Permit: TD-DEV-0725-00181
Permit Details
Status:
Inspections
Type:
Development Package
Address:
10000 E OLD VAIL RD
Address NEW:
10000 E OLD VAIL RD
Apply Date:
07/11/2025
Applicant:
Andrea Leonard
Description:
Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Permit Reviews
Permit Number - TD-DEV-0725-00181
Permit Status: Inspections
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/11/2025 | DEVELOPMENT PACKAGE NEW v.1 | 08/26/2025 | REQUIRES RESUBMIT |
| 11/14/2025 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 12/04/2025 | APPROVED |
| 08/29/2025 | DEVELOPMENT PACKAGE NEW v.2 | 09/26/2025 | REQUIRES RESUBMIT |
| 09/30/2025 | DEVELOPMENT PACKAGE NEW v.3 | 10/06/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TD-DEV-0725-00181
Permit Status: Inspections
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 10/06/2025 | CRWHPLAN NEEDS TO BE CREATED PRIOR TO CLOSEOUT |
Conditions
Permit Number - TD-DEV-0725-00181
Permit Status: Inspections
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
| Date | Description | Comments |
|---|---|---|
| 12/15/2025 | Prior to Final |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0725-00181
Permite Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/14/2026 | N/A | Partial Pass | OK to backfill the 8 inch roof drain 20 feet | |
| 08/10/2026 | ENGR Paving | N/A | Partial Pass | AB on North, East, and South side of building 2 and South side of building 1: depth, slopes, and compaction are good, okay to pave this area including main drive from storage facility to future refuse enclosure. |
| 09/16/2026 | Sign Electric SITE | N/A | Not Applicable | |
| 09/16/2026 | N/A | Not Applicable | ||
| 09/29/2026 | N/A | Not Ready | Multiple dead trees need to be replaced | |
| 09/29/2026 | ENGR Engineering Final | N/A | Not Ready | Disturbed dirt area where trailers, Connexs and material was placed at Southwest corner of site-This dirt needs to be cleaned up and stabilized with either DG or Hydro seed. Water harvesting infiltration area adjacent to pad 4 refuge enclosures needs to be completed, and the basin top needs to be fixed. Dead trees need to be replaced. |
| 09/29/2026 | NPPO Monitoring | N/A | Not Ready | |
| 09/29/2026 | For trash and recycling enclosures | N/A | Partial Pass | Future pad 4 refuse enclosures floors are good to pour and walls are OK to grout reinforcing with bond beam in place take video or a good pictures showing all grout is being vibrated. Ballard placement is correct. |
| 09/16/2026 | N/A | Not Ready | -Future Pad Four-Refuse enclosure Bollards are incorrect at East side of site. Install them correct per plan and TSM section 8 |
Completed Inspections
Permit Status: Inspections
Permit Number: TD-DEV-0725-00181
Permit Description: Rev 1 started 11.14.2025 - update to building numbers (5 to 4), footprints, site ** Multi-Building General Merchandise & Food Service/Food & Beverage
Total Completed Inspections - 11
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/05/2026 | PDSD Engineering Division Pre-Construction SITE | Passed | Pre-Construction meeting held on-site with Geoff. Stormwater controls need to be put in place immediately. Grading work is in progress. Temp fencing is being erected currently. "NPPO Pre-Construction" inspection should be called in asap. "Stormwater Initial" inspection should be called in no later than 1/7/26 to confirm horizontal controls are in place prior to rainfall. |
|
| 01/07/2026 | SITE - Stormwater Setup and Controls | Passed | Initial stormwater controls are set up, site will be monitored for additional needs. | |
| 08/18/2026 | ENGR Paving | Passed | Asphalt pavement is complete throughout. Surfaces, slopes, and curb reveals are good. Paving is complete in accordance with approved plans. | |
| 08/25/2026 | Consultation SITE | Passed | Site visit to confer with concrete contractor concerning sidewalk issues. Cross-slope issue called out at previous inspection will be corrected. Scupper elevation issue called out at previous inspection will be corrected. | |
| 09/16/2026 | COT - FCON - Fire - Final | Passed | ||
| 09/16/2026 | Sign Final SITE | Passed | ||
| 09/21/2026 | Passed | |||
| 09/21/2026 | Passed | |||
| 09/29/2026 | SITE - Zoning Final | Passed | ||
| 09/29/2026 | Passed | |||
| 09/29/2026 | Passed |