Permit: T17CM02636

Parcel: 14043013B

Inspection Status: Approved

Inspection History: ELECTRIC - INTERMEDIATE

Permit Number - T17CM02636

Inspection Description - ELECTRIC - INTERMEDIATE

Inspection Status - Approved

Date Description Inspector Results Comments
03/12/2019 ELECTRIC - INTERMEDIATE Approved
12/20/2018 ELECTRIC - INTERMEDIATE Partial Approval Interior of Range chamber only
12/19/2018 ELECTRIC - INTERMEDIATE Partial Approval area is E & D only
12/13/2018 ELECTRIC - INTERMEDIATE Partial Approval galley room J0 510 janitor closet J0 520 and water closet room J0 530 OK to insulate water lines
12/13/2018 ELECTRIC - INTERMEDIATE Partial Approval Galley room J0510, janitors closet J0520 & water closet room J0530
Ok to insulate hot water lines
11/29/2018 ELECTRIC - INTERMEDIATE Partial Approval JO510, JO510 ok
10/24/2018 ELECTRIC - INTERMEDIATE Not ready for Inspection
10/23/2018 ELECTRIC - INTERMEDIATE Not ready for Inspection
10/19/2018 ELECTRIC - INTERMEDIATE Partial Approval Panels H/D.9-7, L/P8.4, H/Q 2.9B, L/E.1-7, I.T. west and east ok to energize
10/18/2018 ELECTRIC - INTERMEDIATE Partial Approval Transformers in panels in x-ray room c0701 okay to energize for test to remain locked out and tagged out
10/11/2018 ELECTRIC - INTERMEDIATE Partial Approval Potable cold water 100 lb test system only
10/10/2018 ELECTRIC - INTERMEDIATE Partial Approval PDU LQ-3.7
PDU LP-3.7
H/Q2 EM-B
H/P.1-2 EM-A
H/P-2 EMA
TRANSFER SWITCH
IN ELECTRIC ROOM E0300
OK TO ENERGIZE FOR TEST
ALL PANELS AND DISCONNECTS ON EAST ROOF FOR AIR HANDLERS OK TO ENERGIZE FOR TEST
TO REMAIN LOCKED OUT AND TAGGED OUT
10/08/2018 ELECTRIC - INTERMEDIATE Partial Approval Panel LP 6.1 a
janitor closet panels (2)
3 Transformers and 3 panels H/D-8.4.9 EM-A, WALL STOPPER PANEL & H/F.8-5.2A electric room E010
Emergency Transformer disconnect
All panels and Transformers okay to energize for test to remain locked out and tagged out
10/05/2018 ELECTRIC - INTERMEDIATE Partial Approval Panel L/E 5.3 UPS -A

PANEL H/E.3-5.1-B

PANEL H/E .1-5.3A

PANEL H/E.2-5.3B

PANEL L/D.3-5.1-A

PANELPDU/L/D.8-4.5 UOS

PANEL PDU -L/E.3.4.5 UPS.B

ELECTRIC ROOM E041OK TO ENERGIZE FOR YEST

All panels to remain locked out and tagged

out

Disconnect Air Handlers 3 + 30 area A & G & F Auto disconnect did not meet code for working clearances AC units 3 & 4 all disconnects and panels to be locked out and tagged out
10/04/2018 ELECTRIC - INTERMEDIATE Partial Approval Disconnects and panels at air handlers areas D & C onlly

OK TO ENERGIZE FOR TEST
10/02/2018 ELECTRIC - INTERMEDIATE Partial Approval All disconnects and panels in area F ok to energize for test.

Panel LC 761 UPS A area G lab ok to energize for test

ALL PANELS AND DISCONNECTS TO BE LOCKED OUT AND TAGGED OUT
08/24/2018 ELECTRIC - INTERMEDIATE Partial Approval IVRS - Inspection :*
08/24/2018 ELECTRIC - INTERMEDIATE Partial Approval TRANSFORMER AND SWITCH GEAR T-920 LINE SIDE ONLY OK TO ENERGIZE.
TO REMAIN LOCKED OUT AND TAGGED OUT
08/15/2018 ELECTRIC - INTERMEDIATE Partial Approval 1st floor office 6 and 8 ok
07/13/2018 ELECTRIC - INTERMEDIATE Partial Approval restrooms, breakroom, wellness ok