Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T17CM02636
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/21/2018 | PLUMBING - ROUGH, SOIL | Approved | ||
09/11/2018 | PLUMBING - ROUGH, SOIL | Partial Approval | 100 lb trst hot water lines from VAV'S from GL B-D from 7-9 to xray roon ok to insulate Double containment pipe from GL 8-9 from B.5 - D only |
|
08/30/2018 | PLUMBING - ROUGH, SOIL | Partial Approval | Industrial Waste double contained pipe GL 8.75 from D to F only | |
08/21/2018 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
07/23/2018 | PLUMBING - ROUGH, SOIL | Partial Approval | north tie in to HCS ok | |
07/19/2018 | PLUMBING - ROUGH, SOIL | Partial Approval | JANITOR CLOSET ROOM J0520 BATHROOM JO530 GALLEY JO510 4" MAIN FROM GL 5.75 T5O 7 |
|
04/18/2018 | PLUMBING - ROUGH, SOIL | Partial Approval | DRAIN FOR FIRE PUMP OK TO COVER | |
03/14/2018 | PLUMBING - ROUGH, SOIL | Partial Approval | sewer tie in at ne corner area a | |
12/11/2017 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | NO WORK | |
12/08/2017 | PLUMBING - ROUGH, SOIL | Partial Approval | COMBO WASTE AND VENT SYSTEM FLOOR SINKS AT MECH ROOM TO 2-WAY CLEANOUT AT WEST EXTERIOR ONLY | |
10/18/2017 | PLUMBING - ROUGH, SOIL | Partial Approval | AREA G WASTE ONLY |