Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date |
Description |
Inspector |
Results |
Comments |
| 04/12/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
South side of site at GL: D/2.5 - 8. OK to place concrete in progress areas. |
| 04/27/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
Exterior wall footings and interior lateral wall footings. Ok to place concrete in progress areas |
| 05/09/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
West half of building slab at GL: 1 -4. West portion from West end to elevator area, vapor barrier and rebar are in place. Ok to place concrete in progress areas. |
| 05/16/2023 |
COT - HCBU - Preslab |
|
Partial Pass |
East portion of building slab at elevator East to East stairwell. Ok to place concrete in progress areas. |
| 12/11/2023 |
COT - HCBU - Preslab |
|
Passed |
|