Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Apply Date:
05/19/2003
Applicant:
MICHAEL H MAHONEY
Description:
NEW:HOTEL
Contractors:
  • EBCO GENERAL CONTRACTOR LTD

Permit Reviews

Permit Number - T03CM02424
Permit Status: C of o
Permit Description: NEW:HOTEL
Start Date Submittal Complete Date Status  
01/12/2004 RESUBMITTAL 02/09/2004 COMPLETED Review Details
01/12/2004 SITE 02/09/2004 COMPLETED Review Details
02/10/2004 RESUBMITTAL 02/12/2004 COMPLETED Review Details
03/10/2004 3RD PARTY REVIEW-REVISION/OTHER 05/17/2004 COMPLETED Review Details
03/25/2004 3RD PARTY REVIEW-REVISION/OTHER-2ND 03/29/2004 COMPLETED Review Details
04/13/2004 3RD PARTY REVIEW-REVISION/OTHER-2ND 04/27/2004 COMPLETED Review Details
05/13/2004 3RD PARTY REVIEW-REVISION/OTHER-2ND 05/17/2004 COMPLETED Review Details
05/19/2003 PLANS OK TO SUBMIT - 3RD PARTY 05/20/2003 COMPLETED Review Details
05/20/2003 3RD PARTY REVIEW-COMMERCIAL 06/06/2003 COMPLETED Review Details
06/09/2004 3RD PARTY REVIEW-REVISION/OTHER 06/21/2004 COMPLETED Review Details
06/30/2003 3RD PARTY REVIEW-COMMERCIAL 07/07/2003 COMPLETED Review Details
07/21/2003 3RD PARTY REVIEW-COMMERCIAL 07/25/2003 COMPLETED Review Details
08/04/2003 3RD PARTY REVIEW-COMMERCIAL 01/12/2004 COMPLETED Review Details
08/29/2003 SITE 01/12/2004 COMPLETED Review Details
09/09/2004 3RD PARTY REVIEW-REVISION/OTHER 09/13/2004 COMPLETED Review Details
10/06/2004 3RD PARTY REVIEW-REVISION/OTHER 10/06/2004 COMPLETED Review Details
10/06/2004 POST 3RD PARTY REVIEW 10/18/2004 COMPLETED Review Details
10/13/2004 3RD PARTY REVIEW-REVISION/OTHER 10/18/2004 COMPLETED Review Details
10/19/2004 3RD PARTY REVIEW-REVISION/OTHER 11/02/2004 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T03CM02424
Permit Status: C of o
Permit Description: NEW:HOTEL
Total Outstanding Activity Conditions - 1
Date Name
05/19/2003 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T03CM02424
Permit Description: NEW:HOTEL
Total Completed Inspections - 45
Date Description Inspector Results Comments
04/08/2004 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection 0000*
04/14/2004 TEP CLEARANCE - AM JKOZUCH Approved TEMPORARY CONSTRUCTION POLE
04/23/2004 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection :*
04/26/2004 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
07/07/2004 EXT METAL CLIPS/EXT SHEATHING LHANLY Approved IVRS - Inspection :* OK TO WRAP
09/02/2004 ELECTRIC - UFER JORTA Approved IVRS - Inspection :*
09/13/2004 ROOF NAILING LHANLY Approved IVRS - Inspection :*
09/15/2004 ELECTRIC - TEMP POWER FOR TEST JORTA Approved IVRS - Inspection :*/ 1) AS PREVIOUSLY STIPULATED
09/23/2004 FRAMING LHANLY Approved IVRS - Inspection :*
09/23/2004 STUCCO MESH LHANLY Approved IVRS - Inspection :*
10/01/2004 REINFORCED MASONRY PRE-GROUT LHANLY Approved IVRS - Inspection :*APPROVED.
10/19/2004 ELECTRIC - CONSTRUCTION POWER JORTA Approved
10/19/2004 ELECTRIC - TEMPORARY POLE JORTA Approved
10/19/2004 ELECTRIC - CABLE DROP JORTA Approved
10/19/2004 ELECTRIC - INTERMEDIATE JORTA Approved
10/19/2004 ELECTRIC - UNDERGROUND JORTA Approved
10/19/2004 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection :*/INSPECTED 3/25/04 & 10/5/04 LETTER FROM ENGINEER TURNED IN
10/19/2004 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*/INSPECTED AS PARTIALS
10/22/2004 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
11/03/2004 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection :*/OK TO COMPLETE SMALL AREAS & TAPE
11/03/2004 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection :*
11/03/2004 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection :*
11/05/2004 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*/CORRECTIONS MADE
11/18/2004 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*/OK TO CLOSE SHAFT C=3 4TH FLOOR. C-6 4TH FLOOR PROVIDE ACCESS PANEL. OK 3RD FLOOR SOFFIT OK TO CLOSE WATER HEATER SHAFT 2ND FLOOR. OK SHAFT WATER HEATER VENTS? RTH FLOOR
11/22/2004 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
11/23/2004 PLUMBING - GAS PRESSURE TEST RRICH Approved IVRS - Inspection :*
11/24/2004 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
11/24/2004 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
11/24/2004 FIRE SPKLR - UG, PIPING, HYDRO CSCHULTZ Approved
11/24/2004 FIRE - ALARM FINAL CSCHULTZ Approved
11/29/2004 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*/RECIVED (1) COPY BACTERIA REPORT (3) BACKFLOW CERTIFICATIONS (1) PDEQ CERTIFICATION (1) VERIFICATION OF GRADE FOR SITE SEWER
11/30/2004 FIRE - FINAL LTHOMAS Approved OK FOR C OF O
12/01/2004 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*/OK FOR FINAL C/O
12/01/2004 LANDSCAPE - FINAL ACONNOR Approved
12/01/2004 NPPO - FINAL ACONNOR Approved
12/02/2004 BUILDING - FINAL LHANLY Approved
12/02/2004 U VALUE FOR WINDOW LHANLY Approved
12/02/2004 PERMIT FINALED TACHONG Approved
12/02/2004 ENGINEERING - FINAL JSALINE Approved PER PHONE CALL
12/02/2004 FIRE SPKLR - FINAL LTHOMAS Approved BY PHONE
12/02/2004 SIGN - FINAL JYBARRA Approved
12/02/2004 ELECTRIC - ABOVE CEILING RMAJUTA Approved
12/02/2004 ELECTRIC - FINAL RMAJUTA Approved OK FOR C OF O
12/02/2004 ELECTRIC - TEMPORARY SERVICE RMAJUTA Approved
12/02/2004 RIGHT OF WAY - FINAL DLEE Approved OK FOR C OF O

Documents

File Name Document Type  
STRUCCALC.TIF DOCUMENTS VIEW
TRUSSDESIGN_01.TIF DOCUMENTS VIEW
TRUSSDESIGN_02.TIF DOCUMENTS VIEW
None DOCUMENTS VIEW
C OF O_12-02-2004.TIF CERT OF OCC VIEW