Permit: T17CM02636

Parcel: 14043013B

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
01/28/2019 EXCAVATION/LAYOUT REBAR & ZON Approved
10/24/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
10/24/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS APA ACCOUNT $165.00
A equipment yard G0900 pad per detail 107/s3.3
09/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 2 x 6 wall with soffits GL -F from 8-9
LN2 tank pad and both vaporizer pads see highlighted S1.1 plan
sheetrock 1st layer GL 8 from D-F both sides of wall. Fire caulk west end only
09/12/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval West tank pad per detail 3/s1.2 see rfi 330
Soffitt GL 8 from F - G only
09/06/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
08/16/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
08/09/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AREA C GL 5-8 FROM Q-L AROUND PIT AREA PENDING SPECIAL INSP REPORT EPOXY AND NEW TI PERMIT AND APPROVED PLANS
04/24/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
04/16/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval NW MEHANICAL PAD, SOUTH WALL COLUMN BLOCKOUTS 1-O OK TO POUR
04/13/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED
04/13/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
04/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN BLOCKOUTS K-G ON NORTH WALL, MECHANICAL PAD @ SW CORNER OK TO POUR
04/10/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS M,N,L ON NORTH WALL
04/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 4 EQUIPT PADS SW CORNER OK TO POUR
04/04/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
04/03/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 3 EQUIPT PADS WEST SIDE, 10 EQUIPT PADS NORTH SIDE WEST END
03/09/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval footings for central plant size and reinforcement per plans
01/25/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval stair and canopy footings on east side ok to pour
01/11/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED
10/05/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection NO WORK
09/28/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection WORK NOT COMPLETE
09/28/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS APA ACCOUNT $165.00
F-21 FOOTER GRID LINE 9 FROM F TO G
F-20 FOOTER GRID LINE 7.2 FROM P TO Q
F-5 FOOTERS M-5, N-5, L-5 & K-5
09/27/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-17 FOOTER GRID LINE F FROM 7.4 TO 8 WITH COLUMNS F-8 AND F.74
09/27/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS APA ACCOUNT $165.00
F-16 FOOTER GRID LINE P FROM 5 TO 6 WITH COLUMN P6 AND P5
F-20 FOOTER GRID LINE Q FROM 4.5 TO 6 WITH F-1 FOOTER Q5
09/26/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval grade beams P/7 thruP/8 , M/8thruN/8 , G/8thruH/8 , G/8thruG/9.5 columns J/8 , K/8 , L/8 ,
09/26/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED
09/21/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED BY GERALD
09/20/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS APA ACCOUNT $165.00
F-22 FOOTER FROM GRID LINE 9 FROM F TO D
F-21 FOOTERS GRID LINE 9 FROM B TO C
F-20 FOOTERS GRID LINE A FROM 8 TO 8.25
F-20 FOOTER GRID LINE A FROM 7.4 TO 6.4
F-20 FOOTER GRID LINE C FROM 5 TO 5.1
F-20 FOOTER GRID LINE 1 FROM D TO D.2
F-22 FOOTERSGRID LINE 1 FROM F TO N
F-22 FOOTER GRID LINE D FROM 1.75 TO 2
F-22 FOOTER GRID LINE 2 FROM P TO Q
F-1 FOOTERS 9E & 9F
09/19/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval elec vault #1 (south( ok to pour
09/19/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED BY GERALD
09/14/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED BY GERALD
09/13/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
09/11/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FLIGHT TABLE ONLY
09/08/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-14 FOOTER GRID LINE Q FROM GRID LINES 6 TO 7.2 WITH COLUMN BOLTS Q6, Q7& Q7.2
COLUMN Q7 TO BOTTOM OF GRADE BEAM
STEP FOOTER GRID LINE G FROM 8.5 TO 9.5
F-13 STEP FOOTER GRID LINE G FROM 8.5 TO 9.5 WITH COLUMN G-9
09/07/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED BY GERALD
09/06/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS P-8 AND P-7.2 ONLY
09/05/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-15 FOOTER GRID LINE 6.1 FROM A TO B.25
F-10 FOOTER GRID LINE C FROM 6.1 TO 5.1 WITH COLUMNS A-6.1 & B-6.1
09/01/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PIT WALL GRID LINE 6 FROM M TO N
PIT WALL GRID LINE N FROM 6 TO 6.5
F-16 FOOTER GRID LINE P FROM 7 TO 8 WITH COLIUMN FOOTERS P-8, P-7.2 & P-7
F-13 STEP FOOTER GRID LINE G
COLUMN H-8 TO BOTTOM OF GRADE BEAM
08/31/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-9 FOOTERS GRID LINE A FROM 7.4 TO 8 WITH COLUMN FOOTERS A-8 AND A.74
08/30/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PIT WALL GRID LINE K.75 FROM 5.75 TO 6.75
PIT WALL GRID LINE 5.75 FROM N.5 TO K.75
EXCEPT LEDGER BOLTS AND 90- BARS PER NOTE 3
F-12 FOOTER GRID LINE 9 FROM C TO D
C9B COLUMN G-8 TO BOTTOM OF GRADE BEAM
08/29/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED BY GERALD
08/28/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval C-9 COLUMN L-8
PIT WALL GRID LINE 7.5 FROM N.75 TO K.75
PIT WALL GRID LINE K.75 FROM 6.75 TO 7.5 PER DETRAIL 107/S3.3 EXCEPT #6 AND LEDGER BOLTSBARS PER NOTE 3 AND AT TOP OF POUR 24" OC
08/28/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS APA ACCOUNT $165.00
C-9 COLUMN C-9 TO BOTTOM OF GRADE BEAM ONLY
08/25/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMN K-8
F-15 FOOTER GRID LINE 8 FROM G TO H
SEE RFI TO INCLUDE COLUMN FOOTERS H-8 AND G-8
08/24/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval PIT WALLS GRID LINE 7.5 FROM P.75 TO N.75
PIT WALL GRID LINE N.25 FROM 7.5 TO 6.75
PER DETAILS 107/S3.3 AND 106/S3.3 MISSING 3/4" LEDGER BOLTS PER PLAN
MISSING 90 BARS PER NOTE 3 AT THIOS TIME
COLUMN M-8 PER DETAIL 124/S3.3
08/23/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CNB COLUMN N-8 TO GRADE BEAM ELEVATION ONLY
08/22/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED BY GERALD
08/21/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS APA ACCOUNT $165.00
F-14A FOOTER GRID LINE Q FROM 1.75 TO 4.25 WITH COLUMNS Q-2, Q-3 AND Q-4 EXCEPT EPOXY BARS AT COLUMNS PER RFI
08/18/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS INSPECTION APA ACCOUNT $165.00
F-16 FOOTER WITH COLUMN FOOTERS F-4.5 AND F-6 EXCEPT EPOXY BARS AT BOLTS PER RFI
08/17/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-16 FOOTER GRID LINE 4 FROM F.75 TO H.25 WITH COLUMN FOOTERS G-4 AND H-4 EXCEPT EPOXY BARS PER RFI
08/17/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS APA ACCOUNT $165.00
H I L CHAMBER SLAB PER DETAIL 107/S3.3 AND RFI 108/ S3.3 THICKENED SLAB ONLY
08/16/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-6 FOOTER J-8
F-19 FOOTER GRID LINE P FROM 1.75 TO 3.25
F-16 FOOTER GRID LINE 4 FROM P.75 TO M.25
EXCEPT EPOXY BARS PER RFI AT F-16 AND F-19 FOOTERS
08/15/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-18 FOOTER GRID LINE 1 FROM L.75 TO N.2
COLUMNM FOOTERS M-1 AND N-1 EXCEPT EPOXY BARS PER RFI
F-11 FOOTER GRID LINE 1 FROM F.75 TO H-2
COLUMNS G-1 AND H-1 EXCEPT EPOXY BARS PER RFI
08/14/2017 EXCAVATION/LAYOUT REBAR & ZON Denied MISSING VERTS Z-BARS PER NOTE 13 DETAIL 123/S3.5 SEE DELTA 3 AT COLUMN FOOTERS C-1, C-1.1 & D-1
08/14/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS $165.00 APA ACCOUNT
PENDING RFI FOR L DOWELL OPTION SECTION VIEW OPTION 1 OR 2
F-11 FOOTERS GRID LINE C FROM 1 TO 1.3
F-11 FOOTERS GRID LINE 1 FROM C TO D.1
F-22 GRADE BEAM FOOTER GRID LINE 1 FROM H.2 TO H.75
COLUMN FOOTINGS C-1, C-1.1 AND D-1 PENDING RFI APPROVAL
08/11/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-15 FOOTERS GRID LINE 8 FROM N TO M
F-6 FOOTERS L-8, K-8 AND J-8
F-8 FOOTER P-4
08/10/2017 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection CANCELED
08/08/2017 EXCAVATION/LAYOUT REBAR & ZON Denied ISOLATION PIT AREA C PER DETAIL 126/S3.5 MISSING 1 #6 BAR AT BOTTOM MAT 6"OC
COMPLETE ALL FORMS
08/08/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval AFTER HOURS
ISOLATION PIT PER DETAIL 126/S3.5 ONLY
APA ACCOUNT $165.00
SEE SIGNATURE
08/07/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-3 FOOTER E-8
F-2 FOOTERS C-8, B-8, C-7.1 & B-7.1
GRADE BEAM F-20 GRID LINE A FROM 8.75 TO 9 WITH F-1FOOTER A-9
GRADE BEAM F-20 FOOTER GRID LINE 9 FROM A TO B.8 WITH F-1 FOOTER
GRADE BEAM F-20 AND F-22 FOOTERS GRID LINE C FROM 1.5 TO 4.8 WITH F-1 FOOTERS C-4, C-3.1 AND C-2.1
08/04/2017 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-2 FOOTERS D-1.1, D 2.1, D-3.1, D-4, D-5, D-6.1, D-7.1, D-2, E-1.1, E-2.1, E-3.1, E-4, E-5.1, E-6.1,E-7.1
GRADE BEAM GRID LINE 1 FROMD.2 TO E.75 WITH F-1 FOOTER
GRADE BEAM GRID LINE 1 FROM H.3 TO L.75
F-22 FOOTERS 1-J, 1-K AND 1L
GRADE BEAM 1 FROM P TO P-.75
GRADE BEAM P FROM 1 TO1.75
F-22 FOOTER P-1
F-5 FOOTERS 5-J, 5-H AND 5-G
F-7FOOTERS 4-L, 4-K AND 4-J
ONLY