Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/28/2019 | BUILDING PRE-SLAB | Approved | ||
10/24/2018 | BUILDING PRE-SLAB | Partial Approval | AFTER HOURS APA ACCOUNT $165.00 A equipment yard G0900 pad per detail 107/s3.3 |
|
09/05/2018 | BUILDING PRE-SLAB | Partial Approval | After hours APA acoount $165.00 GL 8-9 FROM D.5 - G ONLY |
|
08/09/2018 | BUILDING PRE-SLAB | Partial Approval | AREA C GL 5-8 FROM Q-L AROUND PIT AREA PENDING SPECIAL INSP REPORT EPOXY AND NEW TI PERMIT AND APPROVED PLANS | |
08/02/2018 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* | |
08/02/2018 | BUILDING PRE-SLAB | Partial Approval | PIT SECTION AREA C PER DETAIL 109/S3.3 |
|
03/09/2018 | BUILDING PRE-SLAB | Partial Approval | grid 4-5 p-g amd 1-7 f-f.5 ok to pour | |
01/26/2018 | BUILDING PRE-SLAB | Partial Approval | grid lines P-Q to 4-7.2 ok to pour | |
11/20/2017 | BUILDING PRE-SLAB | Partial Approval | east side vapor ok | |
11/16/2017 | BUILDING PRE-SLAB | Not ready for Inspection | CANCELED | |
11/15/2017 | BUILDING PRE-SLAB | Partial Approval | AFTER HOURS APA ACCOUNT $165.00 AREA F ONLY |
|
11/14/2017 | BUILDING PRE-SLAB | Partial Approval | VAPOR BARRIER LAB ONLY ISOLATED SLAB | |
11/13/2017 | BUILDING PRE-SLAB | Not ready for Inspection | NO WORK | |
08/22/2017 | BUILDING PRE-SLAB | Not ready for Inspection | CANCELED BY GERALD | |
08/17/2017 | BUILDING PRE-SLAB | Partial Approval | AFTER HOURS APA ACCOUNT $165.00 H I L CHAMBER SLAB PER DETAIL 107/S3.3 AND RFI 108/ S3.3 THICKENED SLAB ONLY |