Permit: TC-COM-0925-01779
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
10039 E OLD VAIL RD
Address NEW:
10039 E OLD VAIL RD
Apply Date:
09/29/2025
Applicant:
Andrea Leonard
Description:
New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Permit Reviews
Permit Number - TC-COM-0925-01779
Permit Status: Needs resubmittal
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 12/10/2025 | RESTAMP - COMMERCIAL v.1 | 12/15/2025 | APPROVED |
| 12/15/2025 | ADMINISTRATIVE v.1 | 12/15/2025 | REQUIRES RESUBMIT |
| 09/03/2026 | SPECIAL INSPECTION REVIEW v.1 | 09/09/2026 | REQUIRES RESUBMIT |
| 01/07/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 01/15/2026 | APPROVED |
| 04/27/2026 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 05/04/2026 | APPROVED |
| 09/29/2025 | COMMERCIAL REVIEW - FULL v.1 | 10/23/2025 | REQUIRES RESUBMIT |
| 10/31/2025 | COMMERCIAL REVIEW - FULL v.2 | 11/24/2025 | REQUIRES RESUBMIT |
| 01/15/2026 | ADMINISTRATIVE v.2 | 01/15/2026 | APPROVED |
| 12/04/2025 | COMMERCIAL REVIEW - FULL v.3 | 12/10/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0925-01779
Permit Status: Needs resubmittal
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 01/07/2026 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 01/07/2026 | SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED. |
| 01/07/2026 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
| 09/22/2026 | WATER STERILIZATION REPORT IS REQUIRED. |
Conditions
Permit Number - TC-COM-0925-01779
Permit Status: Needs resubmittal
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
| Date | Description | Comments |
|---|---|---|
| 09/29/2025 | Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512 | |
| 09/29/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 09/29/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 09/29/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0925-01779
Permite Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Outstanding Inspections - 13
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2026 | COT - HCBU - Preslab | N/A | Partial Pass | Partial pass for footing foundation on building 2 |
| 05/19/2026 | COT - LCBU - Roof Nailing | N/A | Canceled | 5-19-26; canceled by contractor. Need to inspect parapet correction and installation of crickets. |
| 06/08/2026 | COT - HCBU - Framing | N/A | Canceled | 6-8-26: canceled |
| 06/03/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved. |
| 06/03/2026 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved. |
| 06/24/2026 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 6-24-26: 2" domestic copper lines above ceiling which extends from northwest wall of Suite 191 verified under test at 94 psi and 1/2" copper line (hose bib) located at west exterior wall of Suite 101 verified under test at 98 psi. Okay to continue with construction at progress areas. |
| 09/16/2026 | COT - HCME - Mechanical Underground | N/A | Not Applicable | 9/16/26: not applicable. |
| 08/06/2026 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | |
| 06/03/2026 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved. |
| 09/17/2026 | ENGR Engineering Final | N/A | Not Ready | Site not complete. |
| 09/17/2026 | COT - HCBU - CofO | N/A | Re-inspection required | 9/17/26: partial pass pending gas meter installation together with outstanding conditions. And engineering final. |
| 09/28/2026 | COT - HCBU - Building Final | N/A | Partial Pass | 9/28/26: Partial pass pending conditions |
| 08/25/2026 | BULD - Electrical Clearance | N/A | Re-inspection required | 8-25-26: not ready. |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0925-01779
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Completed Inspections - 18
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/03/2026 | COT - LCBU - Roof Nailing | Passed | ||
| 07/10/2026 | COT - HCBU - Framing | Passed | ||
| 09/10/2026 | COT - HCBU - Excavation/Rebar/Zoning | Passed | 9/10/26: reinforcement at patio verified per plans/details. Okay for concrete placement. | |
| 09/16/2026 | COT - BULD - SWG Clearance | Passed | 9/16/26: okay to install gas meter. SWG Clearance issued. Note: no interior gas lines. Any construction related with gas will be completed under Tenant Improvement Permit. |
|
| 09/16/2026 | COT - HCEL - Electrical Underground | Passed | 9/16/26: electrical underground approved. | |
| 09/16/2026 | COT - HCME - Mechanical Above Ceiling | Passed | 9/16/26: mechanical above ceiling approved. | |
| 09/16/2026 | COT - HCME - Mechanical Intermediate | Passed | 9/16/26: mechanical intermediate approved. | |
| 09/16/2026 | COT - HCME - Mechanical Progress | Passed | 9/16/26: mechanical progress approved. | |
| 09/16/2026 | COT - HCPL - Rough Soil | Passed | 9/16/26: previously inspected & approved. | |
| 09/16/2026 | COT - HCBU - Building Above Ceiling | Passed | 9/16/26: previously inspected & approved. | |
| 09/16/2026 | COT - HCEL - Electrical Progress | Passed | 9/16/26: electrical progress approved. | |
| 09/16/2026 | COT - HCME - Mechanical Final | Passed | 9/16/26: mechanical final approved. | |
| 09/17/2026 | COT - HCME - Venting | Passed | 9/17/26: approved. | |
| 09/17/2026 | COT - HCPL - Sewer | Passed | 9/17/26: approved. | |
| 09/17/2026 | COT - FCON - Sprinkler - Final | Passed | ||
| 09/17/2026 | TRSP - ROW - Notice of Completion | Passed | shell is completed with no impact to right of way, all traffic control devices removed, approved | |
| 09/17/2026 | COT - FCON - Fire - Final | Passed | ||
| 09/17/2026 | COT - FCON - Alarm - Final | Passed |