Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCEL - Electrical Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/05/2026 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 1-5-26: 3rd floor rough electrical-328- add bank plate at party wall where awg wires are 1 1/4" from edge, 334-fire foam penetrations at decking in restroom, 325-add bank plate center near subpanel at marked location, 323-fire foam top plate penetration backside of tub. Fire foam all penetrations at party walls and at decking throughout all rooms. These items will be re-inspected at intermediates. Note: framing inspection on any floor has not taken place and see previous notes related to 4th floor above ceiling-several rooms had already been covered with cloth material and this must be removed and a reinspection is required. |
|
| 01/20/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Electric above ceilings and in walls in room units on Level,#4. | |
| 01/22/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Level #2, room units; Electric in walls and above ceilings. | |
| 02/12/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 2-12-26: electrical corrections made for units 101-111 & 102-112. Okay to continue with construction. | |
| 02/19/2026 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 2-19-26: reschedule inspection when ready. | |
| 02/23/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Room units at North portion of Level #1 from elevator area to North end. Ok to sheet rock ceiling areas. | |
| 03/31/2026 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 3-31-26: inspection for 1st hard lid areas in corridor and electrical room. Fire foam all penetrations at top plates, all horizontal penetrations and at decking. Add a strap to DWV at electrical room north wall | |
| 04/28/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 4-28-26: electrical above ceiling at canopy approved. Okay to continue with construction at progress areas. | |
| 04/30/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 4-30-26: 1st. floor not ready- non sealed penetrations throughout including low voltage, open junction boxes and not labeled, sections of missing drywall, 1" hot pex lines not insulated. 3rd floor-Open penetrations at south end of corridor and a couple of junction boxes not labeled. 4th floor electrical above ceiling approved. | |
| 05/04/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5/4/2026 corrections were made. 3rd floor pending j box labeling. 2nd floor approved, 1st floor hard lid area only at corridor near entry way. | |
| 05/13/2026 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 5-13-26: missing label at junction boxes north of room 109, missing junction box lid south of room 112. Unable to inspect above ceiling on north side of corridor because of freshly pour adhesive compound. Please reschedule. | |
| 05/14/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5-14-26: MEP's above ceiling/ fire caulking at 1st floor corridor approved. Okay to cover progress areas. | |
| 12/09/2025 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Partial pass. 4th floor approved. Pending fire blocking at all top plates and near all tubs. 12/9/2025 | |
| 12/10/2025 | COT - HCEL - Electrical Above Ceiling | Not Ready | 12/10/25: not ready for inwall inspection or above ceiling. | |
| 12/22/2025 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 12-22-25: rough electrical in wall /above ceiling-fire foam horizontal penetrations at party wall, add bank plates where closer than 1 1/4" from edges, finish rough in electrical from unit's 321/322 to north-awg wires must be made up at time of inspection. |