Permit: T17CM02636

Parcel: 14043013B

Inspection Status: Approved

Inspection History: FRAMING

Date Description Inspector Results Comments
01/23/2019 FRAMING Approved
12/13/2018 FRAMING Partial Approval galley room J0 510 janitor closet J0 520 and water closet room J0 530 OK to insulate water lines
12/13/2018 FRAMING Partial Approval Galley room J0510, janitors closet J0520 & water closet room J0530
Ok to insulate hot water lines
12/04/2018 FRAMING Partial Approval Conference Room H0525
11/29/2018 FRAMING Partial Approval Data room, vestibule, wing wall at LSV lab ok, JO510 and JO510 ok
11/09/2018 FRAMING Partial Approval Area A vestibule L0503B
10/30/2018 FRAMING Partial Approval 10" high walls rooms J0530,J0540 & J0510
10/17/2018 FRAMING Partial Approval 10" high wall GL J.5 from 5-8 only
10/02/2018 FRAMING Partial Approval 10" wall GL 4 from F - G only
09/21/2018 FRAMING Partial Approval GL-C-D grom 8.5 -9 high wall

GL 5 from G-F highwall
09/20/2018 FRAMING Partial Approval Pony wall high wall above GL - F from 7 - 8
09/19/2018 FRAMING Partial Approval -GL C FROM 8.5 TO 9 HIGH WALL
-GL C.5 FROM 8.5 TO 8' SHORT OF 9
09/17/2018 FRAMING Partial Approval 2 x 6 wall with soffits GL -F from 8-9
LN2 tank pad and both vaporizer pads see highlighted S1.1 plan
sheetrock 1st layer GL 8 from D-F both sides of wall. Fire caulk west end only
09/13/2018 FRAMING Partial Approval High wall GL 5 from H-J
Sh3GL F from 7-8
09/12/2018 FRAMING Partial Approval Soffitt GL 8 from F - G only
West tank pad per detail 3/s1.2 see rfi 330
09/11/2018 FRAMING Not ready for Inspection
09/10/2018 FRAMING Partial Approval GL F from 7 - 8 furrout at beam
09/07/2018 FRAMING Partial Approval Popout GL 8 from G-F only

2 x 6wall @ 16"oc GL Q from 5-8
09/05/2018 FRAMING Partial Approval 2 X 6 WALL 12 " OC GL F FROM 7-8
08/31/2018 FRAMING Partial Approval room p 0 500 only
08/30/2018 FRAMING Partial Approval screws at Ledger's room p05 200

Grid line 8 from G to F 12 inch on Center 2 x 6 wall
08/29/2018 FRAMING Not ready for Inspection IVRS - Inspection :*
08/22/2018 FRAMING Partial Approval IVRS - Inspection :*
ROOMS P0520 & P0510 PROVIDE BRACING
08/15/2018 FRAMING Partial Approval entry way hall ok
08/10/2018 FRAMING Partial Approval IVRS - Inspection :*
NORTH CORRIDOR B WALL F0400 AT IT CLOSETS ONLY
08/09/2018 FRAMING Partial Approval ROOMS C0703, C0702,C0704 & C0705 ONLY
08/06/2018 FRAMING Partial Approval GL7.5 FROM C-D
X-RAY ROOM C0701 NORTH AND EAST WALL
ROOM C0705 MACHINE SHOP ROOM A0600
08/01/2018 FRAMING Partial Approval IVRS - Inspection :*
GL F FROM 5-6 ONLY
GL 5 FROM G-J 1ST LIFT ONLY
07/31/2018 FRAMING Partial Approval VESTIBULE ROOM E0600
3/4" PLYWOODFIRE RETARDANT OK TO PAINT I SIDE PRIOR TO INSTALL
GL 5 FROM J-K 10" WALL FLOOR TO ROOF DECK
ROOM C0701 AREA A
07/27/2018 FRAMING Partial Approval SOFFITES IN ROOM B0600 ONLY
07/26/2018 FRAMING Partial Approval TOP OUT WALL GL F FROM 2-4 & 6-7 ONLYH
07/25/2018 FRAMING Partial Approval 6" NORTH WALL ROOM P0300 ONLY
07/24/2018 FRAMING Partial Approval 10 " FIRE WALL GL 5 FROM L-M 2ND LIFT HIGH SECTION TO ROOF DECK
6" CORRIDOR WALL GL 4 FROM G-H
07/20/2018 FRAMING Partial Approval popout at C0600, wall at CL 4 @ H thru F
07/17/2018 FRAMING Partial Approval RISER ROOM D0105
PARTITION WALL E0600 & E0700
FURROUT SOUTH WALL ROOM B0600
07/16/2018 FRAMING Partial Approval VESTIBULE 9 ONLY
07/12/2018 FRAMING Partial Approval demising wall at main elec. room ok, and rooms 420 and 430
07/03/2018 FRAMING Partial Approval IVRS - Inspection :*COMPUTER ROOMS ONLY ROOMS C0300, C0200, C0150, C0105, E0155 & E0305
06/29/2018 FRAMING Partial Approval IVRS - Inspection :*
12" WALL 1ST AMD 2ND FLOOR GL N4-M-4 ONLY
06/25/2018 FRAMING Not ready for Inspection
06/21/2018 FRAMING Partial Approval 10" WALL GL 4 FROM N-P UP TO 2ND LEVEL ONLY
06/19/2018 FRAMING Partial Approval REST ROOMS A0730, A0720, CORRIDOR A0803 & WELLNESS ROOM A0806
05/29/2018 FRAMING Partial Approval F1-7.1
05/14/2018 FRAMING Partial Approval GRID LINE F6-5.1
05/02/2018 FRAMING Partial Approval GRID LINES E1-4, E3.1-2.1
04/20/2018 FRAMING Partial Approval GRID LINE 4 F-C D 1-4
04/16/2018 FRAMING Partial Approval GRID LINE 4C-D, E7-E6, E-F5.1
03/23/2018 FRAMING Partial Approval LAB AND CONFERENCE ROOMS 1ST FLOOR