Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
Permit Number - T22CM03107
Inspection Description - COT - HCBU - Framing
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/21/2023 | COT - HCBU - Framing | Partial Pass | Level #1 corridor, application of required strapping as per detail #76. | |
| 07/10/2023 | COT - HCBU - Framing | Not Ready | Contractor cancelled. | |
| 07/12/2023 | COT - HCBU - Framing | Partial Pass | Levels #1 (at ceiling level through Level #2 to floor level of Level #3) through bolts adjusted and set in place as per SK73 - 76 to include strapping at ledger level. Changes to detail 233 and 235 included to approved to overall required changes. | |
| 07/18/2023 | COT - HCBU - Framing | Partial Pass | Information only for SK-3 (6 -27 -23) and application of proposed placement of hold-downs. | |
| 07/20/2023 | COT - HCBU - Framing | Partial Pass | Level #1, hold downs for all unit rooms in place and epoxy inspected. | |
| 07/25/2023 | COT - HCBU - Framing | Not Ready | Screw pattern for framing track on Level #1 corridor,is incorrect. Shear wall screw pattern in corridor of first floor; OK to tape and texture. | |
| 08/18/2023 | COT - HCBU - Framing | Partial Pass | Roof level: framing is complete. | |
| 08/24/2023 | COT - HCBU - Framing | Partial Pass | Roof area crickets (5) set to roof drains. | |
| 08/29/2023 | COT - HCBU - Framing | Partial Pass | Pop-outs on levels #1 and #2. Ok to cover progress areas. | |
| 12/11/2023 | COT - HCBU - Framing | Passed |