Permit: TD-DEV-0725-00181
Permit Details
Status:
Inspections
Type:
Development Package
Address:
10000 E OLD VAIL RD
Address NEW:
10000 E OLD VAIL RD
Apply Date:
07/11/2025
Applicant:
Andrea Leonard
Description:
Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Permit Reviews
Permit Number - TD-DEV-0725-00181
Permit Status: Inspections
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/11/2025 | DEVELOPMENT PACKAGE NEW v.1 | 08/26/2025 | REQUIRES RESUBMIT |
| 11/14/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 12/04/2025 | APPROVED |
| 08/29/2025 | DEVELOPMENT PACKAGE NEW v.2 | 09/26/2025 | REQUIRES RESUBMIT |
| 09/30/2025 | DEVELOPMENT PACKAGE NEW v.3 | 10/06/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-0725-00181
Permit Status: Inspections
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/06/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Conditions
Permit Number - TD-DEV-0725-00181
Permit Status: Inspections
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
| Date | Description | Comments |
|---|---|---|
| 12/15/2025 | Prior to Final |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0725-00181
Permite Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Total Outstanding Inspections - 6
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/22/2026 | NPPO Monitoring | N/A | Partial Pass | Plants have been set aside in the correct quantities but not yet moved to a temporary nursery. Plants appear healthy and the plan is to have them in the ground prior to hot weather. Will continue to monitor for signs of stress. |
| 07/28/2026 | N/A | Partial Pass | Bollards along north basin are good to pour. Refuse enclosure bollards' placement is correct and they are concrete filled. Sprouts main pedestrian entrance bollards' placement is correct and they are concrete filled. Loading dock and utility bollards' placement is correct and they are concrete filled. | |
| 05/14/2026 | For trash and recycling enclosures | N/A | Partial Pass | I informed the contractor that they needed to punch out grout. We pulled at the bottom so we can see the grout coming out at the bottom on both trash enclosures. |
| 05/14/2026 | N/A | Partial Pass | OK to backfill the 8 inch roof drain 20 feet | |
| 08/14/2026 | N/A | Partial Pass | With the exception of the curb ramp at the NW corner of building 3, all sidewalks' and curb ramps' slopes & cross-slopes are complete within acceptable tolerances. Curb ramp at NW corner of building 3: Cross-slopes of the ramp and lower landing exceed allowable limit of 2% (ramp measures between 3 & 4%). The cross-slope needs to be corrected to a maximum of 2% on the landings and ramp. |
|
| 08/10/2026 | ENGR Paving | N/A | Partial Pass | AB on North, East, and South side of building 2 and South side of building 1: depth, slopes, and compaction are good, okay to pave this area including main drive from storage facility to future refuse enclosure. |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0725-00181
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Total Completed Inspections - 3
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/05/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | Pre-Construction meeting held on-site with Geoff. Stormwater controls need to be put in place immediately. Grading work is in progress. Temp fencing is being erected currently. "NPPO Pre-Construction" inspection should be called in asap. "Stormwater Initial" inspection should be called in no later than 1/7/26 to confirm horizontal controls are in place prior to rainfall. |
|
| 01/07/2026 | SITE - Stormwater Setup and Controls | Passed | Initial stormwater controls are set up, site will be monitored for additional needs. | |
| 08/18/2026 | ENGR Paving | Passed | Asphalt pavement is complete throughout. Surfaces, slopes, and curb reveals are good. Paving is complete in accordance with approved plans. |