Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/12/2026 | COT - HCEL - Electrical Progress | Partial Pass | 3-12-26: Building 3-verified trench depth on 4" schedule 40 communication riser, 2-2 1/2" schedule 40 conduits for p1, p2, p3 feeders, SES -4" schedule 40 conduits, 1 1/2 " panel hp-6-1" & 1-!/2"conduits, 3-1" conduits for pv chargers. Okay to backfill approximately 90' trench. | |
| 03/17/2026 | COT - HCEL - Electrical Progress | Not Ready | ||
| 03/27/2026 | COT - HCEL - Electrical Progress | Partial Pass | 3-27-26: verified trench depth at 2' for 2" electrical schedule 40 conduits at Building 3. Electrical conduits are for phone boards-okay to backfill progress areas | |
| 06/03/2026 | COT - HCEL - Electrical Progress | Partial Pass | 6/3/26: light pole reinforcement and electrical underground/ grounding approved at light poles (6,7,8,9,10,11,12), GROUNDING AT Service entrance approved. | |
| 06/23/2026 | COT - HCEL - Electrical Progress | Canceled | 6-23-26: canceled | |
| 06/24/2026 | COT - HCEL - Electrical Progress | Partial Pass | 6-24-26: partial pass for in wall rough electrical and lighting above ceiling at canopies. Secure mc cabling within 12" of box proximity, ground metal boxes above ceiling, and make sure that all receptacles contain grounding nut and pigtail. | |
| 06/30/2026 | COT - HCEL - Electrical Progress | Partial Pass | 6-30-26: fire foam through penetrations at exterior shear walls above doors and fire foam rigid conduit for exterior lighting. | |
| 07/02/2026 | COT - HCEL - Electrical Progress | Partial Pass | 7-2-26: see previous notes from 6/30/26. | |
| 07/07/2026 | COT - HCEL - Electrical Progress | Partial Pass | 7.7.26 Fire foamed all penetrations called out on 6/30/26. |