout, forms, subgrade, and reinforcement are good, okay to pour.
Wall section along West side: Horizontal and Vertical reinforcement is accurate, okay to grout.
07/17/2025 Partial Pass Contractors good to pull the sidewalk area
07/21/2025 Partial Pass Contractors good to support the sidewalk. Everything is foreign up correctly and all expansions are in.
07/22/2026 Partial Pass Okay to pour light pole foundations
07/28/2026 Partial Pass Sidewalk on north side of Reptile House: 40ft section is good to pour.
07/30/2026 Partial Pass Flatwork at west side of Reptile House, in front of Aviary, to Tiger Pavilion 1: subgrade, forms, and reinforcement are good. Okay to pour.
07/31/2025 Partial Pass Contractor for the sidewalk on the west side
08/03/2026 Partial Pass Okay to pour Concrete Paving 4" at Tiger Pavilion #1 and doorway of Aviary. Expansion material in place at cold joints w/ .5" x 8" slip dowels-Per detail 1 page DD 5.1. Of DP. Take pictures of chairs or dobies being used to keep 6"x6" WWF spaced consistently and correct off of the AB. Thickened edges correct.
08/04/2025 Partial Pass Contractor will call in for reinspection on the flat work sidewalk. The 10 inch storm waterline that was installed is good to backfill.
08/05/2026 Partial Pass Flatwork poured in Aviary entryway and Tiger pavilion 1 is good as well as the next large section north of the aviary. Dobies were used successfully to keep wire mesh spacing consistent and the opinion is that it was not any more difficult than not.
Track out needs more rock or mat at entrance because it is starting to not function correctly.
08/06/2026 Partial Pass Next section of 4" Flatwork next to Tiger pavilion 1 towards the Aviary and to the east 80' section of sidewalk extending towards Red Panda is formed correctly. Thickened edge, dowels expansion joints, wire reinforcing and correct slope. Okay to Pour these areas of sidewalk.
08/07/2026 Partial Pass This is a Lightpost Footers inspection. Light posts- 4 @ 16’ to top of lamp shade. Reinforcement, spacing, dimensions, ground, and conduit clearance correct. Okay to pour footers.

Trackout rock is process of being removed for ABC to be placed at entrance and at adjacent fire access road. Contractor will ensure sweeping all sediment at construction entrance daily continues.
Scheduled
08/20/2025 Partial Pass Architect we designed the patio area where we could not get the 2%. Architect is installing a planner to break up the area where we could not get our 2% contractor will as build it on the set up plans.
10/23/2025 Partial Pass Contractor can pour the ribbon around the sidewalk area
10/27/2025 Partial Pass Contractor poor the patio area on the north west side
11/20/2025 Not Ready Rain day contractor did not work today
11/24/2025 Partial Pass Contractors good to pour the last of the patio slab on the north west side