Inspection Status: Not Ready

Inspection History: COT - HCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
10/26/2022 COT - HCPL - Plumbing Intermediate  Not Ready
10/12/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Not ready for Inspection Entered by VVERA1 - Not ready
10/03/2022 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by VVERA1 - Partial. Room Units on Level #1.
09/30/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Partial Approval Entered by VVERA1 - Partial approval for 4th and 2nd floor elevator room ok for drywall
09/27/2022 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by NGARCIA3 - Partial. All copper piping in building is under test and maintained constant pressure: all room units, kitchen and public restrooms.
09/23/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Partial Approval Entered by VVERA1 - Partial approval 3rd floor corridor ok to drywall
09/21/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Partial Approval Entered by VVERA1 - Partial approval above 3rd floor corridor hard lids And rooms 2030 t0 2080 and 3rd floor storage
09/20/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Cancelled Entered by NGARCIA3 - Inspection canceled by contractor
09/06/2022 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by NGARCIA3 - Partial. Above ceiling.
09/02/2022 COT - HCPL - Plumbing Intermediate  JBURGE Not ready for Inspection Entered by VVERA1 - Not ready. Contractor cancelled
09/01/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Partial Approval Entered by NGARCIA3 - Partial approval for 4th floor stock room
08/30/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Partial Approval Entered by NGARCIA3 - Partial approval for 4th floor data room only
08/24/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Partial Approval Entered by VVERA1 - Partial approval 2092 to 2110 and 2004 to 2021
08/23/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Partial Approval Entered by NGARCIA3 - Partial approval for Rooms 2021 through 2089
08/22/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Not ready for Inspection Entered by VVERA1 - Not ready
08/16/2022 COT - HCPL - Plumbing Intermediate  ESTEVENS Partial Approval Entered by NGARCIA3 - Partial. Level 2. DWV ONLY. 2039, 2077, 2036, 2033, 2080, 2027, 2030, 2086, 2083, 2089, 2092, 2095, 2098. 2018, 2010, 2013, 2101, 2104, 2004, 2007, 2107, 2110.
08/16/2022 COT - HCPL - Plumbing Intermediate  ESTEVENS Partial Approval Entered by NGARCIA3 - Partial. Level 2. Units 2054, 2059. 2062, 2051, 2048, 2065, 2068, 2045. 2071, 2042, 2074.
08/15/2022 COT - HCPL - Plumbing Intermediate  WGALLAGHER Cancelled Entered by VVERA1 - Inspection canceled
08/08/2022 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by VVERA1 - Partial. Level #3; bathroom tub areas: Room units: 3106, 3006, 3103, 3082, 3079, 3076.
07/29/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by NGARCIA3 - PARTIAL, ALL DWV & Potable water lines tested and approved.
07/27/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by VVERA1 - PARTIAL, DWV test for west guest rooms stacks from 1st-4th floor, & grease and laundry vent. Air test for potable water lines approved. Two more stacks required for test.
07/22/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by VVERA1 - Partial, 12 Stack risers & roof drains for East building 1st-4th floor DWV & Potable water lines all tested.
07/20/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by VVERA1 - PARTIAL, DWV & POTABLE WATER TEST FOR 12 STACKS EAST 1ST FLOOR -ROOFTOP OK TO PROCEED
07/15/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by NGARCIA3 - PARTIAL, continued progress for 3rd floor guest rooms ok to proceed. DWV & potable water line test for 5th stack and roof drains .
07/13/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Correction Required Entered by NGARCIA3 - corrections required, 2nd & 3rd floor tubs leaking re test and call in inspections.
07/12/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by NGARCIA3 - Partial, 3rd floor, following guest room tubs have been tested and ok to proceed. (3073, 3067,3064,3061).
07/11/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by NGARCIA3 - PARTIAL, 3rd floor guest rooms 3034,3076, 3038,3041,3070,3073,3064,3067,3047,3044,3058,3061,3053,3050. 4TH floor guest rooms 4085,4082,4029,4026. All ok to Sheetrock.
07/08/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by VVERA1 - PARTIAL, DWV TEST FOR 1ST-4TH FLOOR FOR 8 R00MS WEST OF PREVIOUS PROGRESS OK TO PROCEED.
07/01/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by NGARCIA3 - PARTIAL, NO INSPECTION REQUIRED SEE PREVIOUS NOTES.
06/28/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by NGARCIA3 - PARTIAL, FOLLOWING ROOMS AND DWV STACKS FROM 1ST TO 4TH FLOOR TESTED AND APPROVED. (4038, 4041, 4070, 4073)
06/24/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by VVERA1 - PARTIAL, EAST CORRIDOR 8 ROOMS WEST OF STAIRWELL 1st,2nd,3rd,4th floor OK TO INSULATE & SHEETROCK GUEST ROOMS
06/20/2022 COT - HCPL - Plumbing Intermediate  RCHANDLER Partial Approval Entered by VVERA1 - PARTIAL, ROOM 4601 OK TO PROCEED.
06/15/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Partial Approval Entered by VVERA1 - PARTIAL, INSPECTION FOR ROOM 4601, PROVIDE DWV AND POTABLE WATER TEST.
03/22/2022 COT - HCPL - Plumbing Intermediate  DMUNIZ Not ready for Inspection Entered by VVERA1 - Not Ready
11/03/2022 COT - HCPL - Plumbing Intermediate  Partial Pass partial approval for first floor guest rooms 149-181
11/04/2022 COT - HCPL - Plumbing Intermediate  Partial Pass partial approval for all first floor guest rooms
11/09/2022 COT - HCPL - Plumbing Intermediate  Partial Pass First floor all public areas except buffet kitchen meeting rooms ice machine alcove
11/29/2022 COT - HCPL - Plumbing Intermediate  Re-inspection required
12/01/2022 COT - HCPL - Plumbing Intermediate  Partial Pass partial approval for first floor common area lobby
12/13/2022 COT - HCPL - Plumbing Intermediate  Passed partial approval for meeting room above hard lids