Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
04/05/2017
Applicant:
N/A
Description:
ADVANCED TEST FACILITY
Architects:
  • IAN REGAN
Contractors:
  • BRASFIELD AND GORRIE L L C ,

Permit Reviews

Permit Number - T17CM02636
Permit Status: C of o
Permit Description: ADVANCED TEST FACILITY
Start Date Submittal Complete Date Status  
01/07/2019 REVISION - - 4TH 09/18/2019 COMPLETED Review Details
04/05/2017 PLANS OK TO SUBMIT - COMM 04/05/2017 COMPLETED Review Details
04/05/2017 COMMERCIAL - NEW 05/16/2017 COMPLETED Review Details
05/16/2017 RESUBMITTAL 06/02/2017 COMPLETED Review Details
05/17/2018 REVISION - - 3RD 05/31/2018 COMPLETED Review Details
06/02/2017 RESUBMITTAL 06/09/2017 COMPLETED Review Details
07/28/2017 REVISION - - 1ST 07/28/2017 COMPLETED Review Details
07/28/2017 REVISION - - 1ST 08/03/2017 COMPLETED Review Details
08/03/2017 REVISION - - 1ST 08/03/2017 COMPLETED Review Details
08/25/2017 REVISION - - 2ND 08/25/2017 COMPLETED Review Details
08/25/2017 REVISION - - 2ND 08/31/2017 COMPLETED Review Details
09/18/2019 REVISION - - 5TH 09/25/2019 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T17CM02636
Permit Status: C of o
Permit Description: ADVANCED TEST FACILITY
Total Outstanding Activity Conditions - 1
Date Name
04/05/2017 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T17CM02636
Permit Description: ADVANCED TEST FACILITY
Total Completed Inspections - 40
Date Description Inspector Results Comments
08/31/2017 MECHANICAL - UNDERGROUND RCAMACHO Approved COURTESY INSP ONLY
11/16/2017 PLUMBING - YARD WTR LINE/TEST RCAMACHO Approved CANCELED
11/20/2017 BUILDING PRE-SLAB mramber1 Approved east side vapor ok
12/11/2017 PLUMBING - ROUGH, SOIL RCAMACHO Approved NO WORK
12/27/2017 ELECTRIC - UNDERGROUND rbaldwin Approved 3-0 ground from swithc gears to transformers. grounding through electric room. underground- 9-4" conduits on a&b, 8-4", 1-2 1/2',1-1 1/2" CONDUITS COLUMN P to electric room, 6-1" from P8 toL8
12/27/2017 ELECTRIC - UFER rbaldwin Approved 3-0 ground from swithc gears to transformers. grounding through electric room. underground- 9-4" conduits on a&b, 8-4", 1-2 1/2',1-1 1/2" CONDUITS COLUMN P to electric room, 6-1" from P8 toL8
08/10/2018 MECHANICAL - PROGRESS RCAMACHO Approved 100 PSI COMPLETION OF CHILLED WATER SYSTEM AT ROOF
08/24/2018 ELECTRIC - CONSTRUCTION POWER RCAMACHO Approved TRANSFORMER AND SWITCH GEAR T-920 LINE SIDE ONLY OK TO ENERGIZE.
TO REMAIN LOCKED OUT AND TAGGED OUT
10/24/2018 EXCAVATION/LAYOUT REBAR & ZON RCAMACHO Approved AFTER HOURS APA ACCOUNT $165.00
A equipment yard G0900 pad per detail 107/s3.3
10/24/2018 EXT METAL CLIPS/EXT SHEATHING RCAMACHO Approved Fire riser room N0100
10/24/2018 EXCAVATION/LAYOUT REBAR & ZON RCAMACHO Approved
10/25/2018 FIRE SPKLR - FINAL JPEELDAVIS Approved Area A, F & G Approved
10/25/2018 FIRE - ALARM FINAL JPEELDAVIS Approved Area A, F & G Approved
10/25/2018 FIRE - FINAL JPEELDAVIS Approved Area A, F & G ok for TCO
10/29/2018 PLUMBING - FINAL RCAMACHO Approved Areas a, f and g
pending chlorination report and air balance report to Bob Sherry
pending engineering finals
okay to apply for temporary C of o
11/01/2018 PLUMBING - GAS PRESSURE TEST RCAMACHO Approved
11/07/2018 MECHANICAL - FINAL RCAMACHO Approved IT closet P0510 pending balance report
12/04/2018 BUILDING - PROGRESS RCAMACHO Approved sheet rock nailing 1st layer interior data Room
H0700, computer wing wall H0600 and vestibule 80500 exterior and into your 1st layers only
12/13/2018 MECHANICAL - ABOVE CEILING RCAMACHO Approved
12/13/2018 ELECTRIC - ABOVE CEILING RCAMACHO Approved
12/13/2018 BUILDING ABOVE CEILING RCAMACHO Approved
12/13/2018 FRAMING RCAMACHO Approved Galley room J0510, janitors closet J0520 & water closet room J0530
Ok to insulate hot water lines
12/13/2018 FRAMING RCAMACHO Approved galley room J0 510 janitor closet J0 520 and water closet room J0 530 OK to insulate water lines
12/13/2018 MECHANICAL - ABOVE CEILING RCAMACHO Approved
12/13/2018 ELECTRIC - ABOVE CEILING RCAMACHO Approved
12/13/2018 BUILDING ABOVE CEILING RCAMACHO Approved
12/17/2018 PLUMBING - ABOVE CEILING RCAMACHO Approved
12/17/2018 PLUMBING - INTERMEDIATE RCAMACHO Approved
12/19/2018 ELECTRIC - PROGRESS RCAMACHO Approved transformer and panel is area E OK to energize for test to remain locked out and tagged out
12/20/2018 MECHANICAL - INTERMEDIATE RCAMACHO Approved 100 pound test chiller system and hot water line system 90 foot roof OK to insulate
12/20/2018 ELECTRIC - FINAL RCAMACHO Approved Interior of Range chamber only
12/20/2018 ELECTRIC - INTERMEDIATE RCAMACHO Approved Interior of Range chamber only
02/12/2019 PLUMBING - PROGRESS BSTEVENS Approved
02/12/2019 PLUMBING - PRE SLAB BSTEVENS Approved
02/12/2019 U VALUE FOR WINDOW BSTEVENS Approved
02/12/2019 ROOF NAILING BSTEVENS Approved
02/12/2019 STEM WALL/RETAINING WALL BSTEVENS Approved
03/04/2019 TEP CLEARANCE - AM BSTEVENS Approved CODE ECO
03/12/2019 ELECTRIC - SERVICE UPGRADE RCAMACHO Approved
11/13/2019 BUILDING - FINAL TVALENCIA Approved 1- Attended a pre construction meeting with the contractor about phase 2.

Documents

File Name Document Type  
080222 TCO.PDF DOCUMENTS VIEW
C OF O T17CM02636.PDF DOCUMENTS VIEW
FINAL SIC T17CM02636 - BLDG 927.920.PDF DOCUMENTS VIEW
TCO REQUEST.PDF DOCUMENTS VIEW
TCO.PDF DOCUMENTS VIEW
T17CM02636 - TCO.PDF CERT OF OCC VIEW