Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/02/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 6/2/26 Ok to pour 1,2,6, 13, 14, 15. |
|
| 06/03/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved. | |
| 06/22/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 6/22/2026: light pole reinforcement and electrical underground/ grounding approved at light poles (16-22) okay for concrete placement. | |
| 06/24/2026 | COT - HCBU - Excavation/Rebar/Zoning | Re-inspection required | 6-24-26: reinforcement for light pole cage located south of Suite 101 not per plans- #3 ties measured at 18" versus the required 10" o.c.. Also, missing anchor bolts and remove all loose fill/ debris from footing to allow for 6" clearance at bottom. | |
| 07/01/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 7-1-26: missing anchor bolts & plate at light pole cage located south of Suite 101 of Building 3 approved. Excavation/reinforcement okay. | |
| 07/23/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 7-23-26: Exterior steel column at footing & Interior steel column at G/L: 1/ B verified per S3.0/detail 106 & 2/B verified per S3.0/detail 104. Okay for concrete placement. |