Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2008 | BUILDING PRE-SLAB | Approved | IVRS - Inspection :* OK TO POUR REMAINDER OF SLABS |
|
| 02/14/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* CLASSROOMS #151 & #153 OK TO POUR |
|
| 02/12/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* CLASSROOM #147 |
|
| 02/11/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* MEDIA CENTER EXTERIOR WALL - LINE B/8 TO E/4.5 @ 20'8" OK TO GROUT |
|
| 02/07/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* ROOMS #117, 118, 119, 120, 121, 128, 129, 130, 130A, 134, 139, 137, 138; OK TO POUR |
|
| 02/06/2008 | BUILDING PRE-SLAB | Cancelled | IVRS - RI canceled | |
| 01/31/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* ROOMS #122, 123, 124, 126, 127 -- OK TO POUR |
|
| 01/30/2008 | BUILDING PRE-SLAB | Partial Approval | IVRS - Inspection :* MAIN ADMIN. AREA, CLASSROOMS #110, 114 -- OK TO POUR PROGRESS AREAS |
|
| 01/03/2008 | BUILDING PRE-SLAB | Not ready for Inspection | IVRS - Inspection :* |