Permit: T22CM03107
Permit Details
Apply Date:
04/26/2022
Applicant:
Description:
This project is a new construction 4-story (70 unit) apartment building for the Elderly.
Permit Reviews
Permit Number - T22CM03107
Permit Status: Complete
Permit Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/26/2022 | COMMERCIAL - BLDG/FIRE/ZONING/ENG | 05/25/2022 | COMPLETED |
| 06/30/2022 | RESUBMITTAL | 08/11/2022 | COMPLETED |
| 08/23/2022 | RESUBMITTAL | 09/09/2022 | COMPLETED |
| 10/10/2022 | RESUBMITTAL | 10/14/2022 | COMPLETED |
| 10/17/2022 | RESUBMITTAL | 10/19/2022 | ACTIVE |
| 02/27/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/01/2024 | REQUIRES RESUBMIT |
| 04/20/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/01/2023 | REQUIRES RESUBMIT |
| 01/12/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/16/2024 | APPROVED |
| 06/26/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 06/26/2023 | APPROVED |
| 03/21/2024 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 03/25/2024 | APPROVED |
| 06/07/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 06/12/2023 | APPROVED |
Conditions
Permit Number - T22CM03107
Permit Status: Complete
Permit Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
| Date | Description | Comments |
|---|---|---|
| 10/19/2022 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. | |
| 10/19/2022 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
| 10/19/2022 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. | |
| 10/19/2022 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. | |
| 10/19/2022 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
| 10/19/2022 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
| 10/14/2022 | The Wastewater Utility Fee Application #P22WX01597 was approved with the following PCRWRD Condition:ISSUED WITH PCRWRD CONDITIONS: NO FINAL AND NO CERTIFICATE OF OCCUPANCY UNTIL THE: THE DSD SITE PSL, THE PCRWRD TYPE III CAPACITY, THE ABANDONMENT OF THE EXISTING ON-SITE PUBLIC SEWER, AND THE NEW PUBLIC SEWER MANHOLE, IS ACCEPTED AND RELEASED BY PCRWRD PER DSD/SITE/HUSSEIN AL ZUBAIDIGerry KoziolPima County DSD-Building Codes/Wastewater Utility Fee201 N Stone Ave Tucson, AZ 85701(520)724-6503 | |
| 10/14/2022 | NEED WASTE WATER RECEIPT | |
| 10/19/2022 | SHOP DRAWINGS REQUIRED FOR ROOF TRUSSES. | |
| 10/19/2022 | SHOP DRAWINGS REQUIRED FOR FLOOR TRUSSES. | |
| 10/20/2022 | WATER DISINFECTION REPORT REQUIRED | |
| 03/01/2024 | ELEVATOR INSPECTION IS REQUIRED - PLEASE PROVIDE DOCUMENTATION THAT THE INSPECTION HAS BEEN COMPLETED AND PASSED. | |
| 01/12/2024 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. | |
| 02/01/2024 | AIR BALANCE REPORT REQUIRED | |
| 02/01/2024 | SHOP DRAWINGS REQUIRED FOR ALARM. | |
| 02/01/2024 | SHOP DRAWINGS REQUIRED FOR SPRINKLER. | |
| 02/01/2024 | WATER DISINFECTION REPORT REQUIRED | |
| 01/12/2024 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. | |
| 01/12/2024 | SPECIAL INSPECTION FOR REINFORCING STEEL AND/OR PRE-STRESSING TENDONS IS REQUIRED. | |
| 01/12/2024 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
Outstanding Inspections
Permit Status: Complete
Permit Number: T22CM03107
Permite Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
Total Outstanding Inspections - 17
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/19/2022 | COT - LCME - Mechanical Final | N/A | Re-inspection required | {Activity date: 10/19/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - AIR BALANCE REPORT REQUIRED PRIOR TO FINAL INSPECTION} |
| 10/19/2022 | COT - LCPL - Plumbing Final | N/A | Re-inspection required | {Activity date: 10/19/2022; Status: Prior to Final Inspectn; Inspector: DBENOIT; Comment: Entered by DBENOIT1 - WATER CHLORINATION REPORT REQUIRED PRIOR TO FINAL INSPECTION} |
| 08/24/2023 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | Roof level parapet walls sheathing. |
| 08/24/2023 | COT - HCBU - Framing | N/A | Partial Pass | Roof area crickets (5) set to roof drains. |
| 10/24/2023 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | Level One corridor. Level 2 all floor units demising walls. Okay to proceed progress areas. 9/22/2023 10/24/23: not ready |
| 03/16/2023 | COT - HCPL - Rough Soil | N/A | Partial Pass | Main sewer lines and laterals for ten units at West end of site. waste lines at 2” - 8”. Ok to cover progress areas. Excavation/layout/rebar: East stairwell footing, elevator/sump pump footing. Ok to place concrete in progress areas. |
| 08/31/2023 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Waste and vent lines in laundry rooms on Levels #1 and 2: 2 1/2” - 4” lines. |
| 08/31/2023 | COT - HCBU - Building Progress | N/A | Partial Pass | East shear walls on levels #1 & #2 (except for room 110). Ok to,tape progress areas. |
| 11/28/2023 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 1st floor corridor okay to proceed progress areas. 11/28/2023 |
| 11/28/2023 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | 1st floor corridor okay to proceed progress areas. 11/28/2023 |
| 11/28/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 1st floor corridor okay to proceed progress areas. 11/28/2023 |
| 11/28/2023 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 1st floor corridor okay to proceed progress areas. 11/28/2023 |
| 09/21/2023 | COT - HCEL - Electrical Progress | N/A | Partial Pass | Partial pass. Inspection was for electrical clearance. 9/21/2023 |
| 12/20/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Partial Pass | 12/20/23: 4th floor maintenance room east wall firewall/ fire barrier. |
| 04/20/2023 | COT - HCEL - Electrical Underground | N/A | Partial Pass | Electric conduit (3”) from transformer area to South side of East stairwell - 6 each conduits. 3 each 3” conduits from transformer area to elevator area. Ok to cover progress areas. All center slab underground is complete. Ok to cover progress areas. |
| 06/02/2023 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Light pole cages for two light pole footings. Ok to,place concrete in progress areas. |
| 02/22/2024 | COT - FCON - Fire - Final | N/A | Partial Pass | Ok for tco level 4 per tucson fire for floors one and two. |
Completed Inspections
Permit Status: Complete
Permit Number: T22CM03107
Permit Description: This project is a new construction 4-story (70 unit) apartment building for the Elderly.
Total Completed Inspections - 36