Permit: T06CM05164
Permit Details
Apply Date:
09/26/2006
Applicant:
DOMINIC MONACCHIO
Description:
NEW SCHOOL
Architects:
- CLUTTER, RICHARD JAMES
Contractors:
- TUCSON BUILDING AND REMODELING I
- TUCSON UNIFIED SCHOOL DIST #1 **C
Permit Reviews
Permit Number - T06CM05164
Permit Status: C of o
Permit Description: NEW SCHOOL
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/14/2008 | 3RD PARTY REVIEW-REVISION/OTHER | 05/01/2008 | COMPLETED |
| 04/23/2007 | POST 3RD PARTY REVIEW | 05/15/2007 | COMPLETED |
| 05/15/2007 | RESUBMITTAL - SITE | 08/03/2007 | COMPLETED |
| 05/15/2007 | RESUBMITTAL | 08/03/2007 | COMPLETED |
| 09/26/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 09/26/2006 | COMPLETED |
| 09/26/2006 | 3RD PARTY REVIEW-COMMERCIAL | 04/23/2007 | COMPLETED |
| 09/26/2006 | PLANS OK TO SUBMIT - SITE | 10/24/2006 | COMPLETED |
| 10/24/2006 | PLANS OK TO SUBMIT - SITE | 10/24/2006 | COMPLETED |
| 10/24/2006 | SITE | 05/15/2007 | COMPLETED |
| 12/27/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 12/27/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM05164
Permit Status: C of o
Permit Description: NEW SCHOOL
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/26/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM05164
Permit Description: NEW SCHOOL
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2007 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* 1. 2 1/2" PVC YARDWATER FROM BUILDING TO AS INITIALED ON SITE UTILITY PLAN - OK TO COVER |
| 11/06/2007 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 11/15/2007 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* OK TO POUR OK 3/0 TO REBAR |
| 11/27/2007 | ELECTRIC - UNDERGROUND | RJIROUDE | Approved | IVRS - Inspection :* 1) OK 90 ? STUBS NORTH WEST SIDE OF BLDG |
| 12/07/2007 | STEM WALL/RETAINING WALL | JBURGE | Approved | IVRS - Inspection :* |
| 12/18/2007 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* FOOTINGS NORTH WALL OF #158, INTERIOR FOOTING #158 OK TO POUR |
| 12/31/2007 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK 3RD LIFT EAST 1. TIGHTEN LOOSE FITTINGS |
| 12/31/2007 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* 90' + RISER OF 4" SDR INSTALLED AT 2% + WILL AIR TEST AFTER COVERING |
| 12/31/2007 | REINFORCED MASONRY PRE-GROUT | IVR USER | Approved | IVRS - RI canceled |
| 12/31/2007 | ELECTRIC - INTERMEDIATE | IVR USER | Approved | IVRS - RI canceled |
| 03/03/2008 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR REMAINDER OF SLABS |
| 03/21/2008 | FRAMING | JBURGE | Approved | IVRS - Inspection :* WALLS; BATHROOM CEILINGS & SOFFITS |
| 06/02/2008 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* ALL RESTROOM CEILINGS COMPLETE -- OK TO TAPE |
| 06/26/2008 | TEP CLEARANCE - PM | JWEATHER | Approved | CEC CLEARED PER R. HOLLANDER |
| 06/27/2008 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 06/30/2008 | TEP CLEARANCE - AM | BFLORES | Approved | TMPP PER R.HOLLANDER (TO MAINS ONLY) |
| 07/22/2008 | PLUMBING - ABOVE CEILING | BBENEDON | Approved | IVRS - Inspection :* |
| 07/23/2008 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR REMAINING CEILING TILES |
| 07/25/2008 | ELECTRIC - ABOVE CEILING | RJIROUDE | Approved | IVRS - Inspection :* |
| 07/28/2008 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |
| 07/29/2008 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* COMPLETE WH VENTING FOR GAS CLEARANCE |
| 08/06/2008 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 08/06/2008 | ELECTRIC - CONSTRUCTION POWER | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/06/2008 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/06/2008 | ELECTRIC - OUTDOOR LIGHTING | RJIROUDE | Approved | IVRS - Inspection :* |
| 08/06/2008 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 08/07/2008 | PLUMBING - PRE SLAB | BBENEDON | Approved | |
| 08/07/2008 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* 1) SECURE EXTERIOR HBS, SHOULD HBS BE VANDAL PROOF ? 2) RM 113 CORRECT KINK IN CONDENSATE DRAIN |
| 08/07/2008 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 08/07/2008 | NPPO - FINAL | ACONNOR | Approved | |
| 08/07/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 08/21/2008 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 08/21/2008 | OUTDOOR LIGHTING FINAL | RJIROUDE | Approved | |
| 08/21/2008 | ELECTRIC - FINAL | RJIROUDE | Approved | IVRS - Inspection :* |
| 09/04/2008 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* PENDING FIRE RE-INSPECTION -- TRADES COMPLETE |
| 09/04/2008 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
| 09/04/2008 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
| 09/04/2008 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
| 09/05/2008 | FIRE - ALARM FINAL | EDESCHAI | Approved | |
| 09/05/2008 | FIRE SPKLR - FINAL | EDESCHAI | Approved | |
| 09/05/2008 | FIRE - FINAL | EDESCHAI | Approved | |
| 09/26/2008 | PERMIT FINALED | LJACKSON | Approved | |
| 09/26/2008 | ENGINEERING - FINAL | JBRUCKME | Approved |