Permit Review Detail
Review Status: Requires Resubmit
Review Details: COMMERCIAL REVIEW - FULL v.1
Permit Number - TC-COM-0823-01930
Review Name: COMMERCIAL REVIEW - FULL v.1
Review Status: Requires Resubmit
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/15/2023 | Site Engineering | APPROVED | |||
| 08/09/2023 | Site Zoning | APPROVED | |||
| 09/11/2023 | Water - PDSD | APPROVED | |||
| 09/11/2023 | Bldg Permits - Post Review Express | PENDING ASSIGNMENT | |||
| 08/31/2023 | External Reviewers - SAFEBuilt | REQUIRES RESUBMIT | Structural(S) Reviewer Daljit Benipal dbenipal@safebuilt.com Denied Reason: Date Completed : 8/30/2023 6:53:41 PM 1. Structural steel, components and fasteners that are exposed are to be protected against corrosion in accordance with AISC 360 Section B.13 as indicated in IBC 2018 Section 2203.1. 2. Designer is to coordinate venting and drainage hole requirements for HSS tube members that are galvanized using the hot-dip galvanizing process. Provide for plugs as needed. ◦ AWS D-19.0 calls for welds on galvanized steel to be free of zinc. Field welds on galvanized parts requires the removal of the zinc coating in the area of weld. Provide zinc paint (approved by the galvanizer) and apply as required to the weld and steel area to provide protection. 3. Provide galvanized bolts for the framing connections of the members that are galvanized. Submit a response letter addressing these correction items and provide bubbles on the revisions to the drawings. Building(B) Reviewer Andrew Bevis abevis@safebuilt.com Denied Reason: Date Completed : 8/14/2023 2:47:59 PM 1. Sheet C1: The provided allowable area is incorrect area for a single story S-1 occupancy of type V-B construction protected by a sprinkler system. Provide a correct allowable area in accordance with Table 506.2. 2. Sheet C1: The cover sheet indicates the use of a frontage increase, however ,the calculations have not been provided. Provide the detailed frontage increase calculations. 3. Sheet C1: The floor plans indicate the presence of other uses besides the S-1 occupancy (B and F-1). It appears that non-separated mix use is the mix use strategy that has been chosen. However, when this method is chosen, the structure is is limited to the most restrictive allowable area in accordance with Section 503.1. This will affect the allowable area/frontage increase calculation. Please update all allowable area calculations. 4. General: No egress plans have been provided. Provide detailed egress plans. 5. Sheet A1.0: The floor plans indicated the presence of woodshop. 6. Sheet A1.4: The RCP's do not indicate the location of egress illumination and exit signage. Provide the location of the egress illumination and exit lighting in accordance with Section 1008 and 1013. 7. General: Provide a section through the storage area stairs and all associated details. 8. General: Provide detailed plumbing fixture calculations. 9. General: Provide a section through storage area railing. Mechanical(M) Reviewer Neil Samaan nsamaan@safebuilt.com Conditionally Approved Reason: Date Completed : 8/13/2023 9:36:47 PM Approved/subject to field approval for offices and the storage room #101only the rest of facility is not in the scope of the mechanical review the only mechanical submitted for review is the offices and storage room #101 Electrical(E) Reviewer Ron Ross rross@safebuilt.com Denied Reason: Date Completed : 8/22/2023 12:54:58 PM Electrical Review of Citizens Transfer and Storage By: Ron Ross PE E-3.01 ELECTRICAL POWER PLAN: Keynotes 4 and 5 not shown. Could not locate panel L3. Be sure to comply with NEC 110.26 working clearance requirements. E-4.02 ELECTRICAL SCHEDULES ?? DETAILS: Electrical mechanical schedule is missing Fork Lift Charging stations, specifically the wire size required. Plumbing(P) Reviewer Perry Hendershott phendershott@safebuilt.com Denied Reason: Date Completed : 8/23/2023 9:20:58 PM First Plumbing Review: 1). Need to address Building plan review comment #8 -IPC 403.1 2). Add gutter & downspout sizing calculations to plan page A1.6 -IPC 1106.3, 1106.6 3). Floor sinks on plan page P1.0 can't be located at the exterior. - IPC 1101.3 4). Ice machine floor sink missing from sanitary riser on plan P1.0 - IPC 106.3.1 5). Hose bibs need individual shut off valves on plan pages P1.1 & P2.1 -IPC 606.2 6). label the hot return line on plan pages P0.0, P1.1, P2.1 -IPC 106.3.1, 607.2 7). This occupancy type & load requires a high/low drinking fountain -IPC 403.1 8). Notes 1 & 2 on plan page P2.1 don't correlate to the riser diagram? -IPC 106.3.1 |
||
| 08/14/2023 | Fire New Construction | REVIEW COMPLETED | |||
| 08/08/2023 | PDSD Application Completeness Express | REVIEW COMPLETED |