Inspection History Details
Inspection Status: Requested
Inspection History: COT - HCBU - Building Progress
Permit Number - TC-COM-0125-00202
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Requested
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - HCBU - Building Progress | Requested | |||
| 08/14/2025 | COT - HCBU - Building Progress | Partial Pass | 8-14-25: reinforcement on CMU elevator enclosure verified per plans. Okay to grout 1st lift at 4'. | |
| 08/20/2025 | COT - HCBU - Building Progress | Partial Pass | 8-20-25: reinforcement on CMU elevator enclosure verified per plans. Okay to,grout 4th lift at 16'. | |
| 08/27/2025 | COT - HCBU - Building Progress | Partial Pass | North half of building, second level floor at GL: 1 - 11/J - B. OK to begin,framing in progress areas. | |
| 08/29/2025 | COT - HCBU - Building Progress | Partial Pass | 8-29-25: reinforcement on elevator enclosure verified. Top out at 44' -okay to grout. | |
| 09/04/2025 | COT - HCBU - Building Progress | Not Ready | 9-4-25: contractor will schedule a 2nd floor deck nailing inspection when ready. Note: anchor bolts/hold-downs and framing on 1st floor not inspected. |
|
| 09/12/2025 | COT - HCBU - Building Progress | Partial Pass | South side of Level #2 deck, | |
| 10/02/2025 | COT - HCBU - Building Progress | Partial Pass | 10-2-25: partial pass for 2x8 joists/hangers at 16" o.c. for 1st & 2nd floor corridors. Okay to continue with construction at progress areas. | |
| 10/08/2025 | COT - HCBU - Building Progress | Partial Pass | Information only: placement of electric outlets in separation walls in room units. | |
| 10/17/2025 | COT - HCBU - Building Progress | Partial Pass | 10-17-25: all hangers & hardware along the 3rd & 4th floor corridors approved. Okay to continue construction at progress areas. | |
| 10/23/2025 | COT - HCBU - Building Progress | Partial Pass | 10-23-25: verified hold downs at shear walls throughout 1st & 2nd floor. A combined 44 in total consisting of HTT4'and Continuous rod hold down systems verified per plans. Okay to continue construction at progress areas. | |
| 10/27/2025 | COT - HCBU - Building Progress | Re-inspection required | 10-27-25: correct gaps between roof sheathing at 2 locations along the middle section and south west end of the south roof. Another spacing correction between sheathing is required at the northern roof deck along the east end before transitioning up along the parapet. All mentioned gaps in question were measured between 1" to 1 1/2". Minimum spacing between sheathing joints is 1/8" to 1/4" maximum. Schedule a reinspection at your convenience. |