02/12/2019 | ELECTRIC - UFER | Approved | ||
04/03/2018 | ELECTRIC - UFER | Partial Approval | EXTERIOR GROUND RING COMPLETE | |
03/26/2018 | ELECTRIC - UFER | Not ready for Inspection | ||
03/12/2018 | ELECTRIC - UFER | Partial Approval | exterior grounding grid line q 9-4 ok | |
02/27/2018 | ELECTRIC - UFER | Not ready for Inspection | ||
02/21/2018 | ELECTRIC - UFER | Partial Approval | 1-21/" and grounding vault b ok 3-1' 1-21/2" and grounding at vault a ok | |
01/22/2018 | ELECTRIC - UFER | Partial Approval | GROUNDING AT MECH YARD AND FIRE PUMP AT 2 ATF"S AND FIRE PUMP | |
01/08/2018 | ELECTRIC - UFER | Partial Approval | GROUND RING NORTH END FROM GRID LINE K-Q GROUND RODS AT GRID LINES L, Q AND N | |
01/04/2018 | ELECTRIC - UFER | Partial Approval | GROUND RING FROM GRID LINE G-K NORTH SIDE OF TEST FACILITYGROUND ROD COLUMN J-7 WITH TIE INS | |
12/27/2017 | ELECTRIC - UFER | Partial Approval | 3-0 ground from swithc gears to transformers. grounding through electric room. underground- 9-4" conduits on a&b, 8-4", 1-2 1/2',1-1 1/2" CONDUITS COLUMN P to electric room, 6-1" from P8 toL8 | |
12/20/2017 | ELECTRIC - UFER | Partial Approval | GROUNDING TO L/4, L/5, N/4 AND N/5 COLUMNS ONLY | |
12/14/2017 | ELECTRIC - UFER | Partial Approval | GROUNDING AT COLUMNS H/5, H/4, J/5, J/4 UP TO K/4 ONLY | |
12/06/2017 | ELECTRIC - UFER | Partial Approval | EXTERIOR GROUND RING FROM SW CORNER TO NW CORNER INCLUDING GROUND RODS AND ALL PREVIOUS TIE INS | |
10/27/2017 | ELECTRIC - UFER | Not ready for Inspection | cancelled | |
10/26/2017 | ELECTRIC - UFER | Partial Approval | GROUND WIRE FROM COLUMN G TO JAMITORS CLOSET AND COLUMN C-8 TO TIE INTO BUILDING TO EXTERIOR GROUND RING BY COLUMN D-7 EXTERIOR GROUND RING FROM GROUND ROD AT COLUMN C-9 TO COLUMN G ONLY |
|
10/20/2017 | ELECTRIC - UFER | Partial Approval | EXTERIOR GROUND LOOP FROM COLUMN 7.1/A TO 1ST GROUND ROD TO 2ND GROUND ROD COLUMN 5-1 TO 3RD GROUND ROD COLUMN 2.1 ONLY | |
10/18/2017 | ELECTRIC - UFER | Partial Approval | FUTURER GROUNDING GRID LINE 2 THRU 7.7 FROM C TO F OK TO COVER | |
09/28/2017 | ELECTRIC - UFER | Partial Approval | GROUND WIRE L-5, N-5 COLUMNS AND CADWELD F-20 FOOTER GRID LINE 7.2 FROM P TO Q | |
09/27/2017 | ELECTRIC - UFER | Partial Approval | GROUNDING COLUMN F-8 ONLY | |
09/27/2017 | ELECTRIC - UFER | Partial Approval | PASS THROUGH F-1 FOOTER Q5 ONLY | |
09/26/2017 | ELECTRIC - UFER | Partial Approval | grade beams P/7 thruP/8 , M/8thruN/8 , G/8thruH/8 , G/8thruG/9.5 columns J/8 , K/8 , L/8 , | |
09/22/2017 | ELECTRIC - UFER | Not ready for Inspection | CANCELED | |
09/20/2017 | ELECTRIC - UFER | Partial Approval | GROUNDING AT COLUMN 9F, PASS THRU F-20 FOOTER AT 9E AND F-22 FOOTERS AT COLUMNS H-5, P AND Q | |
09/19/2017 | ELECTRIC - UFER | Partial Approval | C/2.1 , P.5/1 ok | |
09/14/2017 | ELECTRIC - UFER | Not ready for Inspection | CANCELED BY GERALD | |
09/13/2017 | ELECTRIC - UFER | Not ready for Inspection | IVRS - Inspection :* | |
09/08/2017 | ELECTRIC - UFER | Partial Approval | 3 GROUNDS UNDER F-14 FOOTER GRID LINE Q FROM 6 TO 7.2 | |
09/07/2017 | ELECTRIC - UFER | Not ready for Inspection | CANCELED BY GERALD | |
09/06/2017 | ELECTRIC - UFER | Not ready for Inspection | CANCELED | |
09/05/2017 | ELECTRIC - UFER | Partial Approval | GROUND AT COLUMN A-6.1 AND C-5.1 GROUND UNDER F-10 FOOTER AT GRID LINE C |
|
09/05/2017 | ELECTRIC - UFER | Partial Approval | AFTER HOURS APA ACCOUNT $165.00 PIT WALL WEST AT BOTTOM OF FLIGHT TABLE ONLY |
|
08/31/2017 | ELECTRIC - UFER | Partial Approval | GROUND AT COLUMN A-8 | |
08/30/2017 | ELECTRIC - UFER | Partial Approval | GROUNDING COLUMN D-9 | |
08/22/2017 | ELECTRIC - UFER | Not ready for Inspection | CANCELED BY GERALD | |
08/21/2017 | ELECTRIC - UFER | Partial Approval | BOND WIRE COLUMN Q-2, Q-3 AND Q-4 ONLY | |
08/17/2017 | ELECTRIC - UFER | Partial Approval | BOND WIRE COLUMN N-4, P-2 AND P-3 ONLY | |
08/17/2017 | ELECTRIC - UFER | Partial Approval | BOND WIRE AT COLUMN G-4 ONLY | |
08/11/2017 | ELECTRIC - UFER | Partial Approval | BOND WIRE COLUMN N-8, AND L-8 ONLY |