Permit: T07CM01348
Permit Details
Apply Date:
04/02/2007
Applicant:
RELIABLE PERMIT MANAGEMENT
Description:
NEW COMMERCIAL BLDG
Contractors:
- CRYSTAL GENERAL CONTRACTORS L L C
Permit Reviews
Permit Number - T07CM01348
Permit Status: Final
Permit Description: NEW COMMERCIAL BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/09/2008 | RESUBMITTAL - SITE ALL | 01/31/2008 | COMPLETED |
| 01/09/2009 | REVISION - - 3RD | 01/09/2009 | COMPLETED |
| 01/22/2008 | POST 3RD PARTY REVIEW | 03/18/2008 | COMPLETED |
| 02/20/2008 | RESUBMITTAL - SITE ALL | 03/18/2008 | COMPLETED |
| 03/18/2008 | RESUBMITTAL - SITE ALL | 03/19/2008 | COMPLETED |
| 03/25/2008 | RESUBMITTAL | 03/26/2008 | COMPLETED |
| 04/02/2007 | PLANS OK TO SUBMIT - SITE | 04/02/2007 | COMPLETED |
| 04/03/2007 | SITE | 05/03/2007 | COMPLETED |
| 04/05/2007 | PLANS OK TO SUBMIT - 3RD PARTY | 04/06/2007 | COMPLETED |
| 04/06/2007 | 3RD PARTY REVIEW-COMMERCIAL | 01/22/2008 | COMPLETED |
| 06/01/2007 | RESUBMITTAL - SITE ALL | 07/02/2007 | COMPLETED |
| 11/17/2008 | REVISION - - 1ST | 11/17/2008 | COMPLETED |
| 12/18/2008 | REVISION - - 2ND | 12/18/2008 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T07CM01348
Permit Status: Final
Permit Description: NEW COMMERCIAL BLDG
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/02/2007 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T07CM01348
Permit Description: NEW COMMERCIAL BLDG
Total Completed Inspections - 38
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/23/2008 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* CORRECTIONS COMPLETE - OK TO POUR FOOTING |
| 05/28/2008 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection :* EXTERIOR STEM WALL |
| 06/30/2008 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* ALL PIPING EXPOSED TO CONCRETE TO BE WRAPPED CALL 03015 FOR PRE-SLAB INSPECTION |
| 06/30/2008 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
| 06/30/2008 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 07/01/2008 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* OK FOR CONCRETE |
| 07/11/2008 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 07/22/2008 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | |
| 08/25/2008 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 08/25/2008 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/29/2008 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection : Work is not complete enough to inspect.| 950* |
| 10/29/2008 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/18/2008 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | OK 1/0 TO 2 GROUND RODS OK 2ND FLOOR ONLY 1. OUTLETS NOT AS PER PLANS 2. A/C NOT AS PER PLANS 3. SUPPORT LOW VOLTAGE (VDV) CABLING IN WALLS - 725.24 4. INSTALL FAN RATED BOXES FOR CEILING FANS 5. INSTALL PHONE AND CABLE SMART PANEL 6. CONDUITS UNDER DRIVEWAY TO BE AS PER 300.5 (24") 7. FINISH SERVICE AS PER PLANS |
| 11/18/2008 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK 1ST FLOOR/2ND FLOOR ROUGH ELECTRIC TO DRYWALL RECEIVED MONEY ORDER #68254689030 -- $150.00 |
| 11/18/2008 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* |
| 12/19/2008 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1. STILL NOT INSTALLED PER PLAN 2. THE APPROVED PLAN NEEDS TO BE REFLECTIVE OF THE INSTALLATION 3. NO TRAPS IN WALL 4. NO N/H BAND ON ABS 5. BANG PLATES |
| 03/31/2009 | TEP CLEARANCE - PM | JWEATHER | Approved | TEC CLEARED PER L. HANLY |
| 03/31/2009 | ELECTRIC - UFER | LHANLY | Approved | |
| 03/31/2009 | BUILDING ABOVE CEILING | LHANLY | Approved | |
| 03/31/2009 | SHEET ROCK NAILING | LHANLY | Approved | |
| 03/31/2009 | FRAMING | LHANLY | Approved | |
| 03/31/2009 | FRAMING | LHANLY | Approved | |
| 03/31/2009 | BUILDING PRE-SLAB | LHANLY | Approved | |
| 03/31/2009 | ELECTRIC - CABLE DROP | LHANLY | Approved | IVRS - Inspection :* |
| 04/15/2009 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | |
| 04/16/2009 | SIGN - FINAL | JYBARRA | Approved | |
| 04/17/2009 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
| 04/23/2009 | FIRE - FINAL | LTHOMAS | Approved | |
| 04/24/2009 | ELECTRIC - OUTDOOR LIGHTING | LHANLY | Approved | IVRS - Inspection :* |
| 04/27/2009 | OUTDOOR LIGHTING FINAL | LHANLY | Approved | |
| 04/28/2009 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 04/29/2009 | MECHANICAL - ABOVE CEILING | MRAMBER | Approved | |
| 05/01/2009 | PLUMBING - FINAL | LHANLY | Approved | PLAN CHANGES ACCEPTED FOR AS-BUILT CONDITIONS. CLEAN BACTERIA REPORT ACCEPTED. |
| 05/01/2009 | SITE - SEWER | LHANLY | Approved | |
| 05/01/2009 | PLUMBING - ABOVE CEILING | LHANLY | Approved | |
| 05/15/2009 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 07/31/2009 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 12/23/2010 | BUILDING - FINAL | LHANLY | Approved |