Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date |
Description |
Inspector |
Results |
Comments |
| 09/16/2026 |
BULD - Electrical Clearance |
|
Partial Pass |
9/16/26: Verified grounding/bonding. Pending feeders from transformer to CT can, add plastic bushings where needed at conduits feeding panels to protect AWG wires, and duct seal at exterior side to main panel. Schedule clearance after TEP installs transformer and all feeders are landed. |
|
BULD - Electrical Clearance |
|
Scheduled |
|