Date Description Inspector Results Comments
07/15/2026 ENGR Paving Not Ready 7/15/25
Subgrade inspection There has been rain and there is more in the forecast. Some areas are muddy (both corners at rear of lot next to outlets to the basin and just north of building by roof drains). Also two curb islands are incorrect North east of store and one that is broken west of store towards rear of lot. These should to be repoured before area can be finished and have AB placed. Paved area along north wall next to north east corner of store also needs to be corrected. Reschedule one ready.
07/31/2026 ENGR Paving Partial Pass 7/31/26
Okay to place AB from North side of Bldgs 1 an 2 going south to the 1st drive lane in front of bldgs and continuing South and including the 2nd drive lane that runs east to west across site. Subgrade correct in both 3 over 4 parking areas and PAALs and 4 over 4 Drive lanes. Hubs good and area South of store string lined for depths and good. Handicap area look good. Submit densities of Subgrade to the portal. Schedule paving inspections as needed when AB is compacted and ready from back of bldgs all the way south to 2nd east/west drive lane.
08/03/2026 ENGR Paving Canceled duplicate inspection scheduled.
08/03/2026 ENGR Paving Partial Pass Sub-grade inspection for main drive line from Old Vail and parking area in front of building 3 (excluding area immediately south of building 3): Sub-grade, elevations, and slopes are good. Okay to drop AB.
08/04/2026 ENGR Paving Partial Pass Sub-grade at main entrance, drive-way south of building 3, and southern most parking stalls: compaction, slopes, and depths are good. Okay to place AB.
08/05/2026 ENGR Paving Not Ready Not ready to string line. More work needs done, will revisit tomorrow.
08/06/2026 ENGR Paving Partial Pass Parking lot in front of building 1: AB is good, okay to pave this section.
08/10/2026 ENGR Paving Partial Pass AB on North, East, and South side of building 2 and South side of building 1: depth, slopes, and compaction are good, okay to pave this area including main drive from storage facility to future refuse enclosure.
08/11/2026 ENGR Paving Partial Pass Parking stalls and PAALs West of building 3: AB elevations, compaction, and slopes are good; okay to pave.
Parking stalls South of building 3: AB elevations, compaction, and slopes are good; okay to pave.
Main entrance and drive off of Old Vail: AB needs adjustments, will recheck this area.
PAAL South of building 3: AB not checked yet.
08/12/2026 ENGR Paving Partial Pass Main entrance off of Old Vail: AB elevation, compaction, and slopes are good.
Main PAAL from Old Vail: AB elevation, compaction, and slopes are good.
PAAL South of building 3: AB elevation, compaction, and slopes are good.
All AB is good at this point. Good to complete paving.
08/18/2026 ENGR Paving Passed Asphalt pavement is complete throughout. Surfaces, slopes, and curb reveals are good. Paving is complete in accordance with approved plans.