Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Progress
Permit Number - TC-COM-0125-00202
Inspection Description - COT - HCEL - Electrical Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/02/2026 | COT - HCEL - Electrical Progress | Partial Pass | 1-2-26: verified schedule 40 electrical conduit at grid line 17-southeast to southwest of site. Other half to include sections located at north EV were already buried. Therefore, upload photos as an attachment for review and okay to backfill inspected areas. | |
| 07/28/2025 | COT - HCEL - Electrical Progress | Partial Pass | Electric underground: Conduits at 1” - 4” from panels MDP, D, DP1, DP2 to SES Area. Ok to cover progress areas. | |
| 07/30/2025 | COT - HCEL - Electrical Progress | Partial Pass | 7-30-25:verified trench depth on 5 electrical Schedule 40 conduits from room's 147-153, 3-3", 1-2", 1-1 1/2", 1-1" . Also, inspected 15 secondary Schedule 40 conduits, 13-1" & 2- 1 1/2" & grounding/bonding system from MDP to SES and back to area 147-153. Okay to backfill progress areas. | |
| 12/08/2025 | COT - HCEL - Electrical Progress | Partial Pass | 12-8-25: in wall rough electrical on room's 401, 402, 404, 403, 405, 406, 407, 410, 409, 408, 411, 412, 413-check receptacle spacing at south wall-spacing cannot exceed 12', receptacle missing puddy pack on south wall. Okay to continue with construction at progress areas. Will check room 413 when ready. | |
| 12/15/2025 | COT - HCEL - Electrical Progress | Partial Pass | 3” electric conduit lines at approximately 150’ located at Northwest corner of structure to within 5’ of transformer. Ok to cover progress area. | |
| 12/22/2025 | COT - HCEL - Electrical Progress | Partial Pass | 12-22-25: verified trench depth on 8-secondary 4" schedule 40 conduits together with 8-4" schedule 40 electrical primary conduits for building at north side of site. Okay to backfill trenching. |