Inspection Status: Partial Pass
Inspection History: COT - LCBU - Masonry Pregrout
| Date |
Description |
Inspector |
Results |
Comments |
| 04/03/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
CMU walls for East stairwell at 12’ - 14’; elevator shaft at 4’ - 8’. Ok to place concrete in progress areas. |
| 04/04/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
East stairwell at 16’ - 20’; West stair well at 8’ - 12’; Elevator shaft at 8’ - 12’. Ok to place grout in progress areas. |
| 04/06/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
CMU Walls of East stairwell at 24’ - 28’; West stairwell at 20’ -24’; elevator shaft 15’ - 20’. Ok to place grout in progress areas. |
| 04/07/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
CMU walls for East stairwell at 28’ - 32’; west stairwell at 24’ - 28’; elevator shaft at 20’ - 24’. Ok to place grout in progress areas. |
| 04/10/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
CMU walls at East stairwell at 36’ - 40’; West stairwell at 28’ - 32’; Elevator shaft at 24’ - 28’. Ok to place grout in progress areas. |
| 04/11/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
CMU walls for East stairwell. at 36’ - 40’8” (topped out); West stairwell at 32’ - 36’; elevator shaft at 28’ -32’. Ok to place grout in progress areas. |
| 04/12/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
CMU East stairwell topped out at 40’ 8”; West stairwell topped out at 40’ 8”; elevator shaft at 32’ - 40’. Ok to place grout in progress areas. |
| 04/14/2023 |
COT - LCBU - Masonry Pregrout |
|
Partial Pass |
Elevator shaft topped out at 45’. Ok to grout progress areas. |
| 12/11/2023 |
COT - LCBU - Masonry Pregrout |
|
Passed |
|