Inspection History: FIREWALL/FIREBARRIER/FIRESTOP

Date Description Inspector Results Comments
07/27/2021 FIREWALL/FIREBARRIER/FIRESTOP Approved
07/13/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval 1044, 1036, 2036. Partial. Elevator lobby M1
07/02/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Lower level elevator lobby.
06/23/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Pool level restrooms and lobby restrooms.
06/17/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Corridor 151 – G
06/16/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Level 6M. Corridor.
06/10/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Annex/study area. Level 6. Building A&B corridors.
06/08/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval PARTIAL WEST SIDE CORREDOR BUILDING B
06/07/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Level #6 corridor areas except for center section
06/04/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Leasing offices, level one elevator lobby, and mail room.
06/02/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Unit 219, 319, 419, 519, and 516.
05/21/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Unit 703, 121.
05/20/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Units 122, 707, and level four Corridor.
05/19/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Level #7: Room Unit 703; penetrations properly fire caulked.
05/17/2021 FIREWALL/FIREBARRIER/FIRESTOP Denied Denied. Units 121, 122, 703, 707. Not ready, to many errors.
05/13/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval 1044, 1035, 2035, 3035, 4035. Unit 701, 702, 704, 705, 706.
05/11/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Level two and three elevator rooms and Corridors.
05/10/2021 FIREWALL/FIREBARRIER/FIRESTOP Denied denied. Level two and three elevators and Corridor area. Too many errors, not complete.
05/06/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Drywall in trash chute areas. Level 1.5 to level 7.
04/30/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Unit 610, 611, 612, 613, 622.
04/29/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Level six. Units 625 and 624.
04/29/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Firewall around ductwork in unit 3B, Starbucks.
04/26/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Townhouses unit 123, 124, 125. Level six. Unit 601, 602, 604, 608, 626, 6/27, and 628.
04/22/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Unit 603, 605, 606, 607, and 608. Town houses are not ready.
04/20/2021 FIREWALL/FIREBARRIER/FIRESTOP Not ready for Inspection
04/15/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval PARTIAL LEVEL #5 - UNIT #520
04/02/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval 1044, 1035, 2035, 3035, 4035. Unit 517, 518, 521, 522, 523, 527, 526, 501, and 502
04/01/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval PARTIAL UNIT 509, 510, 511, 512, 513, 514, 515, 516
03/30/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Level five. Unit 503, 504, 505, 506, 507, 508, 527, 528.
03/25/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval PARTIAL LEVEL #4, UNITS 405, 410 THRU 424
03/19/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Units. 426. 425. 409. 410. 424. 411. 412.
2035. Partial. Building A & B Corridors on level 4.
03/16/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Units 315, 319, 316, 401, 404, 428.
01/07/2021 FIREWALL/FIREBARRIER/FIRESTOP Partial Approval Partial. Building A. Level two. First layer stair press.