Permit: T21CM00864
Permit Details
Apply Date:
01/27/2021
Applicant:
Erin Dick
Description:
New Hotel
Permit Reviews
Permit Number - T21CM00864
Permit Status: Complete
Permit Description: New Hotel
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/27/2021 | COMMERCIAL - NEW | 03/18/2021 | COMPLETED |
04/30/2022 | REVISION - - 2ND | 05/18/2022 | COMPLETED |
05/24/2022 | REVISION - - 3RD | 06/07/2022 | COMPLETED |
06/28/2022 | REVISION - - 3RD | 07/12/2022 | COMPLETED |
07/07/2021 | RESUBMITTAL | 08/06/2021 | COMPLETED |
09/28/2021 | RESUBMITTAL | 10/07/2021 | COMPLETED |
11/22/2021 | REVISION - - 1ST | 12/07/2021 | COMPLETED |
04/12/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.3 | 04/20/2023 | APPROVED |
04/03/2023 | BUILDING DEFERRED SUBMITTAL REVIEW v.2 | 04/06/2023 | REQUIRES RESUBMIT |
12/08/2022 | BUILDING DEFERRED SUBMITTAL REVIEW v.1 | 03/14/2023 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - T21CM00864
Permit Status: Complete
Permit Description: New Hotel
Total Outstanding Activity Conditions - 2
Date | Name |
---|---|
07/20/2021 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
07/20/2021 | SPECIAL INSPECTION IS REQUIRED FOR EIFS |
Conditions
Permit Number - T21CM00864
Permit Status: Complete
Permit Description: New Hotel
Date | Description | Comments |
---|---|---|
07/20/2021 | ROOF TRUSSES MUST BE APPROVED PRIOR TO FRAMING INSPECTION (P2I) | |
07/20/2021 | SPECIAL INSPECTION FORMS AND REPORTS REQUIRED PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANCY. | |
07/20/2021 | SPECIAL INSPECTION FOR CONCRETE IS REQUIRED.. | |
07/20/2021 | SPECIAL INSPECTION FOR SITE PREPARATION IS REQUIRED. | |
07/20/2021 | SPECIAL INSPECTION FOR FOUNDATION/EXCAVATION IS REQUIRED. | |
07/20/2021 | SHOP DRAWINGS REQUIRED FOR STEEL STAIRS | |
07/20/2021 | SPECIAL INSPECTION IS REQUIRED FOR POST INSTALL ANCHORS |
Outstanding Inspections
Permit Status: Complete
Permit Number: T21CM00864
Permite Description: New Hotel
Total Outstanding Inspections - 23
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/26/2022 | COT - HCBU - Interior Shear Bracing | N/A | Not Ready | |
12/01/2022 | COT - HCPL - Plumbing Intermediate | N/A | Partial Pass | partial approval for first floor common area lobby |
10/26/2022 | COT - HCPL - Gas Pressure Test | N/A | Not Ready | |
01/18/2023 | COT - BULD - SWG Clearance | N/A | Not Ready | |
01/17/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | N/A | Not Ready | |
01/17/2023 | COT - HCEL - Electrical Above Ceiling | N/A | Not Ready | |
01/17/2023 | COT - HCME - Mechanical Above Ceiling | N/A | Not Ready | |
01/17/2023 | COT - HCBU - Building Above Ceiling | N/A | Not Ready | |
01/17/2023 | COT - HCPL - Plumbing Above Ceiling | N/A | Not Ready | |
02/28/2023 | COT - HCME - Kitchen Hood | N/A | Not Applicable | |
10/26/2022 | COT - HCBU - Exterior Clips/Sheathing | N/A | Not Ready | |
10/26/2022 | COT - HCEL - Grounding/Bonding | N/A | Not Ready | |
10/26/2022 | COT - HCBU - Excavation/Rebar/Zoning | N/A | Not Ready | |
10/26/2022 | COT - HCEL - Electrical Underground | N/A | Not Ready | |
10/26/2022 | COT - HCBU - Framing | N/A | Not Ready | |
10/26/2022 | COT - HCME - Mechanical Intermediate | N/A | Not Ready | |
10/26/2022 | COT - HCEL - Outdoor Lighting | N/A | Not Ready | |
10/26/2022 | COT - HCEL - Electrical Intermediate | N/A | Not Ready | |
11/07/2022 | COT - FCON - Sprinkler - Final | N/A | Not Ready | No message was on permit to contact the general contractor could not find them on site. Subs did not call in their permit. 11/7/22 - This was for OH/Hydro of First Floor. Not ready for a Sprinkler Final. |
10/26/2022 | COT - HCPL - Sewer | N/A | Not Ready | |
10/26/2022 | COT - HCME - Mechanical Final | N/A | Not Ready | |
03/06/2023 | COT - HCEL - Electrical Final | N/A | Partial Pass | |
COT - FCON - Fire - Final | N/A | Not Ready | Still need to finish punch list items. |
Completed Inspections
Permit Status: Complete
Permit Number: T21CM00864
Permit Description: New Hotel
Total Completed Inspections - 41
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/28/2022 | COT - HCPL - Rough Soil | Passed | {Activity date: 01/28/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved} ; {Activity date: 01/27/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Under foundation waste lines installed and tested from (GL 8-21) ok to backfill progress areas. } ; {Activity date: 01/20/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Sanitary & Grease lines installed and tested from GL-1-8 OK to backfill and prep slab.} |
|
03/08/2022 | COT - HCBU - Masonry Pregrout | Passed | {Activity date: 03/08/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Approved, final lift for CMU Elevator shaft complete.} ; {Activity date: 03/07/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 12TH lift CMU Elevator shaft @ 48’ ok to grout.} ; {Activity date: 03/04/2022; Status: Cancelled; Inspector: TGAUSP; Comment: Entered by VVERA1 - cancelled by Contractor due to wind} ; {Activity date: 03/02/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - No inspection required today see previous notes.} ; {Activity date: 03/01/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, 8TH LIFT CMU elevator shaft ok to grout and proceed.} ; {Activity date: 02/28/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 7th lift CMU Elevator shaft ok for grout.} ; {Activity date: 02/25/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial.- 5th & 6th lift of CMU @ Elevator shaft ok to grout and proceed.} ; {Activity date: 02/23/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, 4TH lift CMU @Elevator shaft ok to grout and proceed.} ; {Activity date: 02/22/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 3RD LIFT for CMU ELEVATOR SHAFT WALLS OK for grout.} ; {Activity date: 02/18/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - Partial for 2nd lift (10’-4” from pit) of the CMU elevator shaft, okay to grout} ; {Activity date: 02/09/2022; Status: Not ready for Inspection; Inspector: DMUNIZ; Comment: Entered by RSALDAT1 - Not Ready} ; {Activity date: 01/20/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, first lift for elevator shaft CMU walls ok to grout and proceed.} | |
03/14/2022 | COT - HCPL - Backwater Valve | Passed | {Activity date: 03/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} | |
03/14/2022 | COT - HCPL - Plumbing Progress | Passed | {Activity date: 03/14/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 03/07/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, Grease interceptor installed and tested ok to backfill.} ; {Activity date: 02/01/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 3” main line stubbed in foundation out of slab under test and ok to backfill.} | |
03/16/2022 | COT - HCBU - Preslab | Passed | {Activity date: 03/16/2022; Status: Approved; Inspector: TGAUSP; Comment: Entered by VVERA1 - Approved} ; {Activity date: 03/15/2022; Status: Not ready for Inspection; Inspector: TGAUSP; Comment: Entered by NGARCIA3 - NR} | |
05/27/2022 | COT - HCBU - Roof Nailing | Passed | {Activity date: 05/27/2022; Status: Approved; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Approved} ; {Activity date: 05/13/2022; Status: Not ready for Inspection; Inspector: ESTEVENS; Comment: Entered by VVERA1 - Not ready.} ; {Activity date: 04/04/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, CANOPY and second floor deck nailing ok to proceed.} ; {Activity date: 03/30/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by NGARCIA3 - Partial, continued progress for 2nd floor deck nailing ok to proceed.} ; {Activity date: 03/16/2022; Status: Partial Approval; Inspector: TGAUSP; Comment: Entered by VVERA1 - Partial for 2nd floor deck on the south side and continued on north side up to elevator shaft.} ; {Activity date: 03/08/2022; Status: Partial Approval; Inspector: DMUNIZ; Comment: Entered by VVERA1 - Partial, 2nd floor deck nailing from GL 10-21 North of corridor ok to proceed.} | |
06/01/2022 | COT - FCON - Underground Flush | Passed | {Activity date: 06/01/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } | |
06/01/2022 | COT - FCON - Underground Pressure | Passed | {Activity date: 06/01/2022; Status: Approved; Inspector: CBASALDUA; Comment: Entered by CBASALD1 - } | |
08/15/2022 | COT - HCEL - Construction Power | Passed | {Activity date: 08/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - Approved ok for clearance ECO } |
|
08/15/2022 | BULD - Electrical Clearance | Passed | {Activity date: 08/15/2022; Status: Approved; Inspector: WGALLAGHER; Comment: Entered by VVERA1 - CODE ECO} | |
11/09/2022 | COT - HCPL - Plumbing Roof Drains | Passed | ||
11/22/2022 | COT - HCBU - Interior Shear Bracing | Passed | ||
12/13/2022 | COT - HCPL - Plumbing Intermediate | Passed | partial approval for meeting room above hard lids | |
01/04/2023 | COT - HCPL - Gas Pressure Test | Passed | ||
01/13/2023 | COT - HCME - Mechanical Progress | Passed | ||
01/13/2023 | COT - HCBU - Building Progress | Passed | ||
01/13/2023 | COT - HCEL - Electrical Progress | Passed | ||
01/27/2023 | COT - HCBU - Firewall/Fire Barrier/Firestop | Passed | All penetrations through firewall are properly fire caulked. | |
01/27/2023 | COT - HCEL - Electrical Above Ceiling | Passed | All J-boxes are labeled, all penetration through firewalls are fire caulked, all conduit is properly supported, all fire alarm J-boxes & conduits are painted red and labeled properly. | |
01/27/2023 | COT - HCME - Mechanical Above Ceiling | Passed | All mechanical ductwork is properly supported on the first floor corridor, meeting rooms, and break rooms. air supply and return registers are installed in grid ceiling. okay to install ceiling tiles. | |
01/27/2023 | COT - HCBU - Building Above Ceiling | Passed | First floor corridors, break rooms, and meeting rooms are complete. Okay to install ceiling tiles. | |
01/27/2023 | COT - HCPL - Plumbing Above Ceiling | Passed | All plumbing pipes and fire sprinkler pipes are properly supported to plumbing rack. Okay to install ceiling tile. | |
03/01/2023 | COT - HCBU - Exterior Clips/Sheathing | Passed | ||
03/01/2023 | COT - HCEL - Grounding/Bonding | Passed | ||
03/01/2023 | COT - HCBU - Excavation/Rebar/Zoning | Passed | ||
03/01/2023 | COT - HCEL - Electrical Underground | Passed | ||
03/01/2023 | COT - HCBU - Framing | Passed | ||
03/01/2023 | COT - HCME - Mechanical Intermediate | Passed | ||
03/01/2023 | COT - HCEL - Outdoor Lighting | Passed | ||
03/01/2023 | COT - HCBU - Sustainability | Passed | ||
03/02/2023 | COT - HCEL - Electrical Intermediate | Passed | ||
04/05/2023 | COT - FCON - Sprinkler - Final | Passed | ||
04/05/2023 | COT - FCON - Alarm - Final | Passed | ||
03/03/2023 | COT - HCPL - Sewer | Passed | ||
03/06/2023 | COT - HCME - Mechanical Final | Passed | ||
03/08/2023 | COT - HCPL - Plumbing Final | Passed | Plumbing is complete to all rooms and common areas. | |
03/14/2023 | COT - HCEL - Electrical Final | Passed | ||
03/30/2023 | COT - HCBU - Building Final | Passed | ||
04/13/2023 | ENGR Engineering Final | Passed | ||
04/13/2023 | COT - ENGR - Site - Assurance Release | Passed | ||
04/13/2023 | COT - FCON - Fire - Final | Passed |