Date Description Inspector Results Comments
07/27/2021 PLUMBING - PRE SLAB Approved
11/02/2020 PLUMBING - PRE SLAB Partial Approval Partial. Ramp at gridlines AC.3-A7. Wall grout 2nd lift level 1, gridlines AC-A6 to A10.5, gridlines A10.5 and A12-AB to AF. Gridlines BF-B3 to B8.
10/26/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim B. Level 6, pour 25.
10/20/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim B. Level 6, pour number 24.
10/14/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim. Level 6, pour 23.
10/08/2020 PLUMBING - PRE SLAB Partial Approval PARTIAL. POST TENSION INSPECTION WITH BRUCE S. LEVEL 5 POUR #22.
10/02/2020 PLUMBING - PRE SLAB Not ready for Inspection Not ready. Contractor cancelled.
09/28/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post Tension Cable System at Level #5; Pour #20 (East). Fire stop shafts are in place.
09/23/2020 PLUMBING - PRE SLAB Partial Approval Partial. Columns on level 4. Building B.
09/22/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim B. Level 4 pour 19.
09/16/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim B. Level 4 pour #18.
09/10/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim B. Level 4, pour 17.
09/03/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim B. Level 3 pour 16.
08/27/2020 PLUMBING - PRE SLAB Partial Approval Partial. Post tension inspection with Jim B. Level 3, pour number 15.
08/20/2020 PLUMBING - PRE SLAB Partial Approval Partial. Spacers and pass through in place at Level #3; Pour #14/2.
06/22/2020 PLUMBING - PRE SLAB Partial Approval Partial. On site with Jim B. For post tension inspection in grid line areas AA to AM north of gridline A1. Also the area within grid lines AA to AE and A4.5 to A11. Building B, Slab on grade, the area within B2 to B7 and BA to BB.7.
06/19/2020 PLUMBING - PRE SLAB Cancelled This inspection was canceled by the contractor.
06/18/2020 PLUMBING - PRE SLAB Partial Approval Partial. The area within A11 to A14 and AA to AE.