11/23/2004 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* | |
11/02/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :*/GAS AT HOTEL IS COMPLETE AND ONLY FINAL OR BONDING REQUIRED FOR GAS CARD. GAS AT GATE HOUSE IS COMPLETE AND ONLY FINAL OR BONDING REQUIRED FOR GAS CARD. POOL EQUIP AREA REQUIRES COMPLETION OF GAS PIPING AND TESTING. (OR TEMP C OF O FOR STOCKING) 3RD FLOOR FIXTURES IN ROOMS OK. | |
11/01/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :*/ 1) GATE HOUSE 15 PSI TEST TYO WATER HEATERS AND DRYERS OK 2) NEED CORRECT INSTALLATION OF GAS REGULATOR FOR THIS AND COMPLETETION OF POOL EQUIPMENT GAS PIPING 2) INSTALL GAS PIPING TO HOTEL WATER HEATERS PER YOUR CITY APPROVED PLAN | |
10/19/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :*/NEED TEST AT POOL EQUIP STUB UP T POOL EQUIP AND TO SEE ALL REGULATORS & NEED TO SEE GATE HOUSE WATER HEATERS & HOTEL WATER HEATERS | |
10/05/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | MED. PRESSURE LINE OKE AT 60 PSI AIR | |
08/13/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* 14 psi TEST IS OK. INSPECTED GAS LINES & PRESSURE TO 3RD & 4TH FLOOR FIREPLACES. OK TO COVER. | |
08/12/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* | |
07/26/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* | |
07/22/2004 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
07/19/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :* | |
07/16/2004 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
07/08/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :*/ 1) GAS PIPING 1ST FLOOR EXTERIOR TO ROOM 234, 232 AND 223 3/4" PIPE ? PSI AIR TEST PARTIAL APPROVAL | |
05/14/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :*/ 60 PSI AIR TEST ON 3" SERVICE MAIN FROM METER TO 1¼" DISTRIBUTED TO ALL BLD STUB UPS PARTIAL APPROVAL. 3" RISER IS A CSA LISTED DEVICE. | |
05/06/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection : See detailed listing on site.| 999* |
|
04/30/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :*/ 1) 60 PSI AIR TEST ON 5 PSI SYSTEM INSTALLED AS P.E. PIPING PER PLAN LOOPED PAST 2 1/2" SUPPLY BACK TO METER 2) WILL NEED INFORMATIONPER NOTE ON 4/26/04 INSPECTION 3) WILL NEED TO SEE 2 1/2" PIPING INSTALLED AND TESTED | |
04/28/2004 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :*/ 1) 60 PSI TEST AT TIME OF INSPECTION SHALL BE IN PLACE | |
04/26/2004 | PLUMBING - GAS PRESSURE TEST | Partial Approval | IVRS - Inspection :*/ 60 PSI AIR TEST ON 5 PSI SYSTEM FROM SOUTH WEST 7" STUB UP AT FIRE PLACE, 1¼ STUB UP AT SOUTH WTR HTR AREA, CONTINUES 1¼" TO MY INITIAL ON MEP 1.0 - PARTIAL APPROVAL PENDING LETTER FROM ENGINEER STATING P.E. PIPING IS OK. IN PLACE OF BLK I.P. OR CORRUGATED STAINLESS STEEL. |