Inspection Status: Approved
Inspection History: ELECTRIC - PROGRESS
| Date |
Description |
Inspector |
Results |
Comments |
| 07/27/2021 |
ELECTRIC - PROGRESS |
|
Approved |
|
| 10/14/2020 |
ELECTRIC - PROGRESS |
|
Partial Approval |
Partial. Post tension inspection with Jim. Level 6, pour 23. |
| 09/10/2020 |
ELECTRIC - PROGRESS |
|
Partial Approval |
Partial. Post tension inspection with Jim B. Level 4, pour 17. |
| 08/20/2020 |
ELECTRIC - PROGRESS |
|
Partial Approval |
Partial. Conduits and junction boxes in slab T Level #3; Pour 14/2 |
| 06/22/2020 |
ELECTRIC - PROGRESS |
|
Partial Approval |
Partial. On site with Jim B. For post tension inspection in grid line areas AA to AM north of gridline A1. Also the area within grid lines AA to AE and A4.5 to A11. Building B, Slab on grade, the area within B2 to B7 and BA to BB.7. |
| 06/19/2020 |
ELECTRIC - PROGRESS |
|
Cancelled |
This inspection was canceled by the contractor. |
| 06/18/2020 |
ELECTRIC - PROGRESS |
|
Partial Approval |
Partial. The area within A11 to A14 and AA to AE. |