Permit: TC-COM-0925-01779

Parcel: 141186020


Addresses:

10039 E OLD VAIL RD

Inspection Status: Partial Pass

Inspection History: COT - HCEL - Electrical Underground 

Date Description Inspector Results Comments
03/02/2026 COT - HCEL - Electrical Underground  Partial Pass 3/2/26: Electrical underground at under slab for exterior lighting approved ok to backfill. UFER approved
04/17/2026 COT - HCEL - Electrical Underground  Partial Pass 4-17-26: underground electrical site-verified 1-1" schedule 40 conduit located on west side of site for future light poles. Okay to backfill approximately 60' of trench using shading materials.
04/20/2026 COT - HCEL - Electrical Underground  Partial Pass 4-20-26: verified trench depth at 2' on 4 -1" schedule 40 electrical conduits for site lighting. Conduits run from south to north and east to exterior home run tie in located outside of Building 3. Okay to backfill approximately 400' of trench using shading materials.
04/22/2026 COT - HCEL - Electrical Underground  Partial Pass 4-22-26: verified trench depth at approximately 22" on a 1" schedule electrical conduit for site lighting on south end. Conduit runs east to west- okay to backfill 158' of trench using shading materials and another section on west side of building where conduit runs north to south -okay to backfill approximately 60' of trench with shading materials.
05/14/2026 COT - HCEL - Electrical Underground  Partial Pass 5-14-26: 4-4" schedule 40 electrical conduits on east side building. Conduit runs north to south-okay to backfill progress areas using shading materials.
05/18/2026 COT - HCEL - Electrical Underground  Partial Pass 5/18/2026 Partial pass. X2 1 1/4” schedule 40 at 24” depth
X2 1” schedule 40 all at east end of project. Stations 3004.75-3004.13-3004-18 end of run is backside of building 3. Okay to backfill progress areas. Shading required.
05/22/2026 COT - HCEL - Electrical Underground  Partial Pass 5-22-26: trench depth verified for 13-1" schedule 40 conduits for future EV chargers running north to south on west side. Okay to backfill approximately 300' of trench using shading materials.
06/02/2026 COT - HCEL - Electrical Underground  Partial Pass 6.2.26
Light poles
06/03/2026 COT - HCEL - Electrical Underground  Partial Pass 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved.
06/09/2026 COT - HCEL - Electrical Underground  Partial Pass 6-9-26: 1" Schedule 40 electrical conduit for light poles stemming north to south and west of Building 3. Okay to backfill approximately 130' of open trench using shading materials.
06/22/2026 COT - HCEL - Electrical Underground  Partial Pass 6/22/2026: light pole reinforcement and electrical underground/ grounding approved at light poles (16-22) okay for concrete placement.