| 01/08/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) | |
| 01/16/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) 1/16/25: reinforcement per plan at (19) column footings GL A-D.2/1.2-7. Ok for concrete placement. |
|
| 01/17/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) 1/16/25: reinforcement per plan at (19) column footings GL A-D.2/1.2-7. Ok for concrete placement. 1/17/24: reinforcement per plan at slab column footings GL A-D.5/1-7 ok for concrete placement |
|
| 01/21/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) 1/16/25: reinforcement per plan at (19) column footings GL A-D.2/1.2-7. Ok for concrete placement. 1/17/24: reinforcement per plan at slab column footings GL A-D.5/1-7 ok for concrete placement 1/21/25: reinforcement per plan at (16) column footings GL A-D.3/8-12 |
|
| 01/23/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) 1/16/25: reinforcement per plan at (19) column footings GL A-D.2/1.2-7. Ok for concrete placement. 1/17/24: reinforcement per plan at slab column footings GL A-D.5/1-7 ok for concrete placement 1/21/25: reinforcement per plan at (16) column footings GL A-D.3/8-12 1/23/25: reinforcement per plan at slab and dock wall retaining wall. |
|
| 01/31/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 1/8/25: reinforcement at loading dock footing per plan (per detail S3.2/315, S3.3/19, S3.3/25) 1/16/25: reinforcement per plan at (19) column footings GL A-D.2/1.2-7. Ok for concrete placement. 1/17/24: reinforcement per plan at slab column footings GL A-D.5/1-7 ok for concrete placement 1/21/25: reinforcement per plan at (16) column footings GL A-D.3/8-12 1/23/25: reinforcement per plan at slab and dock wall retaining wall. 1/31/25:reinforcement per plans at dock slab ok to proceed |
|
| 02/09/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | Drainage trough at loading dock area; slab area at trash enclosure (rebar reenforcement). Ok to place concrete in progress areas (3000 psi rated). | |
| 02/21/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 2-21-25, reinforcement for pedestals (details 309\310) verified as per approved plans. Okay to pour concrete. | |
| 03/05/2026 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 3-5-26: excavation/reinforcement at stem wall for covered patio garden & covered entry verified per S.1.1 Details 324, 326 and F33-Spread footing schedule. Okay for concrete placement at progress areas. | |
| 12/09/2025 | COT - HCBU - Excavation/Rebar/Zoning | Partial Pass | 12/9/2025 Footings for office space per detail 311 and 312. Vertical reinforcement per plan. Okay for concrete placement. |