Permit: TC-COM-0125-00202
Permit Details
Status:
Needs Resubmittal
Type:
Commercial Building
Address:
1680 E TUCSON MARKETPLACE BL
Address NEW:
1680 E TUCSON MARKETPLACE BL
Apply Date:
01/30/2025
Applicant:
Aaron Jewell
Description:
2nd Party - New construction hotel
Permit Reviews
Permit Number - TC-COM-0125-00202
Permit Status: Needs resubmittal
Permit Description: 2nd Party - New construction hotel
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 06/30/2025 | RESTAMP - COMMERCIAL v.1 | 07/01/2025 | APPROVED |
| 02/04/2025 | COMMERCIAL REVIEW - FULL v.1 | 02/04/2025 | REQUIRES RESUBMIT |
| 03/19/2025 | COMMERCIAL REVIEW - FULL v.4 | 04/15/2025 | REQUIRES RESUBMIT |
| 12/29/2025 | COMMERCIAL REVIEW - FULL REVISION v.2 | 01/15/2026 | REQUIRES RESUBMIT |
| 11/20/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 12/10/2025 | REQUIRES RESUBMIT |
| 02/07/2025 | COMMERCIAL REVIEW - FULL v.3 | 03/07/2025 | REQUIRES RESUBMIT |
| 10/07/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 10/29/2025 | APPROVED |
| 02/06/2025 | COMMERCIAL REVIEW - FULL v.2 | 02/06/2025 | REQUIRES RESUBMIT |
| 05/27/2025 | COMMERCIAL REVIEW - FULL v.5 | 06/19/2025 | REQUIRES RESUBMIT |
| 06/25/2025 | COMMERCIAL REVIEW - FULL v.6 | 06/30/2025 | APPROVED |
| 10/31/2025 | COMMERCIAL REVIEW - FULL REVISION v.1 | 11/13/2025 | APPROVED |
Outstanding Activity Conditions
Permit Number - TC-COM-0125-00202
Permit Status: Needs resubmittal
Permit Description: 2nd Party - New construction hotel
Total Outstanding Activity Conditions - 7
| Date | Name |
|---|---|
| 06/03/2025 | Applies to All: Deferred submittal documents must be submitted and approved prior to installation of construction elements included in deferred submittal documents. |
| 06/03/2025 | SPECIAL INSPECTION FOR CONCRETE INSTALLATION IS REQUIRED. |
| 06/03/2025 | SPECIAL INSPECTION FOR FIELD WELDING IS REQUIRED. |
| 06/03/2025 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. |
| 06/03/2025 | Masonry Inspection Report submittal review is required. |
| 06/03/2025 | SPECIAL INSPECTION FOR WOOD FRAMED DIAPHRAGMS AND SHEAR WALLS IS REQUIRED. |
| 09/18/2025 | Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy. For More Information visit https://www.pima.gov/1076/Sewer-Connection-Permits, To check your permit status https://permits.pima.gov/ |
Conditions
Permit Number - TC-COM-0125-00202
Permit Status: Needs resubmittal
Permit Description: 2nd Party - New construction hotel
| Date | Description | Comments |
|---|---|---|
| 02/03/2025 | Contractor with active Arizona Contractor's License for specified scope of work required prior to issuance of permit. Contractor must have a TDC Online account and be added to the permit as a contact. | |
| 02/06/2025 | Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. For review and assessment: apply online at https://permits.pima.gov/ or contact us at sewer@pima.gov, (520) 724-9900. | |
| 02/03/2025 | A Special Inspections Intermediate Certificate must be submitted and reviewed prior to issuance of this permit. |
Outstanding Inspections
Permit Status: Needs Resubmittal
Permit Number: TC-COM-0125-00202
Permite Description: 2nd Party - New construction hotel
Total Outstanding Inspections - 16
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2025 | COT - HCPL - Rough Soil | N/A | Partial Pass | Six inch main waste line and laterals at Level #1. Ok to cover progress areas. |
| 08/27/2025 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Partial Pass | Elevator shaft at 32’ - 36’. OK to grout progress areas. |
| 09/19/2025 | COT - HCPL - Sewer | N/A | Partial Pass | Information only for location and inspection requirements of man hole. |
| 10/28/2025 | COT - HCBU - Roof Nailing | N/A | Partial Pass | 10-28-25: corrections made for roof deck nailing. Okay to continue construction at progress areas. |
| 08/08/2025 | COT - FCON - Fire - Final | N/A | Re-inspection required | Riser/stub out approved to bury |
| 12/22/2025 | COT - HCEL - Electrical Progress | N/A | Partial Pass | 12-22-25: verified trench depth on 8-secondary 4" schedule 40 conduits together with 8-4" schedule 40 electrical primary conduits for building at north side of site. Okay to backfill trenching. |
| 01/14/2026 | COT - HCBU - Preslab | N/A | Re-inspection required | 1-14-26: this inspection must be called in under your development package plan. |
| 01/15/2026 | COT - HCBU - Interior Shear Bracing | N/A | Partial Pass | 1-15-26: corrections made to exterior sheathing except for room 433 and damaged section of south corridor at 1st floor. Okay to stucco wrap elsewhere. |
| 12/10/2025 | COT - HCPL - Plumbing Above Ceiling | N/A | Partial Pass | 12/10/25: DWV pressure test approved ok to remove plugs. In wall DWV requires stud-shoe or sister stud where bored more than 60% at nonbearing wall. Nail plates required throughout on exterior walls at corridor and on vertical stacks where plumbing comes within 1-1/4" from face of stud |
| 01/21/2026 | COT - FCON - Sprinkler - Final | N/A | Re-inspection required | OH pipes in units approved. Will need to hydrostatically test system when water is available. |
| 12/22/2025 | COT - HCEL - Electrical Above Ceiling | N/A | Re-inspection required | 12-22-25: rough electrical in wall /above ceiling-fire foam horizontal penetrations at party wall, add bank plates where closer than 1 1/4" from edges, finish rough in electrical from unit's 321/322 to north-awg wires must be made up at time of inspection. |
| 01/20/2026 | COT - HCPL - Plumbing Progress | N/A | Partial Pass | Plumbing above ceilings and in walls for room units on Level #4. Ok to insulate and cover walls. |
| 12/22/2025 | COT - HCBU - Exterior Clips/Sheathing | N/A | Re-inspection required | 12-22-25: unit 428-fix damaged sheathing adjacent to window, loose panel north wall of unit 433, loose panels at west wall of 431, west wall of 427, replace/repair gap between sheathing above window of unit 425-gap is 3/4", 421-East exterior wall loose, 419-west wall loose, 413-west wall south of window loose, 401-loose panels west wall south of window. |
| 08/14/2025 | COT - HCBU - Building Progress | N/A | Partial Pass | 8-14-25: reinforcement on CMU elevator enclosure verified per plans. Okay to grout 1st lift at 4'. |
| 02/02/2026 | COT - HCBU - Building Above Ceiling | N/A | Partial Pass | 2/2/26: first layer of 5/8" type-x approved installation on RESILIENT CHANNEL SYSTEMS at 4th and 3rd floor ceilings approved. Ok to proceed with second layer of 5/8" type-x. Ensure all fasteners are spaced per approved plans and fasteners shall be no closer than 3/8" from edge of gypsum board and shall not penetrate more than 1/8", |
| 12/23/2025 | COT - HCME - Mechanical Above Ceiling | N/A | Re-inspection required | 12/23/25: Exhaust ducts must be properly sealed and supported throughout on third floor, Boca plates required throughout at Exhaust duct, 4th floor was not walked (ceilings have been covered prior to inspection) please recall once access is available for above ceiling inspection. |