Permit: TC-COM-0823-01930
Permit Details
Status:
Inspections
Type:
Commercial Building
Address:
1501 E METRIC PL
Address NEW:
1501 E METRIC PL
Apply Date:
08/07/2023
Applicant:
Brad Hoge
Description:
CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
Permit Reviews
Permit Number - TC-COM-0823-01930
Permit Status: Inspections
Permit Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/08/2023 | COMMERCIAL REVIEW - FULL v.1 | 09/11/2023 | REQUIRES RESUBMIT |
| 10/31/2023 | COMMERCIAL REVIEW - FULL v.2 | 11/15/2023 | APPROVED |
| 11/15/2023 | RESTAMP - COMMERCIAL v.1 | 11/17/2023 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0823-01930
Permit Status: Inspections
Permit Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 11/15/2023 | SPECIAL INSPECTION FOR BOLTS INSTALLED IN CONCRETE IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 11/15/2023 | SPECIAL INSPECTION FOR HIGH STRENGTH BOLTING IS REQUIRED. |
| 11/15/2023 | Masonry Inspection Report submittal review is required. |
Conditions
Permit Number - TC-COM-0823-01930
Permit Status: Inspections
Permit Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
| Date | Description | Comments |
|---|---|---|
| 08/08/2023 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment. |
Outstanding Inspections
Permit Status: Inspections
Permit Number: TC-COM-0823-01930
Permite Description: CITIZENS TRANSFER AND STORAGE WAREHOUSE AND OFFICES
Total Outstanding Inspections - 17
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2025 | COT - HCBU - Preslab | N/A | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) 1/16/25: reinforcement per plan at (19) column footings GL A-D.2/1.2-7. Ok for concrete placement. 1/17/24: reinforcement per plan at slab column footings GL A-D.5/1-7 ok for concrete placement 1/21/25: reinforcement per plan at (16) column footings GL A-D.3/8-12 |
| 01/21/2026 | COT - HCBU - Masonry Pregrout | N/A | Partial Pass | 1-21-26: reinforcement at cmu wall verified per plans-okay to grout top out 12-16' at the peak. |
| 01/27/2026 | COT - HCPL - Sewer | N/A | Partial Pass | 1-27-26: precon meeting discuss sewer requirements & testing. |
| 02/09/2026 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Drainage trough at loading dock area; slab area at trash enclosure (rebar reenforcement). Ok to place concrete in progress areas (3000 psi rated). |
| 03/31/2026 | COT - HCBU - Roof Nailing | N/A | Re-inspection required | 3-31-26: missing anchor bolts for SW1 together with HTT5's, 2 king studs are required for opening greater than 6' at ml1/ml2, provide ladder for roof access together with truss calculations, provide revisions for metal interior framing-stopped inspection additional items may be noted. |
| 11/18/2025 | COT - HCEL - Electrical Underground | N/A | Partial Pass | 11-18-25: verified a 3" Schedule 40 electrical conduit to feed building. Okay to backfill approximately 30' of trench and continue with construction at progress areas. |
| 05/13/2026 | COT - HCPL - Plumbing Above Ceiling | N/A | Re-inspection required | 5-13-26: in wall DWV/domestic not under test, in wall supports required and installation of hose bib. We will inspect above ceiling after these items are inspected & approved. |
| 05/13/2026 | COT - HCME - Mechanical Above Ceiling | N/A | Partial Pass | 5-13-26: complete flex tie in & above ceiling framing. Will inspect pookie and supports at upcoming inspections. |
| 05/13/2026 | COT - HCPL - Plumbing Intermediate | N/A | Re-inspection required | 5-13-26: DWV not under test & provide supports for DWV/PCV. |
| 05/13/2026 | COT - HCEL - Electrical Above Ceiling | N/A | Re-inspection required | 5-13-26: will inspect after approving in wall electrical. |
| 05/13/2026 | COT - HCME - Mechanical Intermediate | N/A | Partial Pass | 5-13-26: complete flex tie in & above ceiling framing. Will inspect pookie and supports at upcoming inspections. |
| 06/03/2026 | COT - HCEL - Electrical Intermediate | N/A | Canceled | 6-3-26: canceled by contractor. |
| 06/08/2026 | COT - HCME - Mechanical Progress | N/A | Partial Pass | 6-8-26: secure mechanical whips and complete tie-ins to flex. |
| 11/25/2025 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Plumbing underground: waste lines (2” - 4”) at South side of structure under hydro test, approximately 35 feet from structure. Ok to cover progress areas. |
| 06/08/2026 | COT - HCBU - Building Progress | N/A | Partial Pass | 6-8-26: secure mechanical whips and complete tie-ins to flex. |
| 06/08/2026 | COT - HCBU - Exterior Clips/Sheathing | N/A | Re-inspection required | 6-8-26: missing A34 at warehouse to office entrance above door header,seal penetrations at marked areas, add shot pins with 1/2" disks at marked locations, missing nails at wood top plate splice, remove drywall at northeast shear wall to verify nailing at sheathing, missing bracing at 4' intervals and secure bent web of mtl. Stud brace to,to- track & to bottom flange of roof truss for walls parallel or perpendicular to truss, missing blocking mid height at wood framing, pending revision approval- city is requesting full set of metal framing plans/details. |
| 06/08/2026 | COT - HCBU - Framing | N/A | Re-inspection required | 6-8-26: missing A34 at warehouse to office entrance above door header,seal penetrations at marked areas, add shot pins with 1/2" disks at marked locations, missing nails at wood top plate splice, remove drywall at northeast shear wall to verify nailing at sheathing, missing bracing at 4' intervals and secure bent web of mtl. Stud brace to,to- track & to bottom flange of roof truss for walls parallel or perpendicular to truss, missing blocking mid height at wood framing, pending revision approval- city is requesting full set of metal framing plans/details. |