Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Commercial Building
Address:
1346 N STONE AV
Address NEW:
1346 N STONE AV
Apply Date:
04/26/2022
Applicant:
Description:
This project is a new construction 4-story (70 unit) apartment building for the Elderly.

Permit Reviews

Permit Number - T22CM03107
Permit Status: Complete
Permit Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
Start Date Submittal Complete Date Status  
04/26/2022 COMMERCIAL - BLDG/FIRE/ZONING/ENG 05/25/2022 COMPLETED Review Details
06/30/2022 RESUBMITTAL 08/11/2022 COMPLETED Review Details
08/23/2022 RESUBMITTAL 09/09/2022 COMPLETED Review Details
10/10/2022 RESUBMITTAL 10/14/2022 COMPLETED Review Details
10/17/2022 RESUBMITTAL 10/19/2022 ACTIVE Review Details
02/27/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 03/01/2024 REQUIRES RESUBMIT Review Details
04/20/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/01/2023 REQUIRES RESUBMIT Review Details
01/12/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/16/2024 APPROVED Review Details
06/26/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.1 06/26/2023 APPROVED Review Details
03/21/2024 BUILDING DEFERRED SUBMITTAL REVIEW v.2 03/25/2024 APPROVED Review Details
06/07/2023 BUILDING DEFERRED SUBMITTAL REVIEW v.2 06/12/2023 APPROVED Review Details

Conditions

Permit Number - T22CM03107
Permit Status: Complete
Permit Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
Date Description Comments
10/19/2022 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.
10/19/2022 SPECIAL INSPECTION FOR CONCRETE IS REQUIRED..
10/19/2022 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED.
10/19/2022 SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED.
10/14/2022 The Wastewater Utility Fee Application #P22WX01597 was approved with the following PCRWRD Condition:ISSUED WITH PCRWRD CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE: THE DSD SITE PSL, THE PCRWRD TYPE III CAPACITY, THE ABANDONMENT OF THE EXISTING ON-SITE PUBLIC SEWER, AND THE NEW PUBLIC SEWER MANHOLE, IS ACCEPTED AND RELEASED BY PCRWRD PER DSD/SITE/HUSSEIN AL ZUBAIDIGerry KoziolPima County DSD-Building Codes/Wastewater Utility Fee201 N Stone Ave Tucson, AZ 85701(520)724-6503
10/14/2022 NEED WASTE WATER RECEIPT
10/19/2022 SHOP DRAWINGS REQUIRED FOR ROOF TRUSSES.
10/19/2022 SHOP DRAWINGS REQUIRED FOR FLOOR TRUSSES.
10/20/2022 WATER DISINFECTION REPORT REQUIRED
03/01/2024 ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED.
01/12/2024 SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED.
02/01/2024 AIR BALANCE REPORT REQUIRED
02/01/2024 SHOP DRAWINGS REQUIRED FOR ALARM.
02/01/2024 SHOP DRAWINGS REQUIRED FOR SPRINKLER.
02/01/2024 WATER DISINFECTION REPORT REQUIRED
01/12/2024 SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED.
01/12/2024 SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED.
01/12/2024 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.

Outstanding Inspections

Permit Status: Complete
Permit Number: T22CM03107
Permite Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
Total Outstanding Inspections - 17
Last Inspection Date Description Inspector Results Comments
10/19/2022 COT - LCME - Mechanical Final N/A Re-inspection required {Activity date: 10/19/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION}
10/19/2022 COT - LCPL - Plumbing Final N/A Re-inspection required {Activity date: 10/19/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION}
08/24/2023 COT - HCBU - Exterior Clips/Sheathing N/A Partial Pass Roof level parapet walls sheathing.
08/24/2023 COT - HCBU - Framing N/A Partial Pass Roof area crickets (5) set to roof drains.
10/24/2023 COT - HCBU - Interior Shear Bracing N/A Not Ready Level One corridor.

Level 2 all floor units demising walls. Okay to proceed progress areas. 9/22/2023

10/24/23: not ready
03/16/2023 COT - HCPL - Rough Soil N/A Partial Pass Main sewer lines and laterals for ten units at West end of site. waste lines at 2” - 8”. Ok to cover progress areas. Excavation/layout/rebar: East stairwell footing, elevator/sump pump footing. Ok to place concrete in progress areas.
08/31/2023 COT - HCPL - Plumbing Progress N/A Partial Pass Waste and vent lines in laundry rooms on Levels #1 and 2: 2 1/2” - 4” lines.
08/31/2023 COT - HCBU - Building Progress N/A Partial Pass East shear walls on levels #1 & #2 (except for room 110). Ok to,tape progress areas.
11/28/2023 COT - HCPL - Plumbing Above Ceiling N/A Partial Pass 1st floor corridor okay to proceed progress areas. 11/28/2023
11/28/2023 COT - HCBU - Building Above Ceiling N/A Partial Pass 1st floor corridor okay to proceed progress areas. 11/28/2023
11/28/2023 COT - HCEL - Electrical Above Ceiling N/A Partial Pass 1st floor corridor okay to proceed progress areas. 11/28/2023
11/28/2023 COT - HCME - Mechanical Above Ceiling N/A Partial Pass 1st floor corridor okay to proceed progress areas. 11/28/2023
09/21/2023 COT - HCEL - Electrical Progress N/A Partial Pass Partial pass. Inspection was for electrical clearance. 9/21/2023
12/20/2023 COT - HCBU - Firewall/Fire Barrier/Firestop N/A Partial Pass 12/20/23: 4th floor maintenance room east wall firewall/ fire barrier.
04/20/2023 COT - HCEL - Electrical Underground N/A Partial Pass Electric conduit (3”) from transformer area to South side of East stairwell - 6 each conduits. 3 each 3” conduits from transformer area to elevator area. Ok to cover progress areas. All center slab underground is complete. Ok to cover progress areas.
06/02/2023 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass Light pole cages for two light pole footings. Ok to,place concrete in progress areas.
02/22/2024 COT - FCON - Fire - Final N/A Partial Pass Ok for tco level 4 per tucson fire for floors one and two.

Completed Inspections

Permit Status: Complete
Permit Number: T22CM03107
Permit Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
Total Completed Inspections - 36
Date Description Inspector Results Comments
09/08/2023 COT - HCPL - Plumbing Roof Drains Passed
09/14/2023 COT - HCME - Mechanical Intermediate Passed
09/20/2023 COT - HCPL - Gas Pressure Test Passed
10/11/2023 COT - HCBU - Exterior Clips/Sheathing Passed
11/28/2023 BULD - Electrical Clearance Passed #116. ECO. CLEARANCE FOR TEP
12/11/2023 COT - LCBU - Masonry Pregrout Passed
12/11/2023 COT - HCBU - Framing Passed
12/11/2023 COT - HCBU - Preslab Passed
12/11/2023 COT - HCBU - Roof Nailing Passed
12/11/2023 COT - HCBU - Interior Shear Bracing Passed
12/18/2023 COT - HCPL - Gas Final Passed Forwarded request for gas meter service to PDS at 1115 hours.
12/19/2023 COT - BULD - SWG Clearance Passed
01/17/2024 COT - HCPL - Rough Soil Passed Per Jim Burge
01/17/2024 COT - HCPL - Sewer Passed Per Jim Burge
01/17/2024 COT - HCPL - Backwater Valve Passed Per Jim Burge
01/17/2024 COT - HCPL - Plumbing Progress Passed Per Jim Burge
01/17/2024 COT - HCBU - Building Progress Passed Per Jim Burge
01/17/2024 COT - HCPL - Plumbing Above Ceiling Passed Per Jim Burge
01/17/2024 COT - HCBU - Building Above Ceiling Passed Per Jim Burge
01/17/2024 COT - HCEL - Electrical Above Ceiling Passed Per Jim Burge
01/17/2024 COT - HCME - Mechanical Above Ceiling Passed Per Jim Burge
01/17/2024 COT - HCEL - Electrical Progress Passed Per Jim Burge
01/17/2024 COT - HCBU - Firewall/Fire Barrier/Firestop Passed Per Jim Burge
01/17/2024 COT - HCEL - Electrical Underground Passed Per Jim Burge
01/17/2024 COT - HCBU - Excavation/Rebar/Zoning Passed Per Jim Burge
02/05/2024 COT - HCEL - Electrical Final Passed
02/06/2024 COT - HCEL - Electrical Intermediate Passed
02/06/2024 COT - HCPL - Plumbing Intermediate Passed
02/22/2024 COT - FCON - Sprinkler - Final Passed
03/20/2024 COT - HCME - Mechanical Final Passed
03/20/2024 COT - FCON - Alarm - Final Passed
03/20/2024 ENGR Engineering Final Passed
03/20/2024 COT - HCBU - Building Final Passed OK to make application for Certificate of Occupancy.
03/20/2024 COT - FCON - Fire - Final Passed
03/20/2024 COT - HCEL - Outdoor Lighting Passed
03/20/2024 COT - HCPL - Plumbing Final Passed

Documents

File Name Document Type  
COFO_FINALCOFO_COMMERCIAL.PDF DOCUMENTS VIEW
CASCADE APARTMENTS - FINAL TAB REPORT_V2.PDF DOCUMENTS VIEW
CASCADE APARTMENTS STATE OF ARIZONA ACCEPTANCE REPORT - ELEVATOR_V1.PDF DOCUMENTS VIEW
COFO_TEMPORARYCOFO.PDF DOCUMENTS VIEW
22-079M CASCADE APARTMENTS, FINAL SP. IN. PACKET-2024-01-12_V1.PDF DOCUMENTS VIEW
05 40 00 CASCADE APARTMENTS LGS FLOOR TRUSS RESUBMITTAL_V1 (1)_V1.PDF DOCUMENTS VIEW
05 40 00 CASCADE APTS LGS ROOF TRUSS RESUBMITTAL W-FIELD USE LAYOUT 6-5-23_V1 (1)_V1.PDF DOCUMENTS VIEW
CONS-05 40 00 CASCADE APARTMENTS LGS FLOOR TRUSS RESUBMITTAL_V2 (1)_V1.PDF DOCUMENTS VIEW
SIC.PDF DOCUMENTS VIEW
PLAN SET.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
SUPPLEMENTAL STRUCTURAL CALCULATIONS.PDF DOCUMENTS VIEW
PROJECT MANUAL.PDF DOCUMENTS VIEW
PROJECT MANUAL.PDF DOCUMENTS VIEW
SOILS REPORT.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD.PDF DOCUMENTS VIEW