Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: COT - HCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 01/17/2024 |
COT - HCEL - Electrical Underground |
|
Passed |
Per Jim Burge |
| 04/20/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Electric conduit (3”) from transformer area to South side of East stairwell - 6 each conduits. 3 each 3” conduits from transformer area to elevator area. Ok to cover progress areas. All center slab underground is complete. Ok to cover progress areas. |
| 04/21/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Underground conduits (1” - 3”) from elevator to west stairwell area, approximately 75 feet. Conduits to 90 up at West stairwell. Ok to cover progress areas. |
| 04/27/2023 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
Ufer installed from East transformer area to West secondary lines at West stairwell. |