Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 05/19/2026 |
COT - HCBU - Framing |
|
Re-inspection required |
5-19-26: post to wood beam requires MST 48 strap and H3 clip at each side, missing nails throughout south, east, west & north shear walls- see schedule for details, nails cannot be closer than 3/8" from the edge or splice and cannot over penetrate more than 1/16", nail all protruding nails flush on east exterior sheathing, missing nuts at south end and tighten all anchor bolts, add anchor bolts to marked locations, add shot pins to marked locations. Have framers make corrections and review all details before scheduling inspection. Stopped inspection-additional items may be added. |
| 05/22/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5-22-26: corrections to parapet nailing approved. Nailing for crickets approved-okay to dry-in roof. |
| 06/08/2026 |
COT - HCBU - Framing |
|
Canceled |
6-8-26: canceled |
| 06/12/2026 |
COT - HCBU - Framing |
|
Partial Pass |
6-12-26: partial pass nailing on exterior sheathing |
| 06/15/2026 |
COT - HCBU - Framing |
|
Canceled |
6-15-26: canceled by contractor. |
| 06/23/2026 |
COT - HCBU - Framing |
|
Re-inspection required |
6-23-26: hold downs missing at interior walls-see detail 12, missing Simpson Cs16 strap x 30" long at top plate at intersecting wall at continuous shear wall-see detail 26, missing hold down at shear wall corner-see detail 23, add hold downs and A34'S per detail 35, add nails to top plate splice at southwest wall-corner of patio. |
| 06/25/2026 |
COT - HCBU - Framing |
|
Partial Pass |
6-25-26: corrections made, minus installation of hold-downs, anchor bolts at marked locations and at pour back areas, add double studs at the ends of walls as discussed. Okay to continue with construction at progress areas and mentioned above items requiring corrections will be verified prior to covering up any walls. |
| 07/01/2026 |
COT - HCBU - Framing |
|
Canceled |
7-1-26: canceled by contractor. |
| 07/02/2026 |
COT - HCBU - Framing |
|
Re-inspection required |
7-2-26: missing hold-downs at typical wood stud bearing wall & wood stud shear-see S1.3/ Detail 35 & add framing clips as outlined on detail. Pour back at interior columns was never inspected prior to pour, therefore, submit the 3rd party report to the city for review and provide a video/pictures for anchors & plate at light pole cage south of STE. 100. |
| 07/09/2026 |
COT - HCBU - Framing |
|
Partial Pass |
|
| 07/10/2026 |
COT - HCBU - Framing |
|
Passed |
|