Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/09/2008 | PLUMBING - SEWER HCS CONNECT | Approved | IVRS - Inspection :* | |
| 01/07/2008 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* AIR TEST OK |
|
| 01/03/2008 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* 4" SDR TO 20' FROM BUILDING OK SUBJECT TO PRESSURE TEST |
|
| 12/31/2007 | PLUMBING - SEWER HCS CONNECT | Partial Approval | IVRS - Inspection :* 90' + RISER OF 4" SDR INSTALLED AT 2% + WILL AIR TEST AFTER COVERING |
|
| 12/28/2007 | PLUMBING - SEWER HCS CONNECT | Not ready for Inspection | IVRS - Inspection :* PLAN REVISION SHOWS 4" INSTALL REDUCER AT MANHOLE |
|
| 12/27/2007 | PLUMBING - SEWER HCS CONNECT | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) MET WITH BRYON TBR CONST. AND ENGINEERING, ? WITH STRUCT CONST. PLAN CALLS FOR 4" PIPING 8" IS INSTALLED NOT PER APPROVED PLAN PLANS GO TO ROBERT SHERRY C OF T PLAN CHECK. MADE ALL PARTIES AWARE OF NEED FOR PRE-CONSTRUCTION MEETING AND REQUIREMENTS |