Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Preslab
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2026 | COT - HCBU - Preslab | Partial Pass | Partial pass for footing foundation on building 2 | |
| 03/02/2026 | COT - HCBU - Preslab | Partial Pass | 3/2/26: partial pass for footings only at building 3, per approved plans, | |
| 04/02/2026 | COT - HCBU - Preslab | Partial Pass | 4-2-26: excavation/Reinforcement for stem wall footings & interior steel column footings at Building 3/ Section A & B verified per S2.11/S2.12 Details: F1, F2, F3, F5, C1, C2, C3, C4, 107, 102, 103, 105, 107, 109, 104, 107A, 108A. Okay for concrete placement at progress areas. | |
| 04/08/2026 | COT - HCBU - Preslab | Not Ready | 4-8-26: not ready- pending vapor barrier/ pad reinforcement. | |
| 04/08/2026 | COT - HCBU - Preslab | Passed | 4/8/26 Reinforcements and vapor barrier per plan. Ok to pour. |