Permit: TC-COM-0823-01930
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
1501 E METRIC PL
Address NEW:
1501 E METRIC PL
Apply Date:
08/07/2023
Applicant:
Brad Hoge
Description:
CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
Permit Reviews
Permit Number - TC-COM-0823-01930
Permit Status: Needs resubmittal
Permit Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/11/2023 | REQUIRES RESUBMIT |
| 10/31/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/15/2023 | APPROVED |
| 06/25/2026 | COMMERCIAL REVIEW - FULL v.1 | N/A | REQUIRES RESUBMIT |
| 11/15/2023 | RESTAMP - COMMERCIAL v.1 | 11/17/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0823-01930
Permit Status: Needs resubmittal
Permit Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
Total Outstanding Activity Conditions - 10
| Date | Name |
|---|---|
| 09/11/2026 | Prior to Final - Required Documents - AIR BALANCING REPORT IS REQUIRED. |
| 09/11/2026 | Prior to Final - Special Inspections - SPECIAL INSPECTION FOR OUTDOOR LIGHTING IS REQUIRED. |
| 09/11/2026 | WATER STERILIZATION REPORT IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 11/15/2023 | Masonry Inspection Report submittal review is required. |
Conditions
Permit Number - TC-COM-0823-01930
Permit Status: Needs resubmittal
Permit Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
| Date | Description | Comments |
|---|---|---|
| 08/08/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0823-01930
Permite Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
Total Outstanding Inspections - 18
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2025 | COT - HCBU - Preslab | N/A | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) 1/16/25: reinforcement per plan at (19) column footings GL A-D.2/1.2-7. Ok for concrete placement. 1/17/24: reinforcement per plan at slab column footings GL A-D.5/1-7 ok for concrete placement 1/21/25: reinforcement per plan at (16) column footings GL A-D.3/8-12 |
| 01/21/2026 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 1-21-26: reinforcement at cmu wall verified per plans-okay to grout top out 12-16' at the peak. |
| 01/27/2026 | COT - HCPL - Sewer | N/A | Partial Pass | 1-27-26: precon meeting discuss sewer requirements & testing. |
| 02/09/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Drainage trough at loading dock area; slab area at trash enclosure (rebar reenforcement). Ok to place concrete in progress areas (3000 psi rated). |
| 03/31/2026 | COT - HCBU - Roof Nailing | N/A | Re-inspection required | 3-31-26: missing anchor bolts for SW1 together with HTT5's, 2 king studs are required for opening greater than 6' at ml1/ml2, provide ladder for roof access together with truss calculations, provide revisions for metal interior framing-stopped inspection additional items may be noted. |
| 11/18/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 11-18-25: verified a 3" Schedule 40 electrical conduit to feed building. Okay to backfill approximately 30' of trench and continue with construction at progress areas. |
| 05/13/2026 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 5-13-26: complete flex tie in & above ceiling framing. Will inspect pookie and supports at upcoming inspections. |
| 06/12/2026 | COT - HCBU - Building Progress | N/A | Partial Pass | 6-12-26: partial pass pending intermediates at mezzanine. |
| 06/12/2026 | COT - HCBU - Framing | N/A | Partial Pass | 6-12-26: partial pass for mezzanine framing-pending osb sheathing and nails along joints/edges of decking. Wood sheathing at office areas approved. Interior partition walls are approved. Please provide an RFI to address all exterior wall metal framing. |
| 06/24/2026 | COT - HCBU - Exterior Clips/Sheathing | N/A | Partial Pass | |
| 11/25/2025 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Plumbing underground: waste lines (2” - 4”) at South side of structure under hydro test, approximately 35 feet from structure. Ok to cover progress areas. |
| 09/11/2026 | COT - HCBU - Building Final | N/A | Not Ready | 9/11/26: PERMIT REQUIRED FOR RACKING SYSTEM, PERMIT REQUIRES Resubmittal FOR OUTDOOR LIGHT REQUIREMENTS. WATER STERILIZATION REQUIRED, OUTDOOR LIGHT SIC REQUIRED, VENTILATION REQUIRED AT WEARHOUSE (REVISION IS REQUIRED). |
| 09/11/2026 | COT - HCBU - Building Above Ceiling | N/A | Not Ready | 9/11/26: we will inspect rooftop at finals. |
| 09/11/2026 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 9/11/26: office areas-tape tears to above ceiling at area 112 & 107. |
| 09/11/2026 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 9/11/26: plumbing above ceiling at office areas approved. |
| 09/14/2026 | COT - HCEL - Electrical Above Ceiling | N/A | Partial Pass | 9/14/2026 office areas all approved. Okay to proceed with progress areas. |
| 06/03/2026 | COT - HCEL - Electrical Intermediate | N/A | Canceled | 6-3-26: canceled by contractor. |
| 09/16/2026 | BULD - Electrical Clearance | N/A | Partial Pass | 9/16/26: Verified grounding/bonding. Pending feeders from transformer to CT can, add plastic bushings where needed at conduits feeding panels to protect AWG wires, and duct seal at exterior side to main panel. Schedule clearance after TEP installs transformer and all feeders are landed. |
Completed Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0823-01930
Permit Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/24/2026 | COT - HCPL - Plumbing Intermediate | Passed | ||
| 09/11/2026 | COT - HCME - Mechanical Progress | Passed | 9/11/26: mechanical progress office areas approved. |
Scheduled Inspections
Scheduled Inspections - TC-COM-0823-01930
Status: Needs Resubmittal
Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
| Scheduled Date | Description | Entered By | Entered Date |
|---|---|---|---|
| 09/21/2026 | BULD - Electrical Clearance | Scheduled |