Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 07/28/2026 |
|
|
Partial Pass |
Bollards along north basin are good to pour. Refuse enclosure bollards' placement is correct and they are concrete filled. Sprouts main pedestrian entrance bollards' placement is correct and they are concrete filled. Loading dock and utility bollards' placement is correct and they are concrete filled. |
| 09/16/2026 |
|
|
Not Ready |
-Future Pad Four-Refuse enclosure Bollards are incorrect at East side of site. Install them correct per plan and TSM section 8 |
| 09/29/2026 |
|
|
Canceled |
|