Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T22CM03107

Parcel: 11508007E


Addresses:

1346 N STONE AV


Inspection Status: Passed

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - T22CM03107

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Passed

Date Description Inspector Results Comments
01/17/2024 COT - HCBU - Excavation/Rebar/Zoning  Passed Per Jim Burge
03/23/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Footings at GL: D/2 - 8, West stairwell footing. Ok to place concrete in progress areas.
03/27/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Elevator pit at first lift 0’ - 4’. Ok to place grout in progress areas.
03/29/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Masonry pre-grout stem wall for East stairwell at 24” AFFE; West stairwell at 8” - 36”. Ok to grout progress areas.
03/30/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Masonry pre-grout at West stair well (0’ - 4’): East stairwell at (4’ - 8’). Ok to place grout in progress areas.
04/04/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Stem wall at GL: D.2.3 - 6.2. Ok to place concrete in progress areas.
05/02/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column footings for 5 columns at elevator area. Ok to place concrete in progress areas.
05/03/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Footings and stem walls at East stairwell area and elevator area at GL: A/4 - 8. West stairwell column footings and stem wall footings at GL: A/1 - 4. Ok to place concrete in progress areas.
05/16/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Column/footing (C7, F10 at East stairwell entry, Ok to place concrete in progress areas.
06/02/2023 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Light pole cages for two light pole footings. Ok to,place concrete in progress areas.