Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address:
1055 N PARK AV
Address NEW:
1055 N PARK AV
Apply Date:
10/01/2019
Applicant:
N/A
Description:
NEW STUDENT HOUSING BLDG
Architects:
  • JOSEPH ANTUNOVICH
Contractors:
  • TREEHOUSE CONSTRUCTION

Permit Reviews

Permit Number - T19CM07159
Permit Status: C of o
Permit Description: NEW STUDENT HOUSING BLDG
Start Date Submittal Complete Date Status  
01/20/2021 3RD PARTY REVIEW - REVISION/OTHER 02/05/2021 COMPLETED Review Details
01/28/2020 POST 3RD PARTY REVIEW 03/13/2020 COMPLETED Review Details
02/12/2021 3RD PARTY REVIEW - REVISION/OTHER 04/19/2021 COMPLETED Review Details
03/13/2020 POST 3RD PARTY REVIEW 07/27/2020 COMPLETED Review Details
04/19/2021 3RD PARTY REVIEW - REVISION/OTHER-2ND 06/15/2021 COMPLETED Review Details
06/15/2021 3RD PARTY REVIEW - REVISION/OTHER 08/09/2021 COMPLETED Review Details
07/27/2020 3RD PARTY REVIEW - REVISION/OTHER 08/04/2020 COMPLETED Review Details
10/01/2019 PLANS OK TO SUBMIT - COMM 10/01/2019 COMPLETED Review Details
10/08/2019 3RD PARTY REVIEW - COMMERCIAL 01/28/2020 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T19CM07159
Permit Status: C of o
Permit Description: NEW STUDENT HOUSING BLDG
Total Outstanding Activity Conditions - 1
Date Name
10/01/2019 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T19CM07159
Permit Description: NEW STUDENT HOUSING BLDG
Total Completed Inspections - 53
Date Description Inspector Results Comments
10/02/2020 BUILDING - PROGRESS JBURGE Approved Not ready. Contractor cancelled.
10/14/2020 ELECTRIC - PROGRESS ESTEVENS Approved Partial. Post tension inspection with Jim. Level 6, pour 23.
10/16/2020 ELECTRIC - UFER ESTEVENS Approved Approved.
10/16/2020 ELECTRIC - UNDERGROUND ESTEVENS Approved Canceled.
11/02/2020 PLUMBING - PRE SLAB ESTEVENS Approved Partial. Ramp at gridlines AC.3-A7. Wall grout 2nd lift level 1, gridlines AC-A6 to A10.5, gridlines A10.5 and A12-AB to AF. Gridlines BF-B3 to B8.
11/23/2020 SITE - SEWER ESTEVENS Approved Inlet side of grease trap.
11/24/2020 BUILDING PRE-SLAB ESTEVENS Approved Partial. Post tension inspection with Bruce. Level 7. Roof pour #29.
12/07/2020 FRAMING JBURGE Approved Partial. Exterior framing of Northwest Section of Building at Levels #1; 3; 4; 5; 6.
12/07/2020 FRAMING JBURGE Approved Partial. Exterior framing of Northwest Section of Building at Levels #1; 3; 4; 5; 6.
12/18/2020 PLUMBING - INTERMEDIATE ESTEVENS Approved Canceled
12/21/2020 EXCAVATION/LAYOUT REBAR & ZON JBURGE Approved Partial. Roof level, elevator/stairwell #1; over ride slab. Double mat #5 rebar at 12” on center. Ok to,place concrete..
12/29/2020 REINFORCED MASONRY PRE-GROUT ESTEVENS Approved Partial. Level 6M. North Restroom wall. Building A. Exterior stairwell wall
12/29/2020 EXT METAL CLIPS/EXT SHEATHING ESTEVENS Approved Partial. Exterior densglass. Building B. Level 2, level 3, level 4, are complete.
05/28/2021 TEP CLEARANCE - AM ESTEVENS Approved CODE ECO/SES PANL H HOUSE PANEL, SES RETAIL CABINTE 1 THRU 2 B, SES RETAIL CABINET 3AA THRU 5B, SES RW RESIDENTIAL WEST, SES RE RESIDENTIAL EAST, LEVEL 2 BLDG B METERS FOR UNITS 210 THRU 224, LEVEL 2 BLDG A METERS FOR UNITS 201 THRU 209 AND 225 THRU 228, LEVEL 3 BLDG A METERS FOR UNITS 301 THRU 309 AND 325 THRU 328, LEVEL 3 BLDG B METERS FOR UNITS 310 THRU 324, LEVEL 4 BLDG A METERS FOR UNITS 401 THRU 409 AND 425 THRU 428, LEVEL 4 BLDG B METERS FOR UNITS 410 THRU 424
06/25/2021 GAS CLEARANCE ESTEVENS Approved CODE
06/25/2021 PLUMBING - GAS PRESSURE TEST ESTEVENS Approved
07/02/2021 TEP CLEARANCE - PM ESTEVENS Approved CODE ECO/UNITS 121, 122, 123, 124, 125, FOR METERS ONLY
07/27/2021 MECHANICAL - PROGRESS ESTEVENS Approved
07/27/2021 MECHANICAL - HOOD SYSTEMS ESTEVENS Approved
07/27/2021 MECHANICAL - HOODS ESTEVENS Approved
07/27/2021 PLUMBING - PROGRESS ESTEVENS Approved
07/27/2021 PLUMBING - MD GAS/PRECONST MTG ESTEVENS Approved
07/27/2021 ELECTRIC - SERVICE UPGRADE ESTEVENS Approved
07/27/2021 STUCCO MESH ESTEVENS Approved
07/27/2021 ROOF NAILING ESTEVENS Approved
07/27/2021 STEM WALL/RETAINING WALL ESTEVENS Approved
07/27/2021 ELECTRIC - ABOVE CEILING ESTEVENS Approved
07/27/2021 FIREWALL/FIREBARRIER/FIRESTOP ESTEVENS Approved
07/27/2021 BUILDING ABOVE CEILING ESTEVENS Approved
07/27/2021 MECHANICAL - ABOVE CEILING ESTEVENS Approved
07/27/2021 PLUMBING - ABOVE CEILING ESTEVENS Approved
07/27/2021 SHEET ROCK NAILING ESTEVENS Approved
07/27/2021 PLUMBING - ROUGH, SOIL ESTEVENS Approved
07/27/2021 PLUMBING - ROOF DRAINS ESTEVENS Approved APPROVED UNDER 3035
08/06/2021 LANDSCAPE - FINAL BBENEDON Approved Approved.
08/12/2021 PLUMBING - GAS PRESS TEST FNL ESTEVENS Approved N/A
08/12/2021 ELECTRIC - CONSTRUCTION POWER ESTEVENS Approved Passed.
08/12/2021 MECHANICAL - INTERMEDIATE ESTEVENS Approved Passed.
08/12/2021 ELECTRIC - INTERMEDIATE ESTEVENS Approved Passed.
08/13/2021 ELECTRIC - OUTDOOR LIGHTING ESTEVENS Approved 2090
08/13/2021 OUTDOOR LIGHTING FINAL ESTEVENS Approved 2090
08/16/2021 ELECTRIC - FINAL DQUINN Approved Ap
08/16/2021 PLUMBING - FINAL DQUINN Approved Ap
08/16/2021 MECHANICAL - FINAL DQUINN Approved Ap
08/17/2021 NPPO - FINAL DROBERTS Approved APPROVED
08/17/2021 SIGN - FINAL DROBERTS Approved APPROVED
08/23/2021 RIGHT OF WAY - FINAL Bravin Approved No issues with ROW. final
10/28/2021 ENGINEERING - FINAL DROBERTS Approved APPROVED
11/05/2021 ZONING - FINAL RSALDAT1 Approved FINAL ZONE INSPECTION APPROVED.
ITEM 1: PET RELEIF NA DUE TO NO PET RELIEF PROVIDED.
ITEM 2: WINDOWS WERE APPROVED IN PREVIOUS REVIEW.
11/09/2021 FIRE - FINAL MRoss Approved Need signage:
"Combo" and inlet pressure at FDC
Riser labels in pump room
11/09/2021 FIRE SPKLR - FINAL MRoss Approved Need signage:
"Combo" and inlet pressure at FDC
Riser labels in pump room
11/09/2021 FIRE - ALARM FINAL MRoss Approved
11/10/2021 BUILDING - FINAL ESTEVENS Approved Approved