| 10/26/2022 |
COT - HCPL - Plumbing Intermediate |
|
Not Ready |
|
| 10/12/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Not ready for Inspection |
Entered by VVERA1 - Not ready
|
| 10/03/2022 |
COT - HCPL - Plumbing Intermediate |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Room Units on Level #1. |
| 09/30/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Partial Approval |
Entered by VVERA1 - Partial approval for 4th and 2nd floor elevator room ok for drywall
|
| 09/27/2022 |
COT - HCPL - Plumbing Intermediate |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. All copper piping in building is under test and maintained constant pressure: all room units, kitchen and public restrooms. |
| 09/23/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Partial Approval |
Entered by VVERA1 - Partial approval 3rd floor corridor ok to drywall
|
| 09/21/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Partial Approval |
Entered by VVERA1 - Partial approval above 3rd floor corridor hard lids
And rooms 2030 t0 2080 and 3rd floor storage |
| 09/20/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Cancelled |
Entered by NGARCIA3 - Inspection canceled by contractor |
| 09/06/2022 |
COT - HCPL - Plumbing Intermediate |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. Above ceiling.
|
| 09/02/2022 |
COT - HCPL - Plumbing Intermediate |
JBURGE |
Not ready for Inspection |
Entered by VVERA1 - Not ready. Contractor cancelled |
| 09/01/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Partial Approval |
Entered by NGARCIA3 - Partial approval for 4th floor stock room |
| 08/30/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Partial Approval |
Entered by NGARCIA3 - Partial approval for 4th floor data room only |
| 08/24/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Partial Approval |
Entered by VVERA1 - Partial approval 2092 to 2110 and 2004 to 2021
|
| 08/23/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Partial Approval |
Entered by NGARCIA3 - Partial approval for Rooms 2021 through 2089 |
| 08/22/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Not ready for Inspection |
Entered by VVERA1 - Not ready
|
| 08/16/2022 |
COT - HCPL - Plumbing Intermediate |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Level 2. DWV ONLY. 2039, 2077, 2036, 2033, 2080, 2027, 2030, 2086, 2083, 2089, 2092, 2095, 2098. 2018, 2010, 2013, 2101, 2104, 2004, 2007, 2107, 2110. |
| 08/16/2022 |
COT - HCPL - Plumbing Intermediate |
ESTEVENS |
Partial Approval |
Entered by NGARCIA3 - Partial. Level 2. Units 2054, 2059. 2062, 2051, 2048, 2065, 2068, 2045. 2071, 2042, 2074. |
| 08/15/2022 |
COT - HCPL - Plumbing Intermediate |
WGALLAGHER |
Cancelled |
Entered by VVERA1 - Inspection canceled
|
| 08/08/2022 |
COT - HCPL - Plumbing Intermediate |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Level #3; bathroom tub areas: Room units: 3106, 3006, 3103, 3082, 3079, 3076. |
| 07/29/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, ALL DWV & Potable water lines tested and approved. |
| 07/27/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - PARTIAL, DWV test for west guest rooms stacks from 1st-4th floor, & grease and laundry vent. Air test for potable water lines approved. Two more stacks required for test. |
| 07/22/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - Partial, 12 Stack risers & roof drains for East building 1st-4th floor DWV & Potable water lines all tested. |
| 07/20/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - PARTIAL, DWV & POTABLE WATER TEST FOR 12 STACKS EAST 1ST FLOOR -ROOFTOP OK TO PROCEED
|
| 07/15/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, continued progress for 3rd floor guest rooms ok to proceed. DWV & potable water line test for 5th stack and roof drains . |
| 07/13/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Correction Required |
Entered by NGARCIA3 - corrections required, 2nd & 3rd floor tubs leaking re test and call in inspections. |
| 07/12/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - Partial, 3rd floor, following guest room tubs have been tested and ok to proceed. (3073, 3067,3064,3061). |
| 07/11/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, 3rd floor guest rooms 3034,3076, 3038,3041,3070,3073,3064,3067,3047,3044,3058,3061,3053,3050. 4TH floor guest rooms 4085,4082,4029,4026. All ok to Sheetrock. |
| 07/08/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - PARTIAL, DWV TEST FOR 1ST-4TH FLOOR FOR 8 R00MS WEST OF PREVIOUS PROGRESS OK TO PROCEED.
|
| 07/01/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, NO INSPECTION REQUIRED SEE PREVIOUS NOTES. |
| 06/28/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by NGARCIA3 - PARTIAL, FOLLOWING ROOMS AND DWV STACKS FROM 1ST TO 4TH FLOOR TESTED AND APPROVED. (4038, 4041, 4070, 4073) |
| 06/24/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - PARTIAL, EAST CORRIDOR 8 ROOMS WEST OF STAIRWELL 1st,2nd,3rd,4th floor OK TO INSULATE & SHEETROCK GUEST ROOMS |
| 06/20/2022 |
COT - HCPL - Plumbing Intermediate |
RCHANDLER |
Partial Approval |
Entered by VVERA1 - PARTIAL, ROOM 4601 OK TO PROCEED.
|
| 06/15/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Partial Approval |
Entered by VVERA1 - PARTIAL, INSPECTION FOR ROOM 4601, PROVIDE DWV AND POTABLE WATER TEST. |
| 03/22/2022 |
COT - HCPL - Plumbing Intermediate |
DMUNIZ |
Not ready for Inspection |
Entered by VVERA1 - Not Ready |
| 11/03/2022 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
partial approval for first floor guest rooms 149-181 |
| 11/04/2022 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
partial approval for all first floor guest rooms |
| 11/09/2022 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
First floor all public areas except buffet kitchen meeting rooms ice machine alcove |
| 11/29/2022 |
COT - HCPL - Plumbing Intermediate |
|
Re-inspection required |
|
| 12/01/2022 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
partial approval for first floor common area lobby |
| 12/13/2022 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
partial approval for meeting room above hard lids |