Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/17/2024 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Passed |
Per Jim Burge |
| 03/23/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Footings at GL: D/2 - 8, West stairwell footing. Ok to place concrete in progress areas. |
| 03/27/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Elevator pit at first lift 0’ - 4’. Ok to place grout in progress areas. |
| 03/29/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Masonry pre-grout stem wall for East stairwell at 24” AFFE; West stairwell at 8” - 36”. Ok to grout progress areas. |
| 03/30/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Masonry pre-grout at West stair well (0’ - 4’): East stairwell at (4’ - 8’). Ok to place grout in progress areas. |
| 04/04/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Stem wall at GL: D.2.3 - 6.2. Ok to place concrete in progress areas. |
| 05/02/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Column footings for 5 columns at elevator area. Ok to place concrete in progress areas. |
| 05/03/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Footings and stem walls at East stairwell area and elevator area at GL: A/4 - 8. West stairwell column footings and stem wall footings at GL: A/1 - 4. Ok to place concrete in progress areas. |
| 05/16/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Column/footing (C7, F10 at East stairwell entry, Ok to place concrete in progress areas. |
| 06/02/2023 |
COT - HCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Light pole cages for two light pole footings. Ok to,place concrete in progress areas. |