Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Interior Shear Bracing
Permit Number - T22CM03107
Inspection Description - COT - HCBU - Interior Shear Bracing
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/26/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | ||
| 08/24/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level #3, unit framing | |
| 08/28/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | Interior shear on South wall at level #1. 4” nail pattern throughout. | |
| 09/13/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level #2, corridor (East) shear wall Sheetrock nailing. Ok to tape progress areas. | |
| 09/18/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level #2 corridor shear walls, Sheetrock nailing. Ok to tape progress areas. | |
| 09/22/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level 2 all floor units demising walls. Okay to proceed progress areas. 9/22/2023 | |
| 10/19/2023 | COT - HCBU - Interior Shear Bracing | Not Ready | Contractor cancelled. | |
| 10/23/2023 | COT - HCBU - Interior Shear Bracing | Not Ready | Contractor cancelled. | |
| 10/24/2023 | COT - HCBU - Interior Shear Bracing | Not Ready | Level One corridor. Level 2 all floor units demising walls. Okay to proceed progress areas. 9/22/2023 10/24/23: not ready |
|
| COT - HCBU - Interior Shear Bracing | Partial Pass | Level One corridor. Level 2 all floor units demising walls. Okay to proceed progress areas. 9/22/2023 10/24/23: not ready 10/25/23: level 2 shear wall nail scheduling per plan |
||
| 10/25/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | 10/25/23: level 2 shear wall nailing per schedule | |
| 11/08/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | Demising wall sheetrock nailing on Level #3; rooms 302, 303, 304, 305, 307, 309, 310, 311, 312, 313, 314, 316, 317, 318. Ok to tape progress areas. | |
| 11/22/2023 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level #4 corridor and room units demising walls at #401 through 418. Ok to tape progress areas. | |
| 12/11/2023 | COT - HCBU - Interior Shear Bracing | Passed | ||
| 12/11/2023 | COT - HCBU - Interior Shear Bracing | Passed |