Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Needs Resubmittal
Type:
Commercial Building
Address NEW:
10039 E OLD VAIL RD
Apply Date:
09/29/2025
Applicant:
Andrea Leonard
Description:
New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181

Permit Reviews

Permit Number - TC-COM-0925-01779
Permit Status: Needs resubmittal
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Start Date Submittal Complete Date Status  
12/10/2025 RESTAMP - COMMERCIAL v.1 12/15/2025 APPROVED Review Details
12/15/2025 ADMINISTRATIVE v.1 12/15/2025 REQUIRES RESUBMIT Review Details
09/03/2026 SPECIAL INSPECTION REVIEW v.1 09/09/2026 REQUIRES RESUBMIT Review Details
01/07/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 01/15/2026 APPROVED Review Details
04/27/2026 BUILDING DEFERRED SUBMITTAL REVIEW v.1 05/04/2026 APPROVED Review Details
09/29/2025 COMMERCIAL REVIEW - FULL v.1 10/23/2025 REQUIRES RESUBMIT Review Details
10/31/2025 COMMERCIAL REVIEW - FULL v.2 11/24/2025 REQUIRES RESUBMIT Review Details
01/15/2026 ADMINISTRATIVE v.2 01/15/2026 APPROVED Review Details
12/04/2025 COMMERCIAL REVIEW - FULL v.3 12/10/2025 APPROVED Review Details

Outstanding Activity Conditions

Permit Number - TC-COM-0925-01779
Permit Status: Needs resubmittal
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Outstanding Activity Conditions - 4
Date Name
01/07/2026 SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED.
01/07/2026 SPECIAL INSPECTION FOR STRUCTURAL WELDING IS REQUIRED.
01/07/2026 SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED.
09/22/2026 WATER STERILIZATION REPORT IS REQUIRED.

Conditions

Permit Number - TC-COM-0925-01779
Permit Status: Needs resubmittal
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Date Description Comments
09/29/2025 Please contact Pima County Addressing to resolve issue. Addressing@pima.gov or 520-724-9512
09/29/2025 Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact.
09/29/2025 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900.
09/29/2025 A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit.

Outstanding Inspections

Permit Status: Needs Resubmittal
Permit Number: TC-COM-0925-01779
Permite Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Outstanding Inspections - 13
Last Inspection Date Description Inspector Results Comments
02/27/2026 COT - HCBU - Preslab N/A Partial Pass Partial pass for footing foundation on building 2
05/19/2026 COT - LCBU - Roof Nailing N/A Canceled 5-19-26; canceled by contractor. Need to inspect parapet correction and installation of crickets.
06/08/2026 COT - HCBU - Framing N/A Canceled 6-8-26: canceled
06/03/2026 COT - HCBU - Excavation/Rebar/Zoning N/A Partial Pass 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved.
06/03/2026 COT - HCEL - Electrical Underground N/A Partial Pass 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved.
06/24/2026 COT - HCME - Mechanical Progress N/A Partial Pass 6-24-26: 2" domestic copper lines above ceiling which extends from northwest wall of Suite 191 verified under test at 94 psi and 1/2" copper line (hose bib) located at west exterior wall of Suite 101 verified under test at 98 psi. Okay to continue with construction at progress areas.
09/16/2026 COT - HCME - Mechanical Underground N/A Not Applicable 9/16/26: not applicable.
08/06/2026 COT - HCBU - Building Above Ceiling N/A Partial Pass
06/03/2026 COT - HCEL - Electrical Progress N/A Partial Pass 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved.
09/17/2026 ENGR Engineering Final N/A Not Ready Site not complete.
09/17/2026 COT - HCBU - CofO N/A Re-inspection required 9/17/26: partial pass pending gas meter installation together with outstanding conditions. And engineering final.
09/28/2026 COT - HCBU - Building Final N/A Partial Pass 9/28/26: Partial pass pending conditions
08/25/2026 BULD - Electrical Clearance N/A Re-inspection required 8-25-26: not ready.

Completed Inspections

Permit Status: Needs Resubmittal
Permit Number: TC-COM-0925-01779
Permit Description: New ground-up shell building. all site conditions per development plan TD-DEV-0725-00181
Total Completed Inspections - 18
Date Description Inspector Results Comments
06/03/2026 COT - LCBU - Roof Nailing Passed
07/10/2026 COT - HCBU - Framing Passed
09/10/2026 COT - HCBU - Excavation/Rebar/Zoning Passed 9/10/26: reinforcement at patio verified per plans/details. Okay for concrete placement.
09/16/2026 COT - BULD - SWG Clearance Passed 9/16/26: okay to install gas meter. SWG Clearance issued.
Note: no interior gas lines. Any construction related with gas will be completed under Tenant Improvement Permit.
09/16/2026 COT - HCEL - Electrical Underground Passed 9/16/26: electrical underground approved.
09/16/2026 COT - HCME - Mechanical Above Ceiling Passed 9/16/26: mechanical above ceiling approved.
09/16/2026 COT - HCME - Mechanical Intermediate Passed 9/16/26: mechanical intermediate approved.
09/16/2026 COT - HCME - Mechanical Progress Passed 9/16/26: mechanical progress approved.
09/16/2026 COT - HCPL - Rough Soil Passed 9/16/26: previously inspected & approved.
09/16/2026 COT - HCBU - Building Above Ceiling Passed 9/16/26: previously inspected & approved.
09/16/2026 COT - HCEL - Electrical Progress Passed 9/16/26: electrical progress approved.
09/16/2026 COT - HCME - Mechanical Final Passed 9/16/26: mechanical final approved.
09/17/2026 COT - HCME - Venting Passed 9/17/26: approved.
09/17/2026 COT - HCPL - Sewer Passed 9/17/26: approved.
09/17/2026 COT - FCON - Sprinkler - Final Passed
09/17/2026 TRSP - ROW - Notice of Completion Passed shell is completed with no impact to right of way, all traffic control devices removed, approved
09/17/2026 COT - FCON - Fire - Final Passed
09/17/2026 COT - FCON - Alarm - Final Passed

Documents

File Name Document Type  
BUILDING 3 TRUSS DEFERRED SUBMITTAL COMBINED_V1.PDF DOCUMENTS VIEW
COFT - PDSD - PERMIT CARD (SSRS).PDF DOCUMENTS VIEW
OVID - BLDGS 3 SI CERTS-2026-01-06_V1.PDF DOCUMENTS VIEW
2_BUILDING ENVELOPE COMCHECK_V1.PDF DOCUMENTS VIEW
2_GEOTECHNICAL REPORT_V1.PDF DOCUMENTS VIEW
2_STRUCTURAL CALCULATIONS_V2.PDF DOCUMENTS VIEW
CONS-3_PLAN SET_V3.PDF DOCUMENTS VIEW