Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - INTERMEDIATE
Permit Number - T17CM02636
Inspection Description - MECHANICAL - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/28/2019 | MECHANICAL - INTERMEDIATE | Approved | ||
12/20/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | 100 pound test chiller system and hot water line system 90 foot roof OK to insulate | |
12/13/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | galley room J0 510 janitor closet J0 520 and water closet room J0 530 OK to insulate water lines | |
12/13/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | Galley room J0510, janitors closet J0520 & water closet room J0530 Ok to insulate hot water lines |
|
11/13/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | Entire heating water system except Riser riser to 90 foot roof 100 lb test | |
11/07/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | Hot water and chill water systems on mid roof 100 psi test ok to insulate both systems | |
10/31/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | Chill water mid-roof North system 100 PSI test okay to insulate | |
09/21/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | 100 psi test chill water whole system in luding east roof | |
09/11/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | ||
09/05/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | HOT WATER LINES 5 UNITS ROOM E0600 OK TO INSULATE 100 LB TEST OK | |
08/31/2018 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | ||
08/14/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | HHW hydro test ok at interior piping | |
08/10/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | IVRS - Inspection :* | |
08/10/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | 100 PSI COMPLETION OF CHILLED WATER SYSTEM AT ROOF | |
07/19/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | CHILLED WATER LINES TEST 100 PSI GL G THROUGH CORRIDOR D0700 THRU GL WALL 7.1 OK TO INSULATE | |
07/18/2018 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | ||
07/17/2018 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | ||
07/16/2018 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | NO WORK | |
06/25/2018 | MECHANICAL - INTERMEDIATE | Not ready for Inspection | ||
06/13/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | HEATING WATER VAV1-1 TO 1.2, 1.3, 1.5, 1.6 & 1.7 ONLY 120 LB TEST TERMINATING ABOVE DUCT GRID LINE 7.2 TO D.5 OK TO INSULATE |
|
06/07/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | TEST AT HOT WATER CHILLER LINES AT PUMP HOUSE | |
06/01/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | CHILLED WATER SUPPLY AND RETURN LINES PRESSURE TEST WEEST OF GRID LINE G OK TO INSULATE | |
05/07/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | DUCTS OK TO INSULATE GRID LINES D-E 1-7.1, Q-P 1=8 | |
04/10/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | INFO ONLY | |
04/04/2018 | MECHANICAL - INTERMEDIATE | Partial Approval | AREA F HEATING WATER AND COMPRESSED AIR 150 PSI AND120 PSI TESTS OK |