Inspection Status: Passed
Inspection History: COT - HCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 01/17/2024 |
COT - HCPL - Rough Soil |
|
Passed |
Per Jim Burge |
| 03/01/2023 |
COT - HCPL - Rough Soil |
|
Partial Pass |
Waste lines 2” - 4” ; main line and laterals at GL: B/2 -4. Ok to cover progress areas. |
| 03/16/2023 |
COT - HCPL - Rough Soil |
|
Partial Pass |
Main sewer lines and laterals for ten units at West end of site. waste lines at 2” - 8”. Ok to cover progress areas. Excavation/layout/rebar: East stairwell footing, elevator/sump pump footing. Ok to place concrete in progress areas. |
| 03/23/2023 |
COT - HCPL - Rough Soil |
|
Partial Pass |
Domestic water line tested at 100 psi. Ok to cover progress area. |